The IRI Lahore sent the Hydraulic Model Study Report No.IRI-1270
dated January, 25 2012 with their recommendation for final
location and length of the bridge.
Sub Components:
Page 1 of 6
Preparation of PC-1
of Alleged sub component:
Secretary Irrigation Department Punjab vide letter
No.473/PRO(H)/795-C dated.18-03-2016, directed PRO Hydraulic
and Chief Engineer D.G Khan to fix the alignment of Right Marginal
Bund of Benazir Bhutto Shaheed Bridge over River Indus. A PC-1
amounting 1115.212 (Million) was prepared by the concerned
office and submitted to National Highway Authority (NHA) on
22-04-2016 for approval.
Approval of PC-1
of the project
including
Sub-component: Approval of revised PC-1 with cost clearance was issued on
7th August 2017 vide letter # 16(331) PIA-IIL/PC/2017 by Ministry of
Planning Development & Reform.
Page 2 of 6
Components of
Sub-Project
“Construction of
Right Marginal Bund”: 1. Earth Work 627.463 (Million)
2. Shingle Work 27.533 (Million)
3. Out Fall Structures 61.564 (Million)
4. Data Board, distance
Marks, Gauge Pillar 0.313 (Million)
TOTAL COST OF WORKS 716.878 (Million)
TOTAL COST OF LAND
ACQUISITION 158.464 (Million)
Execution of Works: From the detailed scrutiny of the documents / record produced by
the Irrigation department it was found that Irrigation department is
executing the earth work component of sub-project through its
machinery division.
Conclusion / Findings:
1. Currently work on earth work component is in progress.
2. Irrigation department is executing only one component
through its machinery division.
3. All other components would be executed through open /
competitive bidding.
4. Work is being executed as per approved design and
drawings. As mentioned in written statement submitted by
XEN Irrigation department.
5. No any formal approval from competent authority has been
accord for execution of works by machinery division of
Irrigation department.
6. Work is being executed through machinery division on
verbal directions of Chief Engineer D.G Khan, with the
intension to complete the earth work before flood season-
2018.
Page 3 of 6
7. Following is the detail of Work orders issued to Machinery
Division.
Construction
1-Aug- M. %0
3 "do" Division Dera 15.94 5182 82.60
2018 Cft Cft
Gazi Khan
M.
121.09
TOTAL Cft 627.49
Page 4 of 6
8. Details of Funds transfer and current status is as under
Total Work Total Work
Work Total Amount
Name of done done
Sr# Assigned Deposited
Division (Earth Work) (Amount)
(M.CFT) (M)
M.CFT Millions
Machinery
1 75.49 270 28.687 148.656
Division Multan
Exacavator
2 Division 29.66 150 10.378 53.789
Faisalabad
Construction
3 Division Dera 15.94 75 0.956 4.955
Gazi Khan
G.TOTAL 40.021 207.4
Page 5 of 6
10. Cost Comparison MRS vs Machinery Rates:
Work is awarded at 29% below rates from bi annual at the
time of submission of PC-1.
In case of competitive bidding T.S needs to be revised
incorporating current bi annual rates, which are 62 % higher
as compare to Machinery rates of Irrigation division.
Rate per
Machiner
1000 cft with Differenc %
MRS y Rates Remark
Task Dated same e ag
Period (per 1000 s
specificatio (Amount) e
cft)
ns
(Bi-
Annual
February
Submissio 22.04.201 29
2016 to 6678.4 5182 1496.4 Above
n of PC-1 6 %
July 2016)
of District
Rajanpur
(Bi-
Annual
Approval 07.08.201 2nd July- 53
7932.55 5182 2750.55 Above
of PC-1 7 2017 to %
Decemb
er – 2017)
(Bi-
Annual
Technical
1st
Sanction 03.03.201 62
January- 8392.5 5182 3210.5 Above
of 8 %
2018 to
Estimate
July–
2018)
Recommendations:
It is recommended to forward the case to secretary Irrigation and power department for
proper check and monitoring on expenditure and quality of works.
Engr.Muhammad Iqbal
Page 6 of 6