Dwarka Expressway

Brief:

The alignment of Dwarka Expressway (DEW) takes off from Km 20 Shiv Murti of NH
8 and terminates at Km 40 (near Kherki Daula) of NH 8 at CPR-NH 8-SPR intersection. The
total length of Dwarka Expressway is 29.1 Km., out of which 18.9 Km length falls in
Haryana and remaining 10.3 Km in Delhi. The package wise details of Dwarka Expressway
is as follows:

Package Chainage (Km) Length Cost Description Current Status


(Km) (Rs. Cr.) (tentative)
From To
1 -0.600 5.300 5.90 1349 Shiv Murti to RuB Work Awarded. But awaiting
tree removal permission,
expected to be completed in
March 2022
2 5.300 9.500 4.20 1540 RuB to Haryana Work in Progress, Expected to
Border be completed in Nov 2021
3 9.500 19.700 10.2 1333 Haryana Border to Work in Progress, Expected to
RoB be completed in Dec 2020
4 19.700 28.460 8.76 1047 RoB to NH-8 – SPR Work in Progress, Expected to
Intersection be completed in Dec 2020
Total 29.10 5269

Project Features:

Proposed Carriageway 8 Lane access controlled with Service Road


Major Bridge (Nos.) 8 lane elevated carriageway length 23.12 Km (Viaduct/ underpass
Portion)
Minor Bridge (Nos.) 3 nos.
ROB/RUB (Nos.) 1 ROB & 1 RUB
VUP/ Flyover (Nos.) 8 lane elevated main carriageway length 23.12 Km (Viaduct
Portion), Shallow Tunnel of 3.6 km and Flyovers on Service Road
at 6 locations,
underpasses on Cross Roads at 10 Locations and
4 interchanges at Shiv-murti, SPR junction, ECC and Jaipur
expressway.

Service road 28.5 Km, 3 lane on both Sides, 4 lane at intersections

Physical Progress of Package-2 till 31.08.2020: 4.9%

Financial Progress of Package-2 till 31.08.2020: 3.62%


Package-2 Salient Features:

S.No Details Package-2


1. Name Of Project From km 5+300 to km 9+500
2. DPR/Feasibility Study Consultant M/s AECOM
3. Length & Carriageway Length 4.2 km from RUB (5+300) to Delhi
4. Existing Carriageway The existing road from Km 6+295 to km 8+130 has 6-lane carriageway
with paved shoulder.
5. Proposed Carriageway Proposed is 8L + 1.5 m with minimum 2 lane service road both sides.
6. Major Bridge(Nos.) Nil
7. Minor Bridge (Nos.) 1 Nos. To be newly constructed at km 5+340.
8. ROB(Nos.) Nil
9. Toll Plaza (Nos.) 1 Nos. 17 lane on each side including one lane for over-sized vehicles at
chainage km 9+045.
10. Grade Separated Structures 21 Nos.
VUP/LVUP (Nos.) 4 Nos. Of VUP at km 5+651, km 7+470, km 8+009 (U turn from left
service road towards ECC), km 8+600 with 5.5m vertical clearance.
Flyover/Ramp on Structure(Nos.) 15 Nos. (including elevated structures on +2 level)

14. Pedestrian Subway 5 Nos.


15. Foot Over Bridge Nil
16. Truck Lay Bay (Nos.) Nil
17. Rest Area Nil
18. Bus Bays With Bus Shelter (Nos.) 7 Nos. (4 LHS, 3 RHS) on main carriageway of Dwarka Expressway, 1
Nos. RHS on link road to Najafgarh.
19. Major Junction (Nos.) 7 Nos. Junction are to be improved 4 Nos. through VUP and 3 Nos.
through flyover (details mentioned in S.No 14)
20. Minor Junction (Nos.) 5 Nos. Towards kherki daula ( at km 7+100, km 7+300, km 7+400,km
7+500, km 7+700), 3 Nos. Towards Najafgarh (at km 6+600, km 6+900,
km 7+300).
21. Culverts (Nos.) 1 Nos. Existing culvert at chainage km 5+950 (repair).
22. Additional Provisions ITS for entire Dwarka Expressway is being proposed. EOI has been
floated for preparation of DPR of ITS and offering technological feasible
solutions. This package will also provide access to upcoming Exhibition-
cum-Convention centre, sector-25, Dwarka. DIPP has agreed to bear the
cost of Rs.350 Crores approximate for this cost.
Project Overview:

S.No Description Salient Features


1 Name of Contract Construction of Dwarka Expressway from RUB to Delhi-
Haryana Border- Package-2
2 Type of Contract EPC
3 Authority Ntaional Highways Authority of India
4 Authority Engineer M/s STUP Consultants Pvt. Ltd. & CEOMA Consulting
5 EPC Contractor M/s J Kumar Infraprojects Ltd.
6 Detailed Design Consultant M/s Structcon Designs Pvt. Ltd.
7 Proof Consultant M/s Tandon Consultants Pvt. Ltd.
8 Safety Consultant M/s Almondz Global Infra Consultants Ltd.
9 Date of LOA 26th July 2019
10 Date of Agreement 5TH September 2019
11 Appointed Date 17th October 2019
12 Construction Period 24 Months
13 Maintenance Period 10 Years
14 Contract Value 1540 Crore

Design Status

S. No.  Description Project Total Submitted Approved by PC Approved by AE

1 Plan & Profile Elevated 19 18 18 18


2 Plan & Profile At-Grade 23 23 19 19
3 GAD 19 17 17 17
4 Pile 2502 1778 1484 1430
5 Pile Cap 480 331 273 264
6 Pier 548 331 273 264
7 Pier Cap 514 44 42 2
8 Portals 34 1 0 0

8.1 Pile Cap (Portal) 68 2 0 0

8.2 Portal Beam 34 1 0 0


9 Segment Design
9.1 16m Wide 3 3 2 1
9.2 12.5m Wide 3 2 2 1
9.3 10.25m Wide 3 2 0 0

Physical Progress Till date


S.N. DESCRIPTION UNIT TOTAL SCOPE ACHIVED TILL DATE % SCOPE COMPLETE

1 Piles Nos 2506 1040 40%


2 Pile Cap Nos 548 122 21%
3 Pier Nos 548 20 2.2%
4 Pier Cap Nos 520 2 0.4%
5 Portal Beam Nos 20 -
6 Segment Casting Seg. 6063 124 2%
7 Segment Launching / CIS Span 497 -
432 (Raft)
8 Airport Drain RM 950
1056 (Wall)
9 Underpass RM 811 -
10 Subways RM 395 -
11 Sector Drain RM 14770 917 6.04%
12 Tree Transplantation Nos 5715 3781 66.2%

Utility Shifting Progress:

S.No. Description Approved Date Scope Achieved Status

1 IGL – 5 Inch 17.01.2020 Not Yet Started

HDD machine reached at site, 8” dia


2 IGL – 8 Inch 14.01.2020
2318 rm work is completed.

3 IGL – 12 Inch 14.01.2020 Not Yet Started

Water pipe line – 600


4 29.01.2020 30 mtr pipe line laying done.
Dia (Non Operational)

5 Water pipe line 1000 Dia 18.05.2020 100 mtr pipe line laying done

Water pipe line – 100,


6 06.07.2020 200, 250 & 400 dia completed.
200, 250 & 400 Dia

50 nos Manhole & 1718 rm pipe line


7 Sewer line – 800 Dia 29.01.2020
laying work done.

8 Sewer line – 450/500 Dia 23.09.2020 Not yet Started

Najafgarh side, Near MC02, I Girder &


8 BSES – 11 KV 09.12.2019
Main Casting Yard side complete.

9 DTL – 220 KV 19.06.2020 Drawing sent to approval to DTL.

10 Shifting -Boundary wall 29.01.2020 Dismantling of Boundary wall Done.

Critical Issues:
1. Slow Construction Speed/Slippages of Planned Targets of every month:

The Contractor is continuously slipping in achieving the planned


targets. The progress of last three months is as follows:

2. Submission of Monthly Account Statement of Project related bank


Account:

The Contractor has to submit the Monthly Account Statement of


Project related bank Account every month, as per the Contract obligations.
However, Contractor is not submitting the same, it is important to ensure
that the Contractor is utilising the projects funds for projects related things
only. This will also ensure monitoring of timely payment to Vendors for
smooth progress of works.

3. Delay in Design Submissions from DDC:

Various deadlines have been passed for submissions of detailed


designs, latest deadline is 30.09.2020, however the same has again slipped.

4. Schedule for Pier Cap Shutter, and Segment Shutters (12 m, 12.5m, 10.5
m, 8.5m) programme:

The Contractor is slipping in procurement of shutters of pier cap,


segments, due to which the construction work is suffering badly. Contractor
shall procure these shutters at the earliest.

5. Translocation of Balance trees:

Contractor had to translocate 5717 no. of trees for the project


highway in 90 days from August 2019. However, till date Contractor has
transplanted only 3800 no.of trees approx.

6. Replacement of Dried-up trees:

Out of 3800 no. of trees which are transplanted, 1500 no. of trees are
dead, the contractor has to replace them with new trees, in order to
achieve higher rate of survival of transplantation.

7. Schedule for Routine Pile Load Test:

As per the MoRTH guidelines the contractor shall carry out 2% routine
pile load test of total designed piles, which comes out to be 50 no. approx.
however, till date the contractor has carried out only 02 no . of routine pile
load test.
8. Completion of Balance no. of casting beds: (add segment)

In order to complete the project timely, the contractor has to set up


22 no. of beds in casting yard, till date only 11 no. of casting beds are
operational due to which the speed of segment casting is also slow. Till date
Contractor had planned to cast 752 no. of segment, however, approx. 130
segments were casted.

9. Submission of Revised Work Programme.

The contractor has to submit the revised work programme as per the
91 days extension of time due to NGT Ban.

10. Disposal of C&D Wastes:

The contractor has to dispose off the C&D waste, generating due to
construction work. However, Contractor is not disposing the same.

11. ITS Related Issue:

The Contractor has to submit the location Plan for overhead Traffic
Sign Gantries & Highway Lighting Poles on elevated structures, in-
consultation with ITS Engineer, however, the same has not been finalized
yet by DDC.

12. Contractor to expedite Utility Shifting:

The Contractor has to shift DTL 220 KV Electric line, IGL 8” & 12”
line, DJB Sewer & Water Line. The same is delaying at Contractor’s end, the
Contractor needs to expedite the Utility shifting.