To.
Sr DEN(Co-ord),
East Coast Railway,
KUR/SBP/WAT
Sub: Unit Price ofP.Way materials for the year 2023-24.
Ref.: Railway Board's letter No. 2006/CE-I/MPW/1dated 08.07.2022.
The unit price of various P. way materials, as vetted by Accounts vide
letter No. ECoR/Accts/BBS/Fin-IV/Unit Price-P.Way-2023-24/ENGG/Ol
/1404 dated 24.03.2023 is sent herewith for preparation of detailed estimates
of Track Renewal works sanctioned in Pink Book 2023-24 / to be sanction in
LAW Book 2023-24.
The above rates are only approximate and should be adopted for
preparation of estimates only and not for any other purpose. In other cases,
actual prices should be taken intoconsideration.
(P.K.Panigrahy)23/2
Dy. Chief Engineer/Track
CE
Pr.
RDtecolp3t.*
RAILHA BHUAAN EAST COAST RAILWAY
No.ECoR/Accts/BBS/Fin-IV/Unit Price-PWay-2023-24/ENGG/01/1404
PFA'sOffice/BBS
Dt:24-03-2023
The CTEBBS
Glued Joints and Points
Sub: Vetting of Unit Price of Rails, Sleepers, Fishplates, SEJs,
Track Renewal Works
& Crossings etc for adoption in Detailed Estimates for
included in Pink Book & LAW Book-2023-24.
Ref: (1) Your office Note dt.27-02-2023.
(2)Your office letter No.W7/63 1/EST/RATE/Pt-[V/153 1dt.28-02-2023.(F/222)
(2) Railway Board's letter No:2006/CE-II/MPW/1 dt.08-07-2022 (F/201)
The Unit rates of all P-Way materials for preparation of Detailed Estimates for Track
Renewal Works included in Pink Book & LAW Book 2023-24 are examined with reference to
the rates communicated by Railway Board vide letter dt.08-07-2022(ref-2) as well as with those
rates available from Latest Purchase Orders/Sale Release Orders issued by this Railway.
The rates of P.Way materials are vetted subject to these rates are only approximate and
should be adopted for preparation of track renewal estimates for the Works included in Pink
Book & LAW Book'2023-24 only and not for any other purpose. In other cases, actual prices
should be taken into consideration.
Dy.FA&CAO/Finance
r
Approximate Cost of P.Way materials for adoption in Track Renewal
Estimates Sanctioned in Pink Book /LAW Book 2023-24
(Based on Rly. Board's letter no. 2006/CE-I/MPWI1 dated 08.07.2022)
(() RAILS
(a) New Rails (Prices are in per MT ex works excluding Taxes and Freight)
SI. New Rails, all 90 UTS Unit Price Remarks
No.
13M/26MI260M MT 67500 As per Rly. Bd's letter under ref.
(60Kg/52Kg) above.
(b) New Rails (Prices are in per MT ex works including Taxes and Freight)
SI. New Rails, all 90 UTS Unit Price Remarks
No.
() 13M/26MI260M MT 79650 As per Rly. Bd's letter under ref.
(6OKg/52Kg) above.
Jese/est
Dy. Chief Engineer (TR
East Coest Raitway
atyrt Bhubaneswar
Vetted
For FACAO/E.Co.Rly/BBS
For FA &CAO/E,Go.Rly/BBS
(iü) 52Kg U/S fish plates with Bolts and Nuts (in ) 771 rate analysis at
JAnnexure-IX.
( ii ) 90R U/S fish plates with Bolts and Nuts (in ) 709
For FA &CAOBE.Co.Rly/BBS
For FA &C¤OCQBWBBS
(k) SEJ(52Kg)
34639.94/- |As per vetted rate of 2021-22.
U/S cost
Per Set
Vetted
Vetteg
For FA&CAO
ngatam
Dy. Chief Engineer (TR.)
Annexure-IV
Rate Analysis For Glued Joint 60Kg &52Kg with 110 UTS Rail
Glued Joint for
60 Kg (T-2572) 52Kg (T-671)
(a) Cost of fabrication and fittings Remarks
KUR 13999.52 15245.60 For 60 kg - As per vetted rate of
SBP 13999.52 15245.60 2020-21 (KUR, SBP & WAT)
For 52 kg - As per vetted rate of
WAT 13999.52 15245.60 2020-21 (KUR, SBP &WAT)^
Average Cost 13999.52 15245.60
(b)| Rail 60 Kg (6.5 m) 52Kg (6.5 m)
Qty(MT) 0.39 0.338
Rate / MT 91253.80 91253.80 As per vetted rate of 2019-20.
Unit MT MT
Amount 35588.98 30843.78
Total cost for
49589 46089
1 joint (a+b)
1in 8 1/2 PSC Layout with all fittings (per set) (60Kg/52Kg)
Total Rate Reference
SI. Description Rate Unit Qty
No
PSC 413076.12Set 1 413076.12|As per P.0. No. PCE/ECoRI
1 Special 2022-23/W-7/629//Tender/
Sleepers for 60
Kg 1 in 8.5 |2021-22/12/00030/5341 dated
14.10.2022
Turnouts (T
l4865) 10025.12|As per vetted rate of 2022-23.
2 Grooved Rubber 10025.12 Set 1
Sole Plate for
Turnout (T-4865)
98.94 Each 356 35222.64|As per P.O. No.
3 Elastic Rail Clip
|TP235007DOg904 dated
MK-V
03.02.2023
4GFN-66 Liner for 17.15 Each 356 6105.40|As per vetted rate of 2022-23.
ERC-MK-v
5 Plate screw 44.37 Each 126 5590.62 As per vetted rate of 2022-23.
(T-3912)
Total cost for 1 set Turnout sleeper with fittings = 470019.90
Annexure-VIll
GFN-66 Liner for 17.15 Each 512 8780.80As per vetted rate of 2022-23.
ERC-MK-V
5 Plate screW 44.37 Each 218 9672.66|As per vetted rate of 2022-23.
(T-3912)
Total cost for 1set Turnout sleeperwith fittings = 678791.42
Rate Analysis of Unserviceable Fish plate & Bolt for 60Kg, 52Kg & 90R rails
For Fish Plate Wt. Per Fish Bolt Wt. Total Wt. UIS Weight
Rails Pair (in kg) (4 Nos) in kg (in kg) (95% of Col. 4)
1 2 3 4 5
35.20 1.05 x 4 nos. 39.40 37.43
60 kg
28.71 0.94 'x 4nos. 32.47 30.85
52 kg
90 R 26.11 0.94 x 4n0s. 29.87 28.38
Note: Weight workout as per track manual Vol-l (1994).
For Weight of Fish Rate (in) Unit Cost Per Pair Rate reference
Rails Plate with Bolt Per per Kg (in )
Pair (in kg)
2 3 4 5 6
1
60 kg 37.43 24.98 Pair 935.00
The following approximate prices F.O.R. works for various items of permanent way
materials are advised for the preparation of estimates:
(a) Rails (Primary) Price in Rupees
13M/26M/260M(60kg/52kg) Rs. 67500/- Per MT (ex works, excluding Taxes and
Freight etc)
(b) Rails (Second Hand) 65% of the cost of new material.
(c) Sleepers
Approximate cost of PSC Rs. 2834.61/- per sleeper (ex-works basic Rate) exclusive
Mono-Block Main Line Sleeper of Taxes, transportation and freight on input material.
(RT-8527 & RT-8746) as on
April'2022 exclusive of fittings
viz. ERC-V,GFN Liner, GRSP
etc.
(d) Thick Web Switches 1in 12 TWS 60kg-Rs. 7,41,312/- (all inclusive)
lin 8.5 TWS 60 kg-Rs. 6,64,540/- (all inclusive)
However these rates are indicative only, and may vary
between ZRs, as per their individual contracts.
(e) Weldable CMS Crossings lin 12 WCMSC- Rs.2,39,821/- (excluding GST)
Iin 8.5 WCMSC- Rs.2,00,47 1/- (excluding GST)
However these rates are indicative only, and may vary
between ZRs, as per their individual contracts.
The above rates are only approximate and should be adopted for preparation of
estimates only and not for any other purpose. In other cases, actual prices should be taken into
consideration.