You are on page 1of 3

GOVERNMENT OF WEST BENGAL

OFFICE OF THE DIVISIONAL FOREST OFFICER


WORKING PLAN (SOUTH) -1 DIVISION
Michael Madhusudan Nagar, Midnapore
PaschimMedinipur, PIN- 722122
________________________________________________________________________________________________________________________________
Memo No. 642 /10-1, E-Tender Dated: 06/10/2023 ,Midnapur

Notice Inviting e-Tender No. WBFOR/WPS-1/Conventional Survey of 121.30 km. Forest Land at 4 no.
Divisions under the Western Circle/NIT10(e)/23-24

NOTICE INVITING e-TENDER


Memorandum No. 5400-F(Y)
dated 25-06-2012

Conventional Survey of 121.30 km. Forest Land at 4 no. Divisions under the Western Circle during
F.Y. 2023-24 under SPAP by Working Plan (S)-I Division .

e- tendering ONLINE

TABLE I
Schedule of Dates for e-Tendering

Sl. no Activity Date&Time


1. Tender Publishing date & time 06.11.2023 at 12:00 P.M.
2. Document Download start date & time 06.11.2023 at 5:00 P.M.
3. Bid submission start date & time 06.11.2023 at 5:00 P.M.
4. Bid submission end date & time 13.11.2023 at 5:00 P.M.
5. Technical Bid opening date & time 17.11.2023 at 12:00 P.M.
6. Uploading of Technical Bid Evaluation sheet After evaluation of Technical Bid
7. Financial Bid opening date & time After evaluation of Technical Bid
8. Uploading of Financial Bid evaluation sheet After technical & financial bid evaluation and
approval by the Competent Authority.
9. Publishing the Name of bidder who will get Work order will be issued after signing of
the contract on approval agreement, deposit of security and on availability
10. Issuance of Work order/ Letter of Intent/ Monitor the e-procurement portal, Government of
Award Of Contract West Bengal

1
SCHEDULE I

Length of Rate/km. Expected


Details of work Location
Forest (in Rs.) Estimated date of
Cluster including /Delivery point.
Boundary Cost (in Rs.) completion
Specifications
(in km.) of the work

At 4 no. Forest
Divisions of 121.30 2332.20 2,82,895.86
Western Circle

2
Detailed Estimate for Conventional Survey of 121.30 km. Forest Land at 4 no. Divisions under the
Western Circle during F.Y. 2023-24 under SPAP by Working Plan (S)-I Division

Sl. Rate per Amount


Particulars of Work Unit Quantity
No. Unit (Rs.) (Rs.)

SUB TOTAL 1,956.87

Total 2,309.11

GRAND TOTAL 2332.20


Cost of survey per Km including camping and supervision work for 1 km or 5 no. RCC pillars @
Rs. 2332.20
200 mt. intervals:

Km. 121.30 2332.20 2,82,895.86