FINAL REPORT ON THE PROJECT

“CONSTRUCTION OF RIGHT MARGINAL BUND TOWARDS KOT MITHAN SIDE”

Sponsoring Agency: NHA (National Highway Authority)


Executing Agency: Irrigation Department Government of Punjab

Project Background: NHA is constructing “SHAHEED BENAZIR BHUTTO BRIDGE” over


river Indus connecting Chachran Sharif district Rahim Yar Khan with
KotMithan district Rajanpur.

NHA vide letter No.15(37)/AD(Design)/NHA/10/304 has requested


Irrigation Research Institute Irrigation Department Government of
Punjab to carry out the model study of the SHAHEED BENAZIR
BHUTTO BRIDGE for a design discharge of 36,817 cumecs.

The IRI Lahore sent the Hydraulic Model Study Report No.IRI-1270
dated January, 25 2012 with their recommendation for final
location and length of the bridge.

The project envisaged the construction of a 1200 m long concrete


bridge, with approaches, and river training works. The scope of
work relating to river training works includes construction of guide
banks upstream and downstream of the bridge. According to the
model study the design flood of the proposed bridge as 36,817
cumecs, construction /raising of Right Marginal Bund on Kotmithan
side and raising and improvement of Minchin Bund (Left Marginal
Bund) including J-Spur No1&2 on upstream side and other Spurs on
downstream side have been included on the direction of Chief
Engineer D.G Khan and PRO Hydraulics IRI Lahore.

Sub Components:

 Bridge Length & Width 1200 m, 12.20 m


 Length of Guide Banks 4322 m
 Approach road towards Zahirpir on N-5 14.036 Km
 Toll Plaza with Admin Building 2 Nos
 Construction/Raising of Right Marginal Bund on KotMithan
Side
(22.4 Km)
 Raising and Improvement of Left Marginal Bund on Chichran
Side
(12.79 Km)

Page 1 of 6
Preparation of PC-1
of Alleged sub component:
Secretary Irrigation Department Punjab vide letter
No.473/PRO(H)/795-C dated.18-03-2016, directed PRO Hydraulic
and Chief Engineer D.G Khan to fix the alignment of Right Marginal
Bund of Benazir Bhutto Shaheed Bridge over River Indus. A PC-1
amounting 1115.212 (Million) was prepared by the concerned
office and submitted to National Highway Authority (NHA) on
22-04-2016 for approval.
Approval of PC-1
of the project
including
Sub-component: Approval of revised PC-1 with cost clearance was issued on
7th August 2017 vide letter # 16(331) PIA-IIL/PC/2017 by Ministry of
Planning Development & Reform.

Revised PC-1 with amount 9304.160 (M) was approved by ECNEC


in its meeting held on 26th July 2017.

Total Cost of Sub-Component “Construction of Right Marginal


Bund” approved by ECNEC is 1052.500 (M).
Release of Funds
To Irrigation
Department: Project director (SBBB) NHA vide his letter #
PD(SBBB)/NHA/2018/1380 dated 16th February 2018 has informed
Irrigation Department that competent authority has approved the
case of transfer of funds.
Subsequently a Cheque of amount Rs. 889,674,000/ in favor of
Executive Engineer Jampur Construction Division vide letter #
PD(SBBB)/NHA/2018/1388 dated 19th February 2018 was issued and
XEN Jampur has received this cheque on 20th February 2018.
Preparation &
Approval of Detailed
Design & Estimate
(T.S): After receiving of funds, detailed design and estimate of alleged
component was prepared and NSL were jointly verified by NHA &
Irrigation department.
Project Director NHA vide its letter# PD (SBBB) /NHA/2018/1402
dated 1st March 2018 approved the NSL.
Chief Engineer Irrigation D.G Khan Zone vide its letter#
works/2018/3867/425/16 dated 3rd March 2018 has issued approval
of T.S for an amount of Rs. 917,313,643/-.

Page 2 of 6
Components of
Sub-Project
“Construction of
Right Marginal Bund”: 1. Earth Work 627.463 (Million)
2. Shingle Work 27.533 (Million)
3. Out Fall Structures 61.564 (Million)
4. Data Board, distance
Marks, Gauge Pillar 0.313 (Million)
TOTAL COST OF WORKS 716.878 (Million)
TOTAL COST OF LAND
ACQUISITION 158.464 (Million)

Execution of Works: From the detailed scrutiny of the documents / record produced by
the Irrigation department it was found that Irrigation department is
executing the earth work component of sub-project through its
machinery division.

XEN Irrigation Jampur attended this office on 19th November 2018


for submission of record. He was asked to provide the approval of
competent authority for execution of works through department
itself, He was also directed to provide the cost comparison in case
of open bidding compared with departmental execution.
Reply of XEN Irrigation Department was received on 26th November
2018.
Following are the findings after the study and scrutiny of reply and
all relevant documents.

Conclusion / Findings:
1. Currently work on earth work component is in progress.
2. Irrigation department is executing only one component
through its machinery division.
3. All other components would be executed through open /
competitive bidding.
4. Work is being executed as per approved design and
drawings. As mentioned in written statement submitted by
XEN Irrigation department.
5. No any formal approval from competent authority has been
accord for execution of works by machinery division of
Irrigation department.
6. Work is being executed through machinery division on
verbal directions of Chief Engineer D.G Khan, with the
intension to complete the earth work before flood season-
2018.

Page 3 of 6
7. Following is the detail of Work orders issued to Machinery
Division.

Quantity Rate Amoun


Sr Descriptio Irrigation Remar
Date Quantit Uni t
# n Dept Rate Unit ks
y t (M)
Earth 1st
Work work
excavati order
on from was
outside issued
borrow for
pits 155.474
Avarage 2-Jul- (M)
Machinery
Lead 2018 M. %0 in 2nd
1 Division 75.49 5182
upto 2 5-May- Cft Cft 391.19 Work
Multan
mile 2018 order
including quantit
dressing y and
& Amoun
levelling t of 1st
for all WO is
type of Merge
soil. d
Exacavator
3-May- M. %0
2 "do" Division 29.66 5182 153.70
2018 Cft Cft
Faisalabad

Construction
1-Aug- M. %0
3 "do" Division Dera 15.94 5182 82.60
2018 Cft Cft
Gazi Khan
M.
121.09
TOTAL Cft 627.49

Page 4 of 6
8. Details of Funds transfer and current status is as under
Total Work Total Work
Work Total Amount
Name of done done
Sr# Assigned Deposited
Division (Earth Work) (Amount)
(M.CFT) (M)
M.CFT Millions

Machinery
1 75.49 270 28.687 148.656
Division Multan

Exacavator
2 Division 29.66 150 10.378 53.789
Faisalabad

Construction
3 Division Dera 15.94 75 0.956 4.955
Gazi Khan
G.TOTAL 40.021 207.4

9. Total Progress Till Todate:


Total Utilization % tag
Component
(Approved Cost) Till To date Progress
Earth Work 627.462 207.4 33%
Shingle Work 27.533 0 0%
Out Fall Structures 61.564 0 0%
Data Board, distance 0.313 0%
Marks, Gauge Pillar 0

Page 5 of 6
10. Cost Comparison MRS vs Machinery Rates:
Work is awarded at 29% below rates from bi annual at the
time of submission of PC-1.
In case of competitive bidding T.S needs to be revised
incorporating current bi annual rates, which are 62 % higher
as compare to Machinery rates of Irrigation division.

Rate per
Machiner
1000 cft with Differenc %
MRS y Rates Remark
Task Dated same e ag
Period (per 1000 s
specificatio (Amount) e
cft)
ns
(Bi-
Annual
February
Submissio 22.04.201 29
2016 to 6678.4 5182 1496.4 Above
n of PC-1 6 %
July 2016)
of District
Rajanpur
(Bi-
Annual
Approval 07.08.201 2nd July- 53
7932.55 5182 2750.55 Above
of PC-1 7 2017 to %
Decemb
er – 2017)
(Bi-
Annual
Technical
1st
Sanction 03.03.201 62
January- 8392.5 5182 3210.5 Above
of 8 %
2018 to
Estimate
July–
2018)

Recommendations:

It is recommended to forward the case to secretary Irrigation and power department for
proper check and monitoring on expenditure and quality of works.

Engr.Muhammad Iqbal

Junior Expert II (Engineering)