Name of Work :

Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram
Road in Krishna District.
Sub Estimate 1 :

Transportation of 120' 00'' DSR Bailey bridge Launching nose equipment and Bridge
material etc. for erecting Bailey Bridge from Vijayawada to Km. 11/4-6 of Tallapalem -
Narayanapuram Road.
Est. Amount : Rs 72500/-
SPECIFICATION REPORT

Tallapalem - Narayanapuram road passing through the Agriculturally & Aqua


culturally rich villages like Tallapalem, Kanuru, pedapatnam & Narayanapuram and
other 20 hemlets in the coastal belt within 5 to 6 kms from the sea, Bay of bengal.
Their main mode of trasportation is road.

It is very essential to provide land connection at Km. 11/4-6 of Tallapalem -


Narayanapuram Road to avail the villagers for their Revenue, Law & order, Political,
Educational & Medical facilities, Transportion of their paddy to their required
destination. So, it is essential to erect the Bailey bridge for transporting the goods and
people, this estimate is prepared with the following provisions.

1 Towards conveyance of Launching nose equipment from vijayawada to site


2 Towards conveyance of Bailey bridge materials from vijayawada yard to bailey bridge site.

3 Towards provision for packing material , wooden planks,lubricants, bits and taps, etc.,
4 Provision for VAT @ 4%
5 L.S Provision for Unforeseen items, Stationery, Xerox etc. and rounding off.

The rates are adopted as per 2008-09 AP State Common SSR and as per the local minimum
market rates and the work will be carried out as per rule in force.

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
DETAILED CUM ABSTRACT ESTIMATE
Name of Work: Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road in
Krishna District.

Sub Work 1 : Transportation of 120' 00'' DSR Bailey bridge Launching nose equipment and Bridge material etc. for
erecting Bailey Bridge from Vijayawada to Km. 11/4-6 of Tallapalem - Narayanapuram Road.

S. No Description of Item Nos L B D Quantity Rate per Amount

1 Towards conveyance of Launching nose equipment from vijayawada


to site for erecting of bailey bridge including loading, unloading and
stacking etc., complete.

Launching nose equipment


(vijayawada to site) 1 (Total wt. 10 tons) 1 6090.00 No. 6090
No.
2 Towards conveyance of Bailey bridge materials from vijayawada
yard to bailey bridge site including loading, unloading and stacking
etc., complete.
Bailey bridge materials from
vijayawada yard to site 9 Lorries 9 6090.00 No. 54810
No.
3 Towards provision for packing material , wooden planks,lubricants,
bits and taps, etc.,
a) Wooden planks 2' x 3' x 1'' size 10 No. 10.00 300.00 No. 3000
b) Hydraulic oil 20 litres 20.00 110.00 1 Lit. 2200
c) Greese 20 kgs 20.00 50.00 Kg 1000
d) Wire rope with Bull dog clips 15 RM 15.00 100.00 Rm 1500
e) Bits & taps 2 sets 2.00 400 Set 800
69400

4 Provision for VAT @ 4% 2776


5 Unforeseen items, Stationery, Xerox etc. and rounding off 324
Total Amount Rs. 72500

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
Name of Work :
Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road in Krishna
District.
Sub Estimate 2 :

Transportation of 120' 00'' DSR Bailey bridge Launching nose equipment and Bridge material etc. for erecting
Bailey Bridge from Vijayawada to Km. 11/4-6 of Tallapalem - Narayanapuram Road.

DATA SHEET
1) Towards conveyance of Launching nose equipment and bailey bridge materials from Vijayawada (R&B) site to 11/4-6 of
Tallapalem - Narayanapuram Road

0.00 to 20.00 Kms 244.00 /Tonne / 20 Km 10 Tonne Lorry 2440.00


21.00 to 30.00 Kms 5.75 /Tonne / Km 575.00
31.00 to 50.00 Kms 5.50 /Tonne / Km 1100.00
51.00 to 80.00 Kms 5.00 /Tonne / Km 1500.00
81.00 to 90.00 Kms 4.75 /Tonne / Km 475.00
6090.00 /10 Tonne Lorry

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
Name of Work :

Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram
Road in Krishna District.
Sub Estimate 1 :

Erection of 120' 00'' DSR Bailey bridge at Km. 11/4-6 of Tallapalem - Narayanapuram Road.

Est. Amount : Rs 95000/-

SPECIFICATION REPORT

Tallapalem - Narayanapuram road passing through the Agriculturally & Aqua


culturally rich villages like Tallapalem, Kanuru, pedapatnam & Narayanapuram and
other 20 hemlets in the coastal belt within 5 to 6 kms from the sea, Bay of bengal.
Their main mode of trasportation is road.

It is very essential to provide land connection at Km. 11/4-6 of Tallapalem -


Narayanapuram Road to avail the villagers for their Revenue, Law & order, Political,
Educational & Medical facilities, Transportion of their paddy to their required
destination. So, it is essential to erect the Bailey bridge for transporting the goods and
people, this estimate is prepared with the following provisions.

1 Towards labour charges for the skilled persons at the time of erection
2 Towards labour charges for the unskilled persons at the time of erection

3 Towards Hire charges of Dozer/lorry/JCB for pulling and pushing perpose during the time of
erection.
4 Provision for VAT @ 4%
5 L.S Provision for Unforeseen items, Stationery, Xerox etc. and rounding off.

The rates are adopted as per 2008-09 AP State Common SSR and as per the local minimum
market rates and the work will be carried out as per rule in force.

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
DETAILED CUM ABSTRACT ESTIMATE
Name of Work: Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road in Krishna
District.

Sub Work 2 : Erection of 120' 00'' DSR Bailey bridge at Km. 11/4-6 of Tallapalem - Narayanapuram Road

S. No Description of Item Nos L B D Quantity Rate per Amount

1 Towards labour charges for the skilled persons at the time of erection

Skilled persons 10 5 days 50 206.00 No. 10300


No.
2 Towards labour charges for the unskilled persons at the time of erection

unskilled persons 54 5 days 270 146.00 No. 39420


No.
3 Towards Hire charges of Dozer/lorry/JCB for pulling and pushing perpose
during the time of erection.
Mechinery Equipment 3 5 days/8 hours work 120.00 345.00 Hour 41400
Hour
91120

4 Provision for VAT @ 4% 3645


5 Unforeseen items, Stationery, Xerox etc. and rounding off 235
Total Amount Rs. 95000

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
Name of Work :
Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road in
Krishna District.
Sub Estimate 1 :
Transportation of 120' 00'' DSR Bailey bridge Launching nose equipment and Bridge material etc. for
erecting Bailey Bridge from Vijayawada to Km. 11/4-6 of Tallapalem - Narayanapuram Road.

DATA SHEET
1) Labour Charges a) Skilled Persons Rs. 206.00 /Each
( As per Common SSR 2008-09, Item No. Page No. 8 )

b) Un Skilled Persons Rs. 146.00 /Each


( As per Common SSR 2008-09, Item No.73 Page No.11 )

2) Hire Charges of Dozer (D 80) Rs. 2760.00 /Hour


( As per Common SSR 2008-09, Item No. 1 Page No. 130 )

3) Hire Charges of JCB/ Lorry/ Tractor Pulling Rs. 345.00 /Hour


( As per Common SSR 2008-09, Item No. 9 Page No. 130 )

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
Name of Work :
Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road
in Krishna District.
Sub Estimate 3 :

Tranportation of launching Nose Equipment from Km. 11/4-6 of Tallapalem - Narayanapuram


Road to Vijayawada, Cost & Supply of Deck Bolts,Transom clamps and Recondition of Deck
Plates etc.,
Est. Amount : Rs 98500/-
SPECIFICATION REPORT

Tallapalem - Narayanapuram road passing through the Agriculturally & Aqua


culturally rich villages like Tallapalem, Kanuru, pedapatnam & Narayanapuram and other
20 hemlets in the coastal belt within 5 to 6 kms from the sea, Bay of bengal. Their main
mode of trasportation is road.

It is very essential to provide land connection at Km. 11/4-6 of Tallapalem -


Narayanapuram Road to avail the villagers for their Revenue, Law & order, Political,
Educational & Medical facilities, Transportion of their paddy to their required destination.
So, it is essential to erect the Bailey bridge for transporting the goods and people, this
estimate is prepared with the following provisions.

1 Towards conveyance of Launching nose equipment from site to vijayawada after erecting of bailey
bridge
2 Towards cost and supply of Deck bolts with double nuts and washers
3 Towards cost and supply of transom clamps
4 Towards reconditioning the damaged and deck plates 12 No.s
5 Provision for VAT @ 4%
6 L.S Provision for Unforeseen items, Stationery, Xerox etc. and rounding off.

The rates are adopted as per 2008-09 AP State Common SSR and as per the local minimum market
rates and the work will be carried out as per rule in force.

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
DETAILED CUM ABSTRACT ESTIMATE
Name of Work: Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road in Krishna
District.

Sub Work 3 : Tranportation of launching Nose Equipment from Km. 11/4-6 of Tallapalem - Narayanapuram Road to
Vijayawada, Cost & Supply of Deck Bolts,Transom clamps and Recondition of Deck Plates etc.,

S. No Description of Item Nos L B D Quantity Rate per Amount

1 Towards conveyance of Launching nose equipment from site to


vijayawada after erecting of bailey bridge including loading, unloading
and stacking etc., complete.

Launching nose equipment (From Site to


vijayawada) 1 (Total wt. 10 tons) 1 6090.00 No. 6090
No.
2 Towards cost and supply of Deck bolts with double nuts and washers

Deck bolts 220 220 140.00 No. 30800


No.
3 Towards cost and supply of transom clamps

Transom clamps 50 50 432.00 No. 21600


No.
4 Towards reconditioning the damaged and deck plates 12 No.s (Utilised at
Gudlavalleru) for reuse by providing 6 mm checking plate over the top
surface.

Reconditioning the end deck plates 12 12 3000.00 No. 36000


No.
94490

5 Provision for VAT @ 4% 3780


6 Unforeseen items, Stationery, Xerox etc. and rounding off 230
Total Amount Rs. 98500

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
Name of Work :
Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road in Krishna
District.
Sub Estimate 3 :

Tranportation of launching Nose Equipment from Km. 11/4-6 of Tallapalem - Narayanapuram Road to
Vijayawada and recondition of Deck Plates etc.,

DATA SHEET
1) Towards conveyance of Launching nose equipment from site to vijayawada after erecting of bailey bridge including
loading, unloading and stacking etc., complete.

0.00 to 20.00 Kms 244.00 /Tonne / 20 Km 10 Tonne Lorry 2440.00


21.00 to 30.00 Kms 5.75 /Tonne / Km 575.00
31.00 to 50.00 Kms 5.50 /Tonne / Km 1100.00
51.00 to 80.00 Kms 5.00 /Tonne / Km 1500.00
81.00 to 90.00 Kms 4.75 /Tonne / Km 475.00
6090.00 /10 Tonne Lorry

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
Name of Work :

Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram
Road in Krishna District.
Sub Estimate 4 :
Maintenance of Bailey Bridge including painting, repairs of plates, cost and suply of bolts
and nuts etc.
Est. Amount : Rs 73000/-

SPECIFICATION REPORT

Tallapalem - Narayanapuram road passing through the Agriculturally & Aqua


culturally rich villages like Tallapalem, Kanuru, pedapatnam & Narayanapuram and
other 20 hemlets in the coastal belt within 5 to 6 kms from the sea, Bay of bengal.
Their main mode of trasportation is road.

It is very essential to provide land connection at Km. 11/4-6 of Tallapalem -


Narayanapuram Road to avail the villagers for their Revenue, Law & order, Political,
Educational & Medical facilities, Transportion of their paddy to their required
destination. So, it is essential to erect the Bailey bridge for transporting the goods and
people, this estimate is prepared for painting of the bailey bridge and other repairs with
the following provisions.

1 Painting to iron work with 2-coats of Ready Mixed First Quality Synthetic Enamel Paint of
approved brand for bailey bridge components.
2 Painting to Iron work with 2-coats of Anti Corrosive bitumen paint (Black ) grade1 of approved
brand for deck plates.
3 Provision for VAT @ 4%
4 L.S Provision for Unforeseen items, Stationery, Xerox etc. and rounding off.

The rates are adopted as per 2008-09 AP State Common SSR and as per the local minimum
market rates and the work will be carried out as per rule in force.

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
DETAILED CUM ABSTRACT ESTIMATE

Name of Work: Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road in Krishna District.

Sub Esimate 4 : Maintenance of Bailey Bridge including painting, repairs of plates, cost and suply of bolts and nuts etc.

S. No Description of Item Nos L B D Quantity Rate per Amount

1 Painting to iron work with 2-coats of Ready Mixed First Quality Synthetic
Enamel Paint of approved brand and shade approved brand making 2 coats in all
including cost and conveyance of all materials to work site, all operational,
incidental, labour charges, etc. complete for finished item of work as per SS
1207 & SS 1212

For Panel(Type 1)
Chords(Channel Section) 8 3.000 2 x 0.180 8.640
Horizontals(Channel Section) 3 1.500 2 x 0.145 1.305
Cross Bars( I-Section) 8 0.950 2 x 0.290 4.408
Plates 2 0.230 0.230 0.106
" 4 0.120 0.230 0.110
(For one Panel) 14.57
For Panel(Type 2)
Chords(Channels) 4 3.000 2 x 0.180 4.320
Horizontals( Channels) 3 1.500 2 x 0.145 1.305
Cross Bars( I-Section) 8 0.950 2 x 0.290 4.408
Plates 2 0.230 0.230 0.106
" 4 0.120 0.230 0.110
(For one Panel) 10.25

For 40 Panels(Type 1) 40 14.569 582.77


For 8 Panels(Type 2) 8 10.249 81.99
664.76

For Transoms(I-Section) 50 6.100 0.964 294.02

Bracing Frames 24 1.300 0.510 15.91

Rakers 24 1.110 0.190 5.06

End Posts 8 1.700 0.450 6.12

Bridge Kerbs 2 37.100 0.450 33.39

Total Area(Sqm) 1019.27


L.S for Transom clamps, bolts, nuts and miscellaneous items etc 178.73
1198.00 406.00 10 Sqm 48639
Sqm
S. No Description of Item Nos L B D Quantity Rate per Amount

2 Painting to Iron work with 2-coats of Anti Corrosive bitumen paint (Black )
grade1 of approved brand and shade over an existing steel primer including cost
and conveyance of all materials to work site, all operational, incidental, labour
charges, etc. complete for finished item of work as per SS 2207 & SS 1212

Deck Plates (Top & Bottom) 2 37.100 4.35 322.77


or 325.00 642.00 10 Sqm 20865
Sqm
69504

3 Provision for VAT @ 4% 2780


4 Unforeseen items, Stationery, Xerox etc. and rounding off 716

Total Amount Rs. 73000

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam
Name of Work :
Providing Bailey Bridge Across Salt Creak in Km. 11/4-6 of Tallapalem - Narayanapuram Road in
Krishna District.
Sub Estimate 4 :
Maintenance of Bailey Bridge including painting, repairs of plates, cost and suply of bolts and
nuts etc.

DATA SHEET
1 Painting to Iron work with 2-coats of Ready Mixed First Quality Synthetic
Enamel Paint of approved brand and shade over an existing steel primer/paint
including cost and conveyance of all materials to work site, all operational,
incidental, labour charges, etc. complete for finished item of work as per SS
2207 & SS 1212

1.10 LTR COST OF SYNTHATIC ENAMEL 175.00 1 LTR 192.50


PAINT 390/23 1st grade
0.33 NOS I CLASS PAINTER 206.00 EACH 67.98
0.77 NOS II CLASS PAINTER 188.00 EACH 144.76
TOTAL 405.24
ADD FOR L S FOR BRUSHES 0.76
406.00
ROUNDING OFF RS. 406.00 / 10 SQM

2 Painting to Iron work with 2-coats of Anti Corrosive bitumen paint (Black )
grade1 of approved brand and shade over an existing steel primer including
cost and conveyance of all materials to work site, all operational, incidental,
labour charges, etc. complete for finished item of work as per SS 2207 & SS
1212
1.10 LTR Anti Corrosive bitumen paint (Black 389.00 1 LTR 427.90
) 387/23 grade1
0.33 NOS I CLASS PAINTER 206.00 EACH 67.98
0.77 NOS II CLASS PAINTER 188.00 EACH 144.76
TOTAL 640.64
ADD FOR L S FOR BRUSHES 1.36
642.00
ROUNDING OFF RS. 642.00 / 10 SQM

Dy.Executive Engineer Asst. Executive Engineer


(R&B) Sub-Division, Machilipatnam (R&B) Bantumilli Section

Executive Engineer
(R&B), Division, Machilipatnam