“Rehabilitation and up-gradation of Kundral to Wazar from km

Name of work
of Maharashtra on (EPC) mode.

Client Ministry of Road Transport And Highways (PWD- NH Division,


Authority Engineer M/S TPF Engineer Pvt. Ltd.
Contractor Ajaydeep Construction Pvt. Ltd.

ALL BARROW AREA STATU

BARROW AREA NO LOCATION SIDE OFFSET QTY

Barrow.Area No.01 CH: 83+175 LHS 500 M 92812.5


Barrow.Area No.02 CH: 78+550 RHS 800M 13500
Barrow.Area No.03 CH: 77+100 RHS 50M 14062.5
BHS
ROW CH: 76+350 10500
( cutting material)
BHS
ROW CH: 84+380 14300
( cutting material)
BHS
ROW CH: 88+050 To 88+760 51868
( cutting material)
Barrow.Area No.04 CH: 73+900 LHS 50M 2000
Barrow.Area No.05 CH: 75+000 LHS 200M 0
Barrow.Area No.06 CH: 92+640 LHS 600M 31781
BHS
ROW CH: 98+420 To 98+700 ( cutting material) 64266

Barrow.Area No.07 CH: 71+500 RHS 700M 20000


Barrow.Area No.08 CH:71+100 RHS 200M 6000
Barrow.Area No.09 CH:69+400 LHS 500M 20000
Barrow.Area No.10 CH:77+200 RHS 50M 0
Barrow.Area No.11 CH:65+600 RHS 150M 15000
Barrow.Area No.12 CH:63+920 RHS 300M 9000
Barrow.Area No.13 CH:67+500 RHS 100M 7000
Barrow.Area No.14 CH:60+140 RHS 500M 20000
Barrow.Area No.15 CH:57+900 LHS 1KM 4000
Barrow.Area No.16 CH:63+900 LHS 100M 5500
Barrow.Area No.17 CH:67+400 LHS 200M 7000
Barrow Area No. 18 CH:54+800 RHS 100M 15000
Barrow Area No. 19 CH:53+900 RHS 1.5KM 1000
Barrow Area No. 20 CH:73+950 LHS 500M 1000
Barrow Area No. 21 CH:82+100 1000
TOTAL 408590
dral to Wazar from km 52+730 to km 99+250 of NH 161A two lane with paved shoulder in the state

ys (PWD- NH Division, Gov. of Maharastra)

BARROW AREA STATUS

DATE OF SAMPLING MDD OMC CBR RESULT REMARK

6-Jun-18 1.92 8.97 13.56 APPROVED CLOSED


6-Jun-18 1.91 9.26 15.56 APPROVED CLOSED
3-Jul-18 1.919 9.1 13.54 APPROVED CLOSED

23-Jul-18 1.907 9.18 14.28 APPROVED CLOSED

23-Jul-18 1.894 8.94 13.98 APPROVED CLOSED

23-Jul-18 1.914 9.12 14.36 APPROVED CLOSED

23-Jul-18 1.898 9.2 12.78 APPROVED CLOSED


25-Sep-18 1.92 9 15.48 REJECTED CLOSED
24-Sep-18 1.91 8.3 13.71 APPROVED CLOSED

25-Sep-18 1.91 8.8 14.29 APPROVED CLOSED

26-Nov-18 1.82 8.4 13.6 APPROVED CLOSED


26-Nov-18 1.85 8.5 13.95 APPROVED CLOSED
26-Nov-18 1.91 9.4 14.14 APPROVED CLOSED
4-Dec-18 1.921 9.4 12.89 REJECTED CLOSED
30-Nov-18 1.83 8.4 13.93 APPROVED CLOSED
4-Dec-18 1.845 8.5 13.42 APPROVED CLOSED
4-Dec-18 1.85 8.3 12.89 APPROVED CLOSED
27-Nov-18 1.81 9.3 13.94 APPROVED CLOSED
5-Dec-18 1.83 8.5 14.31 APPROVED WORK IN PROGRESS
11-Dec-18 1.845 9.4 13.45 APPROVED CLOSED
15-Dec-18 1.847 8.6 12.75 APPROVED WORK IN PROGRESS
1-Mar-19 1.91 8.97 13.74 APPROVED WORK IN PROGRESS
1-Dec-19 1.901 9.01 12.84 APPROVED WORK IN PROGRESS
31-Dec-19 1.946 9.14 13.19 APPROVED WORK IN PROGRESS
31-Dec-19 1.886 9.04 12.72 APPROVED WORK IN PROGRESS
S

`
“Rehabilitation and up-gradation of Kundral to Wazar from km 52+730 to km 99+250 of NH 161A two lane with paved shoulder in the state of Maharashtra on (EPC)
Name of work
mode.

Client Ministry of Road Transport And Highways (PWD- NH Division, Gov. of Maharashtra)

Authority Engineer M/S TPF Engineer Pvt. Ltd.

Contractor Ajaydeep Construction Pvt. Ltd.

ALL BARROW AREA STATUS

Consumed Available DATE OF


BARROW AREA NO LOCATION SIDE OFFSET QTY Obtained From MDD OMC CBR RESULT REMARK
QTY QTY SAMPLING

Hangarka Gov.Lake
Barrow.Area No.01 CH: 83+175 LHS 500 M 92812.5 92812.5 6-Jun-18 1.92 8.97 13.56 APPROVED CLOSED
Deeping

B.A. @ CH 78+550 RHS


Barrow.Area No.02 CH: 78+550 RHS 800M 18961 18961 6-Jun-18 1.91 9.26 15.56 APPROVED ( Royalty Paid) CLOSED
Gut.No. 46

Farm Lake
Barrow.Area No.03 CH: 77+100 RHS 50M 8872 16872 3-Jul-18 1.919 9.1 13.54 APPROVED CLOSED
(Gat No. 131,132)

BHS
ROW CH: 76+350 ROW 12000 12000 23-Jul-18 1.907 9.18 14.28 APPROVED CLOSED
( cutting material)

BHS
ROW CH: 84+380 ROW 40000 40000 23-Jul-18 1.894 8.94 13.98 APPROVED CLOSED
( cutting material)

BHS
ROW CH: 88+050 To 88+760 ROW 47100 48000 23-Jul-18 1.914 9.12 14.36 APPROVED CLOSED
( cutting material)

Barrow.Area No.04 CH: 73+900 LHS 50M B.A. @ CH 73+900 LHS 4811 10000 23-Jul-18 1.898 9.2 12.78 APPROVED ( Royalty Paid) CLOSED

Hanegaon Gov.Lake
Barrow.Area No.05 CH: 91+750 RHS 1KM 30000 28300 25-Sep-18 1.92 9 15.48 REJECTED CLOSED
Deeping -1

Hanegaon Gov.Lake
Barrow.Area No.06 CH: 92+640 LHS 2KM 70750 70750 24-Sep-18 1.91 8.3 13.71 APPROVED CLOSED
Deeping -2

BHS
ROW CH: 98+420 To 98+700 ROW 64366 64700 25-Sep-18 1.91 8.8 14.29 APPROVED CLOSED
( cutting material)

BHS
ROW CH: 86+200 To 87+140 ROW 15000 15000 25-Sep-18 1.947 9.07 12.98 APPROVED CLOSED
( cutting material)

Barrow.Area No.07 CH: 71+500 RHS 700M 20000 20000 26-Nov-18 1.82 8.4 13.6 APPROVED CLOSED

Barrow.Area No.08 CH:71+100 RHS 200M 6000 6000 26-Nov-18 1.85 8.5 13.95 APPROVED CLOSED

Farm Lake Dornali


Barrow.Area No.09 CH:69+400 LHS 500M 10000 10000 26-Nov-18 1.91 9.4 14.14 APPROVED CLOSED
(Gat No. 73)

Farm Lake wandgir


Barrow.Area No.10 CH:77+200 LHS 50M 5000 8438 4-Dec-18 1.921 9.4 12.89 REJECTED CLOSED
(Gat No. 93)

Farm Lake Wadgaon


Barrow.Area No.11 CH:65+600 RHS 150M 15000 15000 30-Nov-18 1.83 8.4 13.93 APPROVED CLOSED
(Gat No.290)

Farm Lake Nivali


Barrow.Area No.12 CH:63+920 RHS 300M 7000 9000 4-Dec-18 1.845 8.5 13.42 APPROVED CLOSED
(Gat No. 28)

Farm Lake dornali


Barrow.Area No.13 CH:67+500 LHS 100M 5000 5000 4-Dec-18 1.85 8.3 12.89 APPROVED CLOSED
(Gat No. 81)
Farm Lake Barali
Barrow.Area No.14 CH:60+140 RHS 500M 12300 20000 27-Nov-18 1.81 9.3 13.94 APPROVED CLOSED
(Gat No. 1447)

Barrow.Area No.15 CH:59+140 RHS 1.5KM 15000 15000 5-Dec-18 1.83 8.5 14.31 APPROVED WORK IN PROGRESS

Farm Lake Barali


Barrow.Area No.16 CH:63+900 RHS 100M 5500 7500 11-Dec-18 1.845 9.4 13.45 APPROVED CLOSED
(Gat No. 708)

Farm Lake wadgaon


Barrow.Area No.17 CH:67+400 RHS 200M 7000 11250 15-Dec-18 1.847 8.6 12.75 APPROVED WORK IN PROGRESS
(Gat No. 97

Barrow Area No. 18 CH:56+850 RHS 100M 70750 70750 1-Mar-19 1.91 8.97 13.74 APPROVED WORK IN PROGRESS

Barrow Area No. 19 CH:53+900 RHS 1.5KM 1000 1000 30-Dec-19 1.901 9.01 12.84 APPROVED WORK IN PROGRESS

Barrow Area No. 20 CH:73+950 LHS 500M 1000 1000 31-Dec-19 1.946 9.14 13.19 APPROVED WORK IN PROGRESS

Barrow Area No. 21 CH:82+100 RHS 1.5KM 1000 1000 31-Dec-19 1.886 9.04 12.72 APPROVED WORK IN PROGRESS

TOTAL 586222.5 618333.5