Project: UPGRADATION OF GADCHIROLI-ASTHI ROAD TO TWO LANE WITH PAVED SHOULDERS/FOUR LANE CONFIGRATION ( PACKAGED NO- NH/IAHE/02) IN THE

02) IN THE STATE OF


MAHARASTRA ON ENGINEERING, PROCURMENT & CONSTRUCTION (EPC) BASIS CONTRACT DESIGN CHAINAGE - CH. 123+100 TO CH. 151+020

Client: National Highway ( P.W.D. ) Maharastra

Independent
LNM Infra Projects Pvt. Ltd. Bhopal
Consultant:

EPC Contractor: A.G. Construction Pvt. Ltd.

Change of scope

ABSTRACT

SR.No Description Letter No Dated Amount Remarks

Protection Work where PQC completed,128+060 to 128+210


1 BHS,128+500 to 129+770 BHS,129+950 to 130+650 447,691,540
BHS,131+740 to 132+300 BHS,136+250 to 136+290 BHS.

Protection Work where FRL Rise 126+790 to 127+450,128+983


2 to 129+513,136+420 to 136+640,140+520 to 141+300,142+370 595,134,736
to 143+540

3 MNBR-127+120 18,262,686

4 MNBR-129+275 -

5 Culvert 135+695 2,173,016

6 MNBR-136+540 595,438

7 Major Bridge @ 140+875 129,428,690

8 Scope change from Km 160+850 to 164+660 BHS 38,398,206

9 MNBR-144+245 -

FRL raised due to Flood 126+790 to 127+450,128983 to


10 129+513,136+420 to 136+640,139+330 to 139+710,140+520 to 103,243,743
141+300,142+370 to 143540 Total 3.74 Km earth work qty.

Gross Total Amount (Rs.) - -


Project: UPGRADATION OF GADCHIROLI-ASTHI ROAD TO TWO LANE WITH PAVED SHOULDERS/FOUR LANE CONFIGRATION ( PACKAGED NO- NH/IAHE/02) IN THE STATE OF
MAHARASTRA ON ENGINEERING, PROCURMENT & CONSTRUCTION (EPC) BASIS CONTRACT DESIGN CHAINAGE - CH. 123+100 TO CH. 151+020

Client: National Highway ( P.W.D. ) Maharastra

Independent
LNM Infra Projects Pvt. Ltd. Bhopal
Consultant:

EPC Contractor: A.G. Construction Pvt. Ltd.

Change of scope

ABSTRACT

SR.No Description Letter No Dated Amount Remarks

Protection Work where PQC completed,128+060 to 128+210


1 BHS,128+500 to 129+770 BHS,129+950 to 130+650 447,691,540
BHS,131+740 to 132+300 BHS,136+250 to 136+290 BHS.

Protection Work where FRL Rise 126+790 to 127+450,128+983


2 to 129+513,136+420 to 136+640,140+520 to 141+300,142+370 595,134,736
to 143+540

1,042,826,276

3 MNBR-127+120 18,262,686

4 MNBR-129+275 -

5 Culvert 135+695 2,173,016

6 MNBR-136+540 595,438

7 Major Bridge @ 140+875 129,428,690

8 Scope change from Km 160+850 to 164+660 BHS 38,398,206

9 MNBR-144+245 -

FRL raised due to Flood 126+790 to 127+450,128983 to


10 129+513,136+420 to 136+640,139+330 to 139+710,140+520 to 103,243,743
141+300,142+370 to 143540 Total 3.74 Km earth work qty.

Gross Total Amount (Rs.) - -


UPGRADATION OF GADCHIROLI-ASTHI ROAD TO TWO LANE WITH PAVED SHOULDERS/FOUR LANE CONFIGRATION ( PACKAGED NO- NH/IAHE/02) IN THE STATE OF
Project:
MAHARASTRA ON ENGINEERING, PROCURMENT & CONSTRUCTION (EPC) BASIS CONTRACT DESIGN CHAINAGE - CH. 123+100 TO CH. 151+020

Client: National Highway ( P.W.D. ) Maharastra

Independent
Consultant: LNM Infra Projects Pvt. Ltd. Bhopal

EPC Contractor: A.G. Construction Pvt. Ltd.

Change of scope

ABSTRACT

SR.No Description Letter No Dated Amount Remarks

Protection Work where PQC completed at Chainage 128+060 to


1 128+210 BHS,128+500 to 129+770 BHS,129+950 to 130+650 433,229,226 Annexure-I
BHS,131+740 to 132+300 BHS,136+250 to 136+290 BHS.

Protection Work where FRL Rise at Chainage 126+790 to


2 127+450,128+983 to 129+513,136+420 to 136+640,140+520 to 595,134,736 Annexure-II
141+300,142+370 to 143+540

Sub-Total of Protection Work: [A] 1,028,363,962

3 MNBR-127+120 15,891,290 Annexure-III

4 MNBR-129+275 39,595,098 Annexure-IV

5 Culvert 135+695 1,879,817 Annexure-V

6 MNBR-136+540 545,990 Annexure-VI

634544969.xlsx 3 OF 4
SR.No Description Letter No Dated Amount Remarks

7 Major Bridge @ 140+875 115,664,874 Annexure-VII

8 MNBR-144+240 10,354,460 Annexure-VIII

9 Scope change from Km 160+850 to 164+660 BHS 38,398,206 Annexure-IX

Sub-Total of Structure: [B] 222,329,735

FRL raised due to Flood 126+790 to 127+450,128+983 to


10 129+513,136+420 to 136+640,139+330 to 139+710,140+520 to 112,828,353 Annexure-X
141+300,142+370 to 143540 Total 3.74 Km earth work qty.

Sub-Total of Earthwork: [C] 112,828,353

Gross Total Amount (Rs.) [ A+B+C] 1,363,522,050

Gross Total after rebate 19.19% Amount (Rs.) 1,101,862,169