PROGRESS ON FLOOD PROTECTION WORKS IN

DISTRICT NOWSHERA

IRRIGATION DEPARTMENT KHYBER PAKHTUNKHWA

OCT 2019
Project Brief

Name of Work : Construction of Flood Embankment on


right side Kabul River (Reach No.1)
District Nowshera
ADP NO. 1254
Approved Cost : 914.90 Million

Total Length : 5.79 KM

Achieved Length : 4.94 KM

Approved Consultant : SAK JV ILF CONSULTANT

Approved Contractor : M/S Haji Aurangzeb Khan & Sons

In Progress Length : 0.61 KM

Financial Progress : 59%

Physical Progress : 85 %
Construction of Flood Embankment on right side Kabul River (Reach No.1)
District Nowshera
Project Detail Breakdown
Total Achieved
S # Reach Name / RDs Remarks/Status
Length length
Shahlam Retaining Wall (93+000
1 2000 ft 2000 ft
to 95+000)

Shahalam Embankment ( 95+000


2 3600 ft 3600 ft
to 98+600)

Kabul River Embankment


3 3400 ft 3400 ft
(98+600 to 102+000)
Kabul River Retaining Wall
4 3650 ft 3650 ft
(102+000 to 105+650)
Kabul River Embankment D/S
5 Motorway Bridge ( 108+800 to 3865 ft 3865 ft
112+665)
Joint Survey With
Contractor is completed
6 Bara River 2000 ft - and is directed to
immediately start work
Project Brief
Name of Work : Construction of Flood Embankment on
right side Kabul River (Reach No.2)
District Nowshera
ADP NO. 1255

Approved Cost : 929.18 Million

Total Length : 6.49 KM

Achieved Length : 3.54 KM

Approved Consultant : SAK JV ILF CONSULTANT

Approved Contractor : M/S Haji Aurangzeb Khan & Sons

In Progress Length : 2.95 KM

Financial Progress : 52.65%

Physical Progress : 54 %
Construction of Flood Embankment on right side Kabul River (Reach No.2)
District Nowshera
Project Detail Breakdown
Total Achieved
S# Reach Name / RDs Remarks/Status
Length length
Apron & Pitching is Completed
1 112+450 to 117+150 4700 ft 4700 ft while Sub-base/shingle is
remaining

Apron is completed while


2 117+150 to 120+900 3750 ft 3750 ft embankment and pitching is
remaining

Disputed portion due to land


3 120+900 to 121+650 750 ft - owner naming Arbab Tariq

Embankment / pitching is
4 121+650 to 123+820 2170 ft 2170 ft completed while subbae is
remaining

Disputed Portion due to Arbab


5 123+820 to 125+920 2100 ft Noorhussain

Disputed Portion Due to Arbab


6 125+920 to 128+620 2700 ft - Sheraz & Arbab Azhar

Loose Dumping Completed Apron is


7 128+620 to 130+420 1800 ft - in progress

Embankment and Subbase is


8 130+420 to 131+420 1000 ft 1000 ft
remaining

Contractor is directed to
9 Chilla Nullah 2100 ft -
immediately start work
Project Brief
Name of Work : Construction of Flood Embankment on
right side Kabul River (Reach No.3)
District Nowshera.
ADP NO. 1256

Approved Cost : 2312.08 Million

Total Length : 20.83 KM

Achieved Length : 11.6 KM

Approved Consultant : SAK JV ILF CONSULTANT

Approved Contractor : M/S Pasham khan & Co.

In Progress Length : 9.3 KM

Financial Progress : 46%

Physical Progress : 50%


Construction of Flood Embankment on right side Kabul River (Reach No.3)
District Nowshera
Construction of Flood Embankment on right side Kabul River (Reach No.3)
District Nowshera
Project Detail Breakdown
Total Achieved
S # Reach Name / RDs Remarks/Status
Length length
1 130+932 to 154+400 23468 ft 23468 ft
2 154+400 to 167+500 13100 13100 ft
3 167+500 to 170+500 3000 ft - In Progress
Disputed Portion Due To
4 170+500 to 178+882 8382 ft - land owners of Village
kheshki

5 Main Banda Mohib Drain 1500 ft 1500 ft

6 Dagai Nullah 5000 ft - In Progress

7 Azakhel Drain 1500 ft -

8 Azakhel Payan Khwar 1500 ft -

9 Pirpiai Nullah 4500 ft -


10 Creek 6396 ft -
Proposed Flood Protection Structure