You are on page 1of 6

Activity Report for June 2020 - Pravin Awalkonde

Project: Versova Bandra Sea Link Project


Date Location
6/1/2020 WFH
6/2/2020 WFH
6/3/2020 WFH
6/4/2020 WFH

6/5/2020 WFH
6/6/2020
6/7/2020
6/8/2020 WFH
6/9/2020 WFH
6/10/2020 WFH
WFH
6/11/2020 WFH
6/12/2020 WFH
6/13/2020
6/14/2020
6/15/2020 WFH

6/16/2020 WFH
6/17/2020
6/18/2020
6/19/2020
6/20/2020
6/21/2020
6/22/2020
6/23/2020 WFH

6/24/2020 WFH

6/25/2020 WFH

6/26/2020 WFH
6/27/2020
6/28/2020
6/29/2020 WFH

6/30/2020 WFH

Mumbai Pune Missing Link/Agumentation Project


Date Location
6/1/2020 WFH

6/2/2020 WFH

WFH

WFH

WFH
6/3/2020
6/4/2020 WFH
6/5/2020 WFH
6/6/2020
6/7/2020
6/8/2020 WFH
6/9/2020
6/10/2020
6/11/2020
6/12/2020 WFH
6/13/2020
6/14/2020
6/15/2020
6/16/2020
6/17/2020
6/18/2020
6/19/2020
6/20/2020
6/21/2020
6/22/2020 WFH

6/23/2020 WFH
6/24/2020 WFH
6/25/2020 WFH
6/26/2020 WFH
6/27/2020
6/28/2020
6/29/2020 WFH
6/30/2020
t for June 2020 - Pravin Awalkonde

Project: Versova Bandra Sea Link Project


Activities / Remarks / Holidays

ENGG TRANSMITTAL 0326- SUBMISSION OF DESIGN REPORT & DRAWINGS OF PILE CAP FORM
WORK 10.7M X 8.0M X 2.5M Ht.
MSRDC/ENGG/VBSL/2020/0325 BANDRA CONNECTOR PILECAP, PIER AND PIER HEAD AT AXIS "
B309", BANDRA CONNECTOR PIER AND PIER HEAD AT AXIS B309 R.C. DETAILS
Weekly Holiday
Weekly Holiday
MSRDC/ENGG/VBSL/2020/0327 DESIGN BASIS REPORT
MSRDC/ENGG/VBSL/2020/0330 VERSOVA CONNECTOR GENERAL ARRANGEMENT PLANS &
DETAILS
Juhu Connector – Plan & Profile & Structural Schemes from Ch. 0+943.999 to 1+708.999
MSRDC/ENGG/VBSL/GFC/2020/0019 - LIST OF GOOD FOR CONSTRUCTION (GFC) DRAWINGS FOR
STAMP
MSRDC/ENGG/VBSL/2020/0327 DESIGN BASIS REPORT
MSRDC/ENGG/VBSL/2020/0327 DESIGN BASIS REPORT
Weekly Holiday
Weekly Holiday
MSRDC/ENGG/VBSL/2020/0330 VERSOVA CONNECTOR GENERAL ARRANGEMENT PLANS &
DETAILS
MSRDC/ENGG/VBSL/2020/0330 VERSOVA CONNECTOR GENERAL ARRANGEMENT PLANS &
DETAILS

Weekly Holiday
Weekly Holiday

MSRDC/ENGG/VBSL/2020/0337 DESIGN CALCULATION REPORT & DRAWINGS OTTER'S CLUB


CONNECTOR RCC MONOLITHIC SOLID SLAB
MSRDC/ENGG/VBSL/2020/0337 DESIGN CALCULATION REPORT & DRAWINGS OTTER'S CLUB
CONNECTOR RCC MONOLITHIC SOLID SLAB
MSRDC/ENGG/VBSL/2020/0337 DESIGN CALCULATION REPORT & DRAWINGS OTTER'S CLUB
CONNECTOR RCC MONOLITHIC SOLID SLAB
MSRDC/ENGG/VBSL/2020/0337 DESIGN CALCULATION REPORT & DRAWINGS OTTER'S CLUB
CONNECTOR RCC MONOLITHIC SOLID SLAB
Weekly Holiday
Weekly Holiday
MSRDC/ENGG/VBSL/2020/0337 DESIGN CALCULATION REPORT & DRAWINGS OTTER'S CLUB
CONNECTOR RCC MONOLITHIC SOLID SLAB
MSRDC/ENGG/VBSL/2020/0337 DESIGN CALCULATION REPORT & DRAWINGS OTTER'S CLUB
CONNECTOR RCC MONOLITHIC SOLID SLAB

Mumbai Pune Missing Link/Agumentation Project


Activities / Remarks / Holidays
Review: AFCS-E1000-DES-CIV-DSM-DRW-0231 - Design & Drawings of Pier cap, Pedestal and
Arrestors for Viaduct 1 (Free Pier)
Review: AFCS-E1000-DES-CIV-DSM-DRW-0230 - Design & Drawings of Pier cap, Pedestal and
Arrestors for Viaduct 1 (EJ Pier)
Observations on Credentials of the RWDI for wind tunnel test submitted vide letter number AFC-
MPEW-AU-2020-542 dated 05-03-2020
Review: AFCS-E1000-DES-CIV-DSM-DRW-0220 - Design & Drawings of Pier caps of Pier SLP1 to
SLP5 & SRP1 to SRP10 for Slip Road
Review: AFCS-G2020-DES-CIV-DSM-DRW-0227 - General Arrangement of Pipe Culvert for
Approach Road from Casting Yard III to Viaduct II (2.1 Km)

Review: AFCS-D1000-DES-CIV-DSM-DRW-0229 - Design & Drawings of Post-Tensioned PSC I-


Girder for MJB1, 2 & 3

Weekly Holiday
Weekly Holiday
Review: AFCS-E1000-DES-CIV-DSM-DRW-0234 - Design & Drawings of Pier cap, Pedestal and
Arrestors for Viaduct 1 (Fixed Pier)

SO-P2-0648 - Review of “Design & Drawings of Deck Slab for Viaduct 1”


Weekly Holiday
Weekly Holiday

Weekly Holiday
Weekly Holiday
Review: AFCS-D4000-DES-CIV-DSM-DRW-0242 - Design & Drawings for RCC Box Culvert at Ch
38+225
Review: AFCS-E1000-DES-CIV-DSM-DRW-0182 (Documents) & AFCS-E1000-DES-CIV-DSM-DRW-
0251 (CRS) - Design & Drawings of Deck Slab for Viaduct 1
Review: AFCS-E1000-DES-CIV-DSM-DRW-0254 - Design & Drawings of Pier cap, Pedestal and
Arrestors for Viaduct 1 (Fixed Pier)
Review: AFCS-E1000-DES-CIV-DSM-DRW-0255 - Design & Drawings of Pier cap, Pedestal and
Arrestors for Viaduct 1 (EJ Pier)
Review: AFCS-E2000-DES-CIV-DSM-DRW-0246 - General Arrangement of Pipe Culvert At
CH:5+219 On Existing Approach Road
Weekly Holiday
Weekly Holiday
Review: AFCS-E1000-DES-CIV-DSM-DRW-0259 - Design & Drawings of Pier cap, Pedestal and
Arrestors for Viaduct 1 (Free Pier)

You might also like