Finance Controller/Addl.

Chief Executive Officer/Chief Executive Officer


Vide this office letter no. 1207/UPEIDA/19/1718/Tech dated 18.05.2022 (F/A) in-principal
approval was accorded to Team Leader, AE for issuance of change of scope notice to EPC contractor
for providing 3 no’s of PUP, PUP at km 76+250, PUP at km 82+335 & PUP at km 84+560 in Pkg-II of
Gorakhpur Link Expressway.
In compliance to above Team Leader, Authority’s Engineer, M/s TPF Getinsa Eurostudios,
S.L. vide his letter no. TPF/AE/TL/SCIA037/EPC/2022-23/1032 Dt. 23.05.2022 (F/B) issued change of
scope notice to contractor for providing 3 no’s of PUP, PUP at km 76+250, PUP at km 82+335 & PUP
at km 84+560 in Pkg-II of Gorakhpur Link Expressway.
The Contractor vide his letter no: DBL/UPEIDA/GLE/PKG-II/2385 dated 27.06.2022 (F/C)
has submitted the CoS Cost Estimate for providing 3 no’s of PUP, PUP at km 76+250, PUP at km
82+335 & PUP at km 84+560 in Pkg-II of Gorakhpur Link Expressway.
After scrutiny vide his TPF/AE/TL/SCIA037/EPC/2023-24/2071 Dt. 01.07.2023 (F/D) Shri
Nigmanand Adhikari, Authority Engineer, M/s TPF Getinsa Eurostudios, S.L. has submitted Change of
scope proposal along with cost details with recommendation for issuance of Change of scope order
as per clause 13.2 of contract Agreement. The details of cost estimate recommended by Authority's
Engineer is as below: -
Change of Scope cost details
Change of Scope Notice Issued by the
recommended by the
Authority's Engineer
SN Authority’s Engineer
Brief Details of
Reference Reference Amount (Rs.)
Works
1 2 3 4 5
CoS for providing 3 no’s of TPF/AE/TL/
TPF/AE/TL/
PUP, PUP at km 76+250, SCIA037/
1 SCIA037/EPC/2022-
PUP at km 82+335 & PUP at EPC/2023- 5,97,77,766/-
23/1032 Dt.
km 84+560 in Package-II, of 24/2071 Dt.
23.05.2022
Gorakhpur Link Expressway 01.07.2023
Total Amount (Including Labour Cess & Excluding GST) Rs. 5,97,77,766/-
Executive Engineer, PIU-2, Azamgarh vide his letter no. 986/1C/2023 dated 03.07.2023 has also
recommended the CoS estimate for the work amounting to Rs. 5,97,77,766/- (Rs. Five Crore
Ninety-Seven Lacs Seventy-Seven Thousand Seven Hundred Sixty-Six only) (F/E)
 The Drawing of structure are flagged at (F/F).
 The detail of measurement is flagged at (F/G).
 The Bill of Quantities are flagged at (F/H).
 BOQ rates based on SOR of PWD Azamgarh prevailing on date 26.06.2020.
 Few items not included in Schedule of Rates, like Bitumen and Emulsion the prevailing market
rates have been taken.
 The Bill of Quantity rates have been derived based on MORTH Standard Data Book-2019 and
applicable schedule of rates of PWD Azamgarh as mentioned above.
* Vide this office letter 1210/UPEIDA/18/1179-III/Tech dated 26.05.2023, (F/I) a committee
was formed under chairmanship of Additional Chief Executive Officer, UPEIDA for examining
and recommending the Change of Scope proposals pertaining to Gorakhpur Link Expressway
project.
The following Change of Scope proposals were found appropriate to be placed before the
board meeting for approval by the Committee in the meeting (refer minutes of meeting issued
vide this office letter 2172/UPEIDA/19/1749/22/Tech dated 03.07.2023 (F/J)).
Notice for COS
Pack Cost Proposal as
issued by Corrigendum
age Description submitted by AE at
Authority's Letter
No. UPEIDA
Engineer
TPF/AE/TL/
SCIA037/EPC/
TPF/AE/TL/ 2020-21/632 Dated Additional Minor Bridge at Ch. 13+568
SCIA037/EPC/ 13.10.2021 in MCW and SR Descoping of Box Rs.
2020-21/339 Dt. TPF/AE/TL/SCIA03 Culvert (1x2x2) at MNB Location as 24,55,15,861.00
18.03.2021 7/EPC/2022- per Sch B
I
23/1395 Dated
06.10.2022
TPF/AE/TL/ Ground Improvement below RE Wall
SCIA037/EPC/ Foundation in the approaches due to
N.A. Rs. 2,72,77,002.00
2022-23/1649 Dated introduction of underpasses under
13.01.2023 Change of Scope
TPF/AE/TL/
SCIA037/EPC/ Additional Box Culvert at Ch. 27+840
N.A. Rs. 1,98,26,570.00
2022-23/1560 Dated (1x3x3) and at Ch. 29+340 (1x2x2)
06.12.2022
TPF/AE/TL/
SCIA037/EPC/ Additional Box Culvert at Ch. 38+190
N.A. Rs. 42,64,439.00
2022-23/1365 Dated (1x2x2)
26.09.2022
I
Additional Major Bridge at Ch. 42+540
Descoping of Minor Bridge in SR at Ch.
TPF/AE/TL/ TPF/AE/TL/ 43+679
SCIA037/EPC/ SCIA037/EPC/ Descoping of Box Culvert in SR at Ch. Rs.
2020-21/378 Dated 2022-23/1686 Dated 42+095, Ch. 42+635, Ch. 43+545 & Ch. 67,73,03,185.00
14.05.2021 02.02.2023 43+915,
Descoping of SR from Ch. 42+070 to
Ch. 43+980
TPF/AE/TL/ TPF/AE/TL/
SCIA037/EPC/ SCIA037/EPC/ Construction of LVUP at Ch. 74+415
Rs. 5,60,12,979.00
2020-21/377 Dt. 2023-24/2070 Dt. for MCW, SR (BHS), Cross Road
14.05.2021 01.07.2023
II
TPF/AE/TL/ TPF/AE/TL/
Construction of 3 No. PUP at Ch.
SCIA037/EPC/ SCIA037/EPC/
76+250, 82+335 & 84+560 for MCW, Rs. 5,97,77,766.00
2022-23/1032 Dt. 2023-24/2071 Dt.
SR (BHS), Cross Road
23.05.2022 01.07.2023
Additional agenda point-04: -
According to the recommendation of the Committee, the above mentioned 07 Change of Scope
proposals were placed before the Board in its 84 th meeting. The Board approved all the Change of
Scope proposals except that pertaining to Ground Improvement below RE Wall Foundation in the
approaches due to introduction of underpasses under Change of Scope in package-1 of Gorakhpur
Link Expressway. (Refer minutes of 84th meeting of UPEIDA Board F/K).
On the recommendation of the Authority’s Engineer and PIU-02 UPEIDA, Azamgarh
of Gorakhpur Link Expressway the Change of Scope order no.-2 for providing 3 no’s of PUP, PUP at
km 76+250, PUP at km 82+335 & PUP at km 84+560 in Pkg-II of Gorakhpur Link Expressway
amounting Rs. 5,97,77,766/- (Rs. Five Crore Ninety-Seven Lacs Seventy-Seven Thousand Seven
Hundred Sixty-Six Only) may be approved/issued under Clause 13.2.4 of the Contract Agreement
Consequent to the above Change of Scope order, the revised agreement cost as per
Clause 13.2.2 of the Agreement shall be Rs. 1259,27,03,987/- (Previous cost up to CoS Order no-1 is
Rs. 1253,29,26,221/- + CoS-2 cost is Rs. 5,97,77,766/-).
The payment of work approved by this Change of Scope order will be made after 100%
completion of work. GST shall be paid as per prevailing rules/rates. At the time of payment, Authority’s
Engineer shall submit an undertaking that the work has been done as per reviewed design, drawing and
estimate against which this Change of Scope order has been issued and no observation of ETA is pending
against the work. No extension of time shall be given to EPC contractor on account of this change of
scope order.
In case of concurrence with above, may please like to sign a letter put alongside to EPC
Contractor for issuance of CoS Order - 2 for Package-II, of Gorakhpur Link Expressway.

UTTAR PRADESH EXPRESSWAYS INDUSTRIAL


DEVELOPMENT AUTHORITY
C-13, 2ndFloor, Paryatan Bhawan, Vipin Khand, Gomti Nagar, Lucknow- 226010
É0522-2307542, 2307592 Fax- 0522-4013560
email-be.upeida@gmail.com
Ref. No /UPEIDA/20/1725/Tech Date July, 2023
To,
Authorised Signatory
M/S Dilip Buildcon Limited,
EPC Contractor of Package-II,
Gorakhpur Link Expressway (Camp-I Vill. Mandohi)
Tehsil-Budhanpur, Azamagrh, UP.-223223
Sub: -Development of Gorakhpur Link Expressway (Package-II) From Fulwariya (Dist. Ambedkar
Nagar) to Salarpur (Dist. Azamgarh) (Km 47+500 to Km 90+535) in the State of Uttar Pradesh .
Reg. CoS order no-2 for providing 3 no’s of PUP, PUP at km 76+250, PUP at km 82+335 & PUP at
km 84+560 in Pkg-II of Gorakhpur Link Expressway.
Ref.:-
i. Authority’s Engineer letter no. TPF/AE/TL/SCIA037/EPC/2023-24/2071 Dated
01.07.2023
ii. Authority’s Engineer Notice no. TPF/AE/TL/SCIA037/EPC/2022-23/1032 Dated.
23.05.2022
iii. EPC Contractor letter no: - DBL/UPEIDA/GLE/PKG-II/2385 Dated.
27.06.2023.
iv. Executive Engineer, PIU-2, letter no. 986/1C/2023 Dated.
03.07.2023
Dear Sir,
Please refer your above captioned letter at sl.no. (iii) vide which you have submitted the
cost estimate for Change of Scope for the work providing 3 nos of PUP, PUP at km 76+250, PUP at
km 82+335 & PUP at km 84+560 in Pkg-II of Gorakhpur Link Expressway.

Change of Scope cost details


Change of Scope Notice Issued by the
recommended by the
Authority's Engineer
SN Authority’s Engineer
Brief Details of Amount
Reference Reference
Works (Rs.)
1 2 3 4 5
TPF/AE/
CoS for providing 3 no’s of PUP,
TPF/AE/TL/ TL/
PUP at km 76+250, PUP at km
1 SCIA037/EPC/ SCIA037/
82+335 & PUP at km 84+560 in 5,97,77,766/-
2022-23/1032 Dt. EPC/2023-
Pkg-II of Gorakhpur Link
23.05.2022 24/2071 Dt.
Expressway
01.07.2023
Total Amount (Including Labour Cess & Excluding GST) Rs. 5,97,77,766/-
Authority’s Engineer has recommended CoS estimate vide letter under reference at
sl.no. (i) as per details below:-

Executive Engineer, PIU-02, Azamgarh vide letter under reference at sl.no. (iv) has also
recommended the CoS estimate for the work amounting to Rs. 5,97,77,766/- (Rs. Five Crore Ninety-
Seven Lacs Seventy-Seven Thousand Seven Hundred Sixty-Six only)

On the recommendation of the Authority’s Engineer and Executive Engineer, PIU-02,


Azamgarh of Gorakhpur Link Expressway Pkg-II the Change of Scope order no.-2 for providing 3 no’s
of PUP, PUP at km 76+250, PUP at km 82+335 & PUP at km 84+560 in Pkg-II of Gorakhpur Link
Expressway amounting Rs. 5,97,77,766/- (Rs. Five Crore Ninety-Seven Lacs Seventy-Seven Thousand
Seven Hundred Sixty-Six Only) is here by approved/issued under Clause 13.2.4 of the Contract
Agreement.
Consequent to the above Change of Scope order, the revised agreement cost as per
Clause 13.2.2 of the Agreement shall be Rs. 1259,27,03,987/- (Previous cost up to CoS Order no-1 is
Rs. 1253,29,26,221/- + CoS-2 cost is Rs. 5,97,77,766/-).
The payment of work, approved by this Change of Scope order will be made after 100%
completion of work under reference. GST shall be paid as per prevailing rules/rates. At the time of
payment, Authority’s Engineer shall submit an undertaking that the work has been done as per
reviewed design, drawing and estimate against which this Change of Scope order has been issued and
no observation of ETA is pending against the work. No extension of time shall be given to EPC
contractor on account of this change of scope order.

Chief Executive Officer


UPEIDA, Lucknow
Copy to following for information and necessary action: -
1. Finance Controller, UPEIDA, Lucknow.
2. Chief Engineer, UPEIDA, Lucknow.
3. Executive Engineer, PIU-02, Gorakhpur Link Expressway, UPEIDA, Azamgarh.
4. Shri N. Adhikari, Authority Engineer, M/S TPF Getinsa Eurostudios, S.L. Taramandal,
Gorakhpur 273017.

Chief Executive Officer


UPEIDA, Lucknow