You are on page 1of 6

Page 1 of 6

NORTHERN RLY
FEROZPUR DIVISION-
ENGINEERING
Divisional Railway Manager
Office, Near Railway Officers
Club
Firozpur, 152001
Punjab, India

Letter No: FEROZPUR DIVISION-ENGINEERING / 124-2021-22-ADEN-II-


Dated: 25/03/2022
FZR / 01259280051677

M/s CHANDAN KUMAR ROY-JALANDHAR


VPO. UPPAL KHALSA, UPPAL JAGIR, JALANDHAR PHILLOUR
JALANDHAR- 144039
Punjab, India

Sub: Letter Of Acceptance

Ref: 1. Tender No. 124-2021-22-ADEN-II-FZR closing date 09-02-2022 15:00 for Crossing
of 800 MM dia RCC sewer Pipe Line Passing through 1200 mm MS encasing pipe &
1400 mm dia Ms casing pipe under the Railway Track near level crossing no C-12 at
Km 18/1-2 on JUC_NRO section under ADEN-II/FZR
2. Your bid ID 13432244 dated 09/02/2022 14:19

The Competent Authority has accepted your offered rates in connection with the subject work. The
total cost of the work at the accepted rates works out to Rs. 6829437.72 (Rupees Sixty-Eight Lakh
Twenty-Nine Thousand Four Hundred And Thirty-Seven Rupees And Seventy-Two Paise Only)

A sum of Rs.132200 deposited as Earnest Money vide IREPS reference ID PE660514534583 has been
retained towards initial Security Money for due and faithful fulfillment of the contract, and the balance
Security Money will be recovered from the progressive bills @ 6 % of the bill amount till it reaches 5 % of
the contract value in terms of clause 16(1) of GCC July 2020.

You are requested to submit Performance Guarantee in the form as given in Clause 16(4) of GCC July
2020 equivalent to 3 % of the contract value amounting to Rs. 204883.13 (Rupees Two Lakh Four
Thousand Eight Hundred And Eighty-Three Rupees And Thirteen Paise Only) within 21 days from the
date of issue of Letter of Acceptance, valid up to stipulated date of completion plus 60 days so that
contract agreement can be executed. However, a penal interest of 12% per annum shall be charged for the
delay beyond 21(Twenty one) days, i.e. from 22nd day after the date of issue of LOA. Further, if the 60th
day happens to be a declared holiday in the concerned office of the Railway, submission of PG can be
accepted on the next working day.

The entire work shall be completed within 4 month from the date of issue of Letter of Acceptance.

Estimate No.: 72/2021-22

Allocation No. : Deposit Work

Condition 1 : The overall cost of this work is below by more than 10.00% hence the rates of all items of
this work may not be used for future estimation & comparison in isolation till completion of this work.

Condition 2: The quantities of all USSOR Chapters & NS-6 are more than 10.00% below so these items
should be utilized as maximum as possible and should not be reduced without prior approval of tender
accepting authority.

All Other terms and conditions, as stipulated in the tender documents shall be applicable.

DEVENDRA KUMAR
DENTrack
Digitally Signed
View Signature Details

Awarded Quantities And Rates

Item Item Desc Item Item Qty Unit Rate Escl. Advt.Value Bid Rate/ Bid Amount (Rs)
Sno. Code Qty Unit (Rs) (%) (Rs) Unit Rate
%
Schedule A-USSOR ITEMS-2010 (Item Directory - NR-HQ-USSOR-2010-1-Ver-4) 3093898.13 10.00 2784508.32
Below
1 Ch-1 Earth work View Details 8.16 43400.07
2 Chapter-02 carriage of material View Details 1.55 59612.73
3 Chapter-03 Plain concrete View Details 22.00 644100.94
4 Chapter-04 RCC work View Details 22.30 1071741.87
5 Chapter-05 Brick Work View Details 32.65 237155.52
6 Chapter-08 steel and aluminium work View Details 22.27 363178.58
7 Chapter-09 Flooring paving and Dado View Details 9.01 178111.98
8 Chapter-10 Roofs and ceiling View Details 10.21 3461.50
9 Chapter-11 Finishing and Masonary View Details 7.51 93976.53
Chapter-12 Painting polishing and
10 View Details 10.24 26236.68
varnishing

https://ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublish... 26-03-2022
Page 2 of 6

11 Chapter-13 water supply View Details 9.91 23576.40


12 Chapter-14 Drainage and sewerage View Details 0.61 42792.31
(-)
13 Chapter-15 sanitary and installations View Details 9689.06
5.40
Chapter-19 Bridge works
14 View Details 15.00 16028.70
substructure
Chapter-23 Roads and platform
15 View Details 6.61 280835.26
works
Schedule Totals 2784508.32
%
Schedule B-NS ITEMS (Item Directory - Not Applicable) 3517329.91 15.00 4044929.40
Above
1 NS ITEMS View Details At Par 3517329.91
Schedule Totals 4044929.40
Total Value 6611228.04 6829437.72
Rebate on Total Value (%) 0.00
Net Bid Value 6829437.72

Item Breakup
Schedule A-USSOR ITEMS-2010

Item - 1 Ch-1 Earth work

S No. Item No Description of Item Unit Qty Rate Amount

Earth work in excavation as per approved drawings and dumping at


embankment site or spoil heap, within railway land, including 50m lead
and 1.5m lift, the lead to be measured from the centre of gravity of
excavation to centre of gravity of spoil heap: the lift to be measured
from natural ground level and paid for in layers of 1.5m each,
including incidental work, as per specifications-in

1 011011 All kinds of soils cum 280 81.36 22780.80

Extra over item 011010 for excavation in foundations for buildings and
bridges to cover dressing to neat dimension and plumbing sides etc.
2 012010 cum 200 8.70 1740.00
Note : Dressing under this item is payable for the total quantity of
excavation in foundation and not partly

Extra for watering and ramming earth in foundation and floors in 15cm
3 012030 layers. Note : This item is payable where ramming is not included in cum 80 15.40 1232.00
the original rate for earthwork in filling.

Removal of excavated/slip earth/ debris/ malba from the site of works


to any other place outside Railway land/premises, including all
excavations, handling, re-handling, loading, unloading and leading,
etc. all labour and material as a complete job. Removal of Earth (all
kinds of soils)/ROCKS, BOULDERS including mud/slush, slipped earth
4 013140 in catch water drains, side drains, over berms in cutting, water way of cum 150 95.82 14373.00
bridges, over coping of toe/breast/retaining walls etc. including
crossing of nallah, railway tracks, making/repairing approach roads if
required, all lead, lift, ascent, descents, or any other obstruction. Earth
spoils to be dumped outside the cutting or railway embankments as
per direction of Engineer in charge

Total 40125.80

Item - 2 Chapter-02 carriage of material

S No. Item No Description of Item Unit Qty Rate Amount

Leading ballast, kankar, brickbats, stone-chips, shingle, stone


boulders, block kankar, pitching stones, rubble stones, laterite, coal,
1 021090 surkhi, dry mortar, sand, moorum, earth, manure or sludge, ashes, cum 100 98.26 9826.00
lime, debris, muck, malba, etc. for lead upto 25 km. Note : Lead under
this item is payable when the same exceeds 500m.

Hiring and operating Multi-Utility vehicle of loading capacity one MT


with sitting capacity of 4/6 persons, 4 strokes, 4 cylinders engine,
factory-built metal body, cargo box type or passenger cabin type or
both (with 24 hours availability), including cost of fuel, lubricants,
major/minor repairs, salary of driver, toll tax, all other tax complete,
2 021430 Each/month 2 24438.42 48876.84
operation and maintenance including running upto 1200 km in a
month. The vehicle shall run on pucca, kutcha road and along the
track. The contractor shall arrange road permit for vehicles for all the
States of operation, as per instructions of engineer in-charge and
vehicle shall not be more than three years old.

Total 58702.84

Item - 3 Chapter-03 Plain concrete

S No. Item No Description of Item Unit Qty Rate Amount

Providing and laying in position cement concrete of specified


proportion excluding cost of cement, centering and shuttering - All
works upto Plinth level :

1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40mm


1 031014 cum 30 1746.01 52380.30
nominal size)

Providing and laying cement concrete, up to plinth in retaining walls,


walls (any thickness) including attached plasters, columns, pillars,
posts, struts, buttresses, string or lacing courses, parapets, coping,
bed blocks, anchor blocks, plain window sills, fillets etc, excluding the
cost of cement and of shuttering, centering.

1:3:6 (1 cement : 3 sand : 6 graded stone aggregate 20mm nominal


2 031021 cum 15 2193.34 32900.10
size)

1:1.5:3 (1cement : 1.5 sand : 3 graded stone aggregate 20mm


3 031024 cum 16 2137.59 34201.44
nominal size)

Centering and shuttering including strutting, propping etc. and


removal of form work for :

4 031061 Foundations, footings, bases of columns Sqm 25 121.03 3025.75

https://ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublish... 26-03-2022
Page 3 of 6

Supply and using cement at worksite :

5 033063 PPC Tonne 78 5198.00 405444.00

Total 527951.59

Item - 4 Chapter-04 RCC work

S No. Item No Description of Item Unit Qty Rate Amount

Providing and laying in position M 20 Grade concrete for reinforced


concrete structural elements but excluding cost of centering,
shuttering, reinforcement and Admixtures in recommended proportion
(as per IS:9103) to accelerate, retard setting of concrete, improve
workability without impairing strength and durability as per direction of
Engineer in charge

All work upto plinth level, including raft foundation of washable aprons,
1 041011 cum 35 2422.38 84783.30
HS tank, pile cap, footings of FOB, and Platform shelter etc.

2 041012 All work in buildings above plinth level upto floor two level. cum 25 2645.23 66130.75

Centering and shuttering including strutting, propping etc. and


removal of form for :

Suspended floors, roofs, landings, balconies, FOB slabs, walkway slabs


3 042013 Sqm 100 185.57 18557.00
and access platform

Lintels, beams, plinth beams, bed blocks, girders, bressumers and


4 042014 Sqm 50 163.20 8160.00
cantilevers

5 042015 Columns, pillars, , posts and struts Sqm 150 240.50 36075.00

Providing, hoisting and fixing in position upto floor two level M20
Grade precast RCC work including setting in cement mortar 1:3 (1
cement : 3 coarse sand) and finishing smooth with 6mm thick cement
plaster 1:3 (1 cement : 3 fine sand) on exposed surfaces complete
including cost of centering, shuttering, finishing, Admixtures in
recommended proportion (as per IS:9103) to accelerate, retard setting
of concrete, improve workability without impairing strength and
durability, excluding cost of cement and steel reinforcement, as per
approved plan & direction of Engineer incharge.

In blocks of complicated design such as C blocks of cabins, Platform


6 043019 cum 40 4670.40 186816.00
walls etc.

Supplying Reinforcement for R.C.C. work including straightening,


cutting, bending, placing in position and binding all complete.

7 045014 High yield strength deformed bars Kg 10000 47.58 475800.00

Total 876322.05

Item - 5 Chapter-05 Brick Work

S No. Item No Description of Item Unit Qty Rate Amount

Brick work with non-modular (FPS) bricks of class designation 7.5 in


foundation and plinth in :

1 051015 Cement mortar 1:6 (1 cement : 6 fine sand) cum 80 2143.06 171444.80

Extra over item 051010 & 051020 for brick work in superstructure
2 051040 cum 55 133.42 7338.10
beyond plinth level upto floor two level :

Total 178782.90

Item - 6 Chapter-08 steel and aluminium work

S No. Item No Description of Item Unit Qty Rate Amount

Structural steel work welded in built up sections, trusses and framed


work, girders, stagings, racks, etc including cutting, bending,
straightening, hoisting, fixing in position, including applying a priming
coat of approved steel primer, complete - upto 6m height above GL

1 081031 In RSJ, tees, angles and channels Kg 1500 75.92 113880.00

2 081032 In flats, plates , round or square bars Kg 2500 73.26 183150.00

Total 297030.00

Item - 7 Chapter-09 Flooring paving and Dado

S No. Item No Description of Item Unit Qty Rate Amount

Cement concrete flooring 1:2:4 (1cement: 2coarse sand: 4graded


stone aggregate) finished with a floating coat of neat cement including
cement slurry, but excluding the cost of nosing of steps etc. complete

1 092012 40mm thick with 20mm nominal size stone aggregate Sqm 150 120.99 18148.50

Supplying and laying interlocking pre-cast CC block pavers of approved


design factory manufactured of specified grade cement concrete on
passenger platform, foot paths, circulating area etc. including setting
in position over 25mm thick bedding layer of fine sand, filling the
joints with fine sand, leveling including compaction as per IS:15658

2 098023 120mm thick blocks of M40 grade for heavy traffic Sqm 150 968.28 145242.00

Total 163390.50

Item - 8 Chapter-10 Roofs and ceiling

S No. Item No Description of Item Unit Qty Rate Amount

Providing and fixing on wall face unplasticised - Rigid PVC single


socketed rain water pipes conforming to IS: 13592 Type A including
jointing with seal ring conforming to IS: 5382 leaving 10mm gap for
thermal expansion.

1 108162 110mm dia. Metre 6 182.18 1093.08

Providing and fixing on wall face unplasticised - PVC moulded bend and
shoe for unplasticised-Rigid PVC rain water pipes conforming to

https://ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublish... 26-03-2022
Page 4 of 6

IS:13592 Type A including jointing with seal ring conforming to


IS:5382 leaving 10mm gap for thermal expansion

2 108182 Bend 87.5o, 110mm dia bend Each 2 236.39 472.78

3 108184 Shoe (Plain), 110mm dia shoe Each 2 294.46 588.92

Providing and fixing unplasticised-PVC pipe clips of approved design to


unplasticised-PVC rain water pipes by means of 50x50x50mm hard
wood plugs, screwed with M.S. screws of required length including
cutting brick work and fixing in cement mortar 1:4 (1 cement : 4
coarse sand) and making good the wall etc. complete

4 108192 110mm Each 6 164.34 986.04

Total 3140.82

Item - 9 Chapter-11 Finishing and Masonary

S No. Item No Description of Item Unit Qty Rate Amount

12 mm cement plaster of mix -

1 111011 1:4 (1cement: 4 fine sand) Sqm 600 57.39 34434.00

15mm cement plaster on rough side of single or half brick wall finished
a floating coat of neat cement of mix -

2 111081 1:3 (1cement: 3fine sand) Sqm 70 76.63 5364.10

Pointing on brick work with cement mortar 1:3(1cement: 3fine sand)

3 114011 Flush/Ruled/Struck or weathered pointing Sqm 70 42.14 2949.80

Finishing walls with Acrylic Smooth Interior paint of required shade on


new work (Two or more coats applied @ 1.67 ltr/10 sqm over and
4 115170 Sqm 600 74.44 44664.00
including base coat of water proofing cement paint applied @ 2.20
kg/10sqm

Total 87411.90

Item - 10 Chapter-12 Painting polishing and varnishing

S No. Item No Description of Item Unit Qty Rate Amount

Finishing with Epoxy paint (two or more coats) at all locations


prepared and applied as per manufacturer's specifications including
appropriate priming coat, preparation of surface etc. complete

1 121041 On steel work Sqm 220 89.63 19718.60

Painting with synthetic enamel paint of approved brand and


manufacture to give an even shade

2 121051 Two or more coats on new work Sqm 100 40.81 4081.00

Total 23799.60

Item - 11 Chapter-13 water supply

S No. Item No Description of Item Unit Qty Rate Amount

Providing and fixing G.I. pipes complete with G.I. fittings and clamps,
including cutting and making good the walls etc. Internal work -
Exposed on wall

1 131131 15 mm dia. nominal bore Metre 50 131.57 6578.50

2 131133 25 mm dia. nominal bore Metre 25 221.72 5543.00

Providing and fixing medium grade G.I. pipes complete with G.I.
fittings and clamps, including cutting and making good the wall etc.
Concealed pipe including painting with anti corrosive bitumestic paint,
cutting chase and making good the wall

3 131141 15 mm dia. nominal bore Metre 25 170.10 4252.50

Providing and fixing unplasticised PVC connection pipe with brass


unions: 45 cm length

4 132141 15 mm nominal bore Each 2 54.85 109.70

Providing and fixing PTMT bib cock of approved quality and colour

5 134011 15mm nominal bore, 86mm long. Weighing not less than 88 gms Each 1 166.16 166.16

Providing and fixing PTMT stop cock of approved quality and colour

6 134021 15mm nominal bore, 86mm long. Weighing not less than 88 gms Each 1 166.16 166.16

Providing and fixing PTMT angle stop cock 15mm nominal bore.
7 134070 Each 2 218.43 436.86
Weighing not less than 85 gms

Providing and fixing G.I. Union in G.I. pipe including cutting and
threading the pipe and making long screws etc. complete (new work)

8 136131 15mm nominal bore Each 5 94.34 471.70

Providing and placing on terrace/staging (at all heights) polyethylene


water storage tank ISI : 12701 marked with cover and suitable locking
9 136150 Litre 500 6.43 3215.00
arrangement and making necessary holes for inlet, outlet and overflow
pipes but without fittings and the base support for tank

Hoisting, fitting and fixing in position plastic moulded water storage


tank including making connection of intake, delivery, outlet and
overflow .pipes etc. with all lead and lift upto all stories. Cost of
tanks/fittings to be paid separately

10 138042 500 ltr capacity tank Each 1 511.06 511.06

Total 21450.64

Item - 12 Chapter-14 Drainage and sewerage

S No. Item No Description of Item Unit Qty Rate Amount

Providing and laying non-pressure NP3 class (medium duty ) R.C.C.


pipes including bends etc with collars jointed with stiff mixture of

https://ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublish... 26-03-2022
Page 5 of 6

cement mortar in the proportion of 1:2 (1cement: 2fine sand)


including testing of joints etc. complete up to 800mm dia.

1 142037 800mm dia. R.C.C. pipe Metre 22.86 1860.58 42532.86

Total 42532.86

Item - 13 Chapter-15 sanitary and installations

S No. Item No Description of Item Unit Qty Rate Amount

Providing and fixing water closet squatting pan (Indian type W.C. pan)
with 100mm sand cast iron P or S trap, 10litre low level white P.V.C.
flushing cistern with manually controlled device (handle lever)
conforming to IS : 7231, with all fittings and fixtures complete
including cutting and making good the walls and floors wherever
required

White Vitreous China Orissa pattern W.C. pan of size 580x440-mm


1 151011 Each 1 3057.59 3057.59
with integral type foot rests

Providing and fixing white, vitreous china wash basin, including making
all connections but excluding the cost of fittings

2 151281 Flat back wash basin of size 630x450mm Each 1 817.49 817.49

Providing and fixing mirror of 5.5 mm thickness of float Glass (of


approved Quality) required shape and size with plastic moulded frame
of approved make and shade with 6mm thick hard board backing

3 152124 Rectangular shape 1500x450 (outer dimension) Each 1 1750.45 1750.45

Providing and fixing PTMT liquid soap container 109mm wide, 125mm
high and 112mm distance from wall of standard shape with bracket of
4 153300 Each 1 185.84 185.84
the same materials/ with snap fittings of approved quality colour and
make, weighing not less than 105gms

Providing and fixing PTMT shelf 440mm long, 124mm width and 36mm
5 153330 height of approved quality, colour and make weighing not less than Each 1 501.91 501.91
300gms

Providing and fixing Towel rail (C.P.)brass15 mm dia x 600 mm long


6 153410 Each 2 413.49 826.98
having approx. wt.500 gm

Providing and fixing C P brass grating with openable lid :

Grating 100 mm nominal dia. and 12 mm. high domed shape having
7 153471 Each 1 81.70 81.70
wt. not less than 25 gms

Providing and fixing S.C.I. trap with 10 cm inlet and 10 cm outlet of


self cleansing design with S.C.I. screwed down or hinged grating with
8 153630 Each 1 356.23 356.23
or without vent arm complete, including cost of cutting and making
good the walls and floors

Providing and fixing 110mm dia PVC soil, waste and vent pipes
9 154010 Metre 10 205.50 2055.00
including jointing and cost of spun yarn and sand etc. complete

Providing and fixing 110 mm PVC bend of the required degree with
access door inclusive of 3mm thick bitumastic felt washer, bolts and
10 154110 Each 3 89.16 267.48
nuts, complete, including jointing and cost of spun yarn and sand etc.
complete

Providing and fixing 110mm dia PVC terminal guard including jointing
11 154120 Each 1 195.13 195.13
and cost of spun yarn and sand etc, complete

Providing and fixing 110 mm PVC collar (loose socket) including


12 154130 Each 2 73.17 146.34
jointing and cost of spun yarn and sand etc. complete

Total 10242.14

Item - 14 Chapter-19 Bridge works substructure

S No. Item No Description of Item Unit Qty Rate Amount

Conducting laboratory Tests on collected soil samples as per relevant


IS code

1 191141 Moisture contents/ Dry density Each 1 1161.50 1161.50

2 191142 Atterberg Limit Each 1 1161.50 1161.50

3 191143 Specific Gravity Each 1 580.75 580.75

4 191144 Grain size analysis including Hydrometer analysis Each 1 1161.50 1161.50

5 191145 Direct Shear Test Each 1 2323.00 2323.00

6 191146 Natural density Each 1 580.75 580.75

7 191147 Consolidation test Each 1 2323.00 2323.00

8 191148 Unconfined compression test Each 1 2323.00 2323.00

9 191149 Tri-axial test Each 1 2323.00 2323.00

Total 13938.00

Item - 15 Chapter-23 Roads and platform works

S No. Item No Description of Item Unit Qty Rate Amount

Providing and laying water bound macadam with specified stone


aggregate, stone screening and binding material including screening,
sorting, spreading to template and consolidation with power road roller
of 8 to 10 tonne capacity etc. complete.

Base course with 63mm to 45mm size including stone screening


1 231042 cum 50 1297.96 64898.00
13.2mm size

Providing and applying tack coat using bitumen emulsion (Rapid


setting) complying with IS: 8887- 1995, spraying the bitumen
emulsion with mechanically operated spray unit, cleaning and
preparing the existing road surface as per specification

2 233011 On W.B.M. @ 0.4kg/ sqm Sqm 250 20.72 5180.00

https://ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublish... 26-03-2022
Page 6 of 6

4cm thick bitumastic sheet with hot bitumen of approved quality using
stone chippings (60% 12.5mm nominal size and 40% 10mm nominal
size) 2.60cum and coarse sand 2.60cum of road surface and with
478kg bitumen per 100sqm of road surface over a tack coat including
consolidation with road roller of 8 to 10tonne etc. complete (tack coat
to be paid separately)

With paving bitumen 80/ 100 heated and then mixed with solvent at
3 234021 Sqm 500 386.69 193345.00
the rate of 70grams per kg. of asphalt

Total 263423.00

Schedule B-NS ITEMS

Item - 1 NS ITEMS

S No. Item No Description of Item Unit Qty Rate Amount

NS-1) Thrusting of MS casing pipe by pushing method including the


cost of M.S. pipe1400mm dia made out of 20mm thick MS sheet and
fabricated as per IS : 3587 from steel plate confirming to IS :2062
complete as per approved Divl. Drg. with all L & M. The item includes
the cost for using contractor, s own cutting edge, hydraulic jacks,
welding work lighting arrangement and thrust bed etc. The item also
includes all lead ,lift ,loading, Unloading and excavation work inside
the MS pipe with thrusting and pulling out/ removing excavated earth
from the pipes etc. The item also includes the cost for working in soil ,
sub soil below sub soil water level condition (all types of soil
1 1 conditions ) including the cost of pumping / bailing out water in case of Metre 22.86 64259.04 1468961.65
necessity. All the material will be approved by ADEN / DEN in charge
at site . The work shall be complete in all respects with all labour ,
material , T & P, misc. and incidental works related to the job The
work shall be carried out as per directives of engineer incharge at site
to his entire satisfaction as per approved drawing.Nothing extra will be
paid on any account . The contractor will provide and apply
polyurethene coating confirming to ASTM D-16 type-V classification by
applying two component elestomaric aromatic polyurethene membrone
on out side of the MS casing pipe. The thickness of coating should be
1500-2000 micrown ( As per RDSO specification No M&C/PCM/111/88)

NS-2) Mfg., supplying, various M.S. pipe of 1200/1400 /1600 mm


internal dia with 16/20/22mm thick at site of work including all labour
material ,T&P, loading, leading, unloading, handling rehandling,
2 2 Kg 26990.25 59.42 1603760.66
lowering, lifting, crossing of any nallah, tracks or any type of
obstructions, taxes, octroi etc. complete job ( Nothing extra will be
paid on this account what so ever the case may be)

NS-3) Jointing and laying of MS casing pipe of 1200/1400/1600mm


internal dia by cut and cover method at given site under railway track
and hook up with the main pipe line on both sides in accordence with
supply of tools, equipments, tackles, manpower etc. including cutting,
grinding, levelling, radio graphically welding, testing of pipe line,
cleaning & painting to inner and outer surface of pipe, making thrust
pit/bed and receiving pit of required size, open / close timbering in
3 3 Metre 22.86 7582.46 173335.04
trenches etc. & all other incidental works to complete the job as per
approved drawing or as per instrucions of site engineer with all labour,
material, T&P, loading , leading, unloading, handling rehandling,
lowering, lifting, crossing of any nallah, track or any type of
obstructions taxes, octrio etc. complete job.This item does not include
the cost of pipe which will be paid seperately. ( Nothing extra will be
paid on this account what so ever the case may be ).

NS-4) P & F pipe line indicator boards (retro reflective type) including
making foundation complete in all respects as directed by Engineer
4 4 incharge. Nothing extra will be paid on any acount. The payment of Each 4 4607.13 18428.52
cement will be paid seperately under SOR item as per actual
consumption of cement as per std. specifications.

NS-5) Providing and seal on 1200 & 1400 mm dia M.S. pipe of 20mm
5 5 thick 50 mm dia G.I. vent pipe with screen complete as directed by Each 2 18782.25 37564.50
Engineer Incharge.

NS-6) P&F high density polythene spacer of required size at distance of


2.0m apart to avoid contact of casing pipe & carrier pipe in between
6 6 Each 46 4139.99 190439.54
MS casing pipe & RCC carrier pipe as approved & direction of engineer
incharge. Nothing extra will be paid on any account

NS-7) Providing lighting arrangement during night block to be availed


between 20.00 Hrs. (night) to 6.00 Hrs (morning) in the section of
ADEN / CONCERNED on hiring basis with contractor's generator of
minimum 5KVA capacity 6 halogen lamps of 500 watt operation and
7 7 maintenance of generator set & Halogen lamps with his own labour, Hour 50 496.80 24840.00
T&P, transportation etc. The payment will be done for only that day
when PWI/Incharge or IOW/Incharge actually require & put up his
requirement. Stand by arrangement has to be ensured by agency for
any possible failure as block may be burst on this account only.

Total 3517329.91

https://ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublish... 26-03-2022