M/S.
K J S CEMENT LIMITED
FOR- 6000 TPD CEMENT PLANT
CONTRACTORDESCRIPTIONSL.
NO.
DATE : 28.03.12
M/S. JK ENGINEERING
R.A. BILL-07 Dated: 10.02.12 (PIPE LINE WORK AT PH BLDG. & COAL MILL AREA)
DESCRIPTION
UNIT
RATE
(Rs.)/UNIT
CLAIMED
QTY.
THIS BILL
QTY.
DIFF.
AMOUNT
CLAIMED (Rs.)
PAYABLE
AMOUNT (Rs.)
DIFF.
(Rs.)
MS-Pipe Erection-1''
MTR
48.50
MS-Pipe Erection-3/4''
MTR
48.50
MS-Pipe Erection-2''
MTR
97.00
GI-Pipe Erection-3/2''
MTR
72.75
GI-Pipe Erection-5/2''
MTR
121.25
MS-Bend Erection-3/4''
NOS
110.00
MS-Tee Erection-3/4''
NOS
120.00
MS-Bend Erection-1''
NOS
110.00
MS-Tee Erection-1''
NOS
120.00
Bend Erection-3/2''
NOS
165.00
MS-Tee Erection-3/2''
NOS
180.00
MS-Bend Erection-2''
NOS
220.00
MS-Bend Erection-5/2''
NOS
275.00
MS-Tee Erection-2''
NOS
240.00
Gate Valve Erection-1''
NOS
250.00
Gate Valve Erection-5/2''
NOS
250.00
17 Gate Valve Erection-3/2''
NOS
250.00
361.500
100.000
115.500
122.500
72.500
23.000
7.000
54.000
10.000
10.000
14.000
14.000
5.000
1.000
13.000
8.000
2.000
361.500
100.000
115.500
122.500
72.500
23.000
7.000
54.000
10.000
10.000
14.000
14.000
5.000
1.000
13.000
8.000
2.000
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
17532.75
4850.00
11203.50
8911.88
8790.63
2530.00
840.00
5940.00
1200.00
1650.00
2520.00
3080.00
1375.00
240.00
3250.00
2000.00
500.00
17532.75
4850.00
11203.50
8911.88
8790.63
2530.00
840.00
5940.00
1200.00
1650.00
2520.00
3080.00
1375.00
240.00
3250.00
2000.00
500.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
18 Gate Valve Erection-1/2''
NOS
250.00
19 Hose Pipe Erection
NOS
31.00
20 Erection of Reducer 2''-1''
NOS
140.00
8.000
17.000
1.000
8.000
17.000
1.000
0.00
0.00
0.00
2000.00
527.00
140.00
2000.00
527.00
140.00
0.00
0.00
0.00
Erection of Reducer 5/2''3/2''
NOS
210.00
1.000
1.000
0.00
210.00
210.00
0.00
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
21
REMARKS
Erection of Reducer 3/2''3/4''
NOS
140.00
3.000
3.000
0.00
420.00
420.00
0.00
Union Flange Erection-1''
NOS
30.00
Erection of Flange-3/2''
NOS
30.00
Erection of Flange-3/4''
NOS
30.00
Fixing of Insert Plate
NOS
275.00
11.000
10.000
13.000
52.000
11.000
10.000
13.000
52.000
0.00
0.00
0.00
0.00
330.00
300.00
390.00
14300.00
330.00
300.00
390.00
14300.00
0.00
0.00
0.00
0.00
27 Fixing of Anchor Fastners
NOS
80.00
156.000
156.000
0.00
12480.00
12480.00
0.00
28
29
30
31
32
Fabrication of Bag Filter
KGS
5800.00
Erection of Bag Filter
KGS
6000.00
Fabrication of Hopper
KGS
7000.00
Erection of Hopper
KGS
7000.00
Hold Release R.A. Bill-06
..
..
62.600
62.60
4607.50
4607.50
.
62.600
62.600
4607.500
4607.500
.
0.00
0.00
0.00
0.00
.
363.08
375.60
32252.50
32252.50
92000.81
363.08
375.60
32252.50
32252.50
92000.81
0.00
0.00
0.00
0.00
0.00
264755.24
264755.24
0.00
22
23
24
25
26
ABOVE SUM
Net Payable Amount = Rs. 264755.24
Net Payable Amount -- Rs.Two Lac Sixty Four Thousand Seven Hundred Fifty Five and Twenty Four Paisa Only
TRUSST ENGINEERS
M/S. K J S CEMENT LIMITED
FOR- 6000 TPD CEMENT PLANT
CONTRACTORDESCRIPTION-
DATE: 05.05.12
M/S. JK ENGINEERING
R.A. BILL-08 DATED : 16.03.12 ( MAN POWER SUPPLY WORK )
SL.
NO.
DESCRIPTION
RATE
(Rs.)
CLAIMED
QUANTITY
CHECKED
QUANTITY
DIFF.
(Excess)
AMOUNT
CLAIMED (Rs.)
AMOUNT
CHECKED (Rs.)
EXCESS
/ HOLD
Fitter
450.00
18.750
18.750
0.000
8437.50
8437.50
0.00
Welder
250.00
21.500
21.500
0.000
5375.00
5375.00
0.00
Rigger
250.00
27.120
27.120
0.000
6780.00
6780.00
0.00
Grinder Man
225.00
1.370
1.370
0.000
308.25
308.25
0.00
Khalashi
200.00
29.870
29.870
0.000
5974.00
5974.00
0.00
Helper
200.00
14.250
14.250
0.000
2850.00
2850.00
0.00
29724.75
29724.75
0.00
ABOVE SUM
Net Payable Amount = Rs.
REMARKS
29724.75
Net Payable Amount -- Rs. Twenty Nine Thousand Seven Hundred Twenty Four & Seventy Five Paisa Only
TRUSST ENGINEERS
M/S. K J S CEMENT LIMITED
FOR- 6000 TPD CEMENT PLANT
CONTRACTORDESCRIPTIONSL.
NO.
DATE: 04.05.12
M/S. JK ENGINEERING
R.A. BILL-09 DATED : 06.03.12 ( MISCELLANEOUS AIR PIPE LINE WORK )
DESCRIPTION
Air Pipe Line Work from Clinker Cooler to
Un-burnt Silo
Water Line Work in Clinker Cooler Area
Bag Filter Air Pipe Line Work at GF
Air Pipe Line Work from Un-burnt Silo to
Clinker Silo
Nitrogen Pipe Line Work at 36.00 MTR Floor
Level in Coal Mill Area
Inserts & Anchor Fixing at Burner Platform
ABOVE SUM
AMOUNT
CLAIMED (Rs.)
AMOUNT
CHECKED (Rs.)
EXCESS
AMOUNT (Rs.)
REMARKS
72093.71
70745.71
1348.00
Excess Amount
72093.71
70745.71
1348.00
Net Excess Amount = Rs.
1348.00
Net Payable Amount = Rs.
70745.71
Net Payable Amount -- Rs. Seventy Thousand Seven Hundred Forty Five & Seventy One Paisa Only
TRUSST ENGINEERS