You are on page 1of 4

PCE

GM

Bay Sgred
07/07/2021 6:18 PM
SUSHIL KUMAR YADAVA

(CE/RSW/ENGG/HQ/NCR)

Note No. #164

Please process for sending to RIy Board so that these may be examined by AM
Committee w.r.t their essentiality.

08/07/2021 11:02 AM
SANJAY KUMAR SRIVASTAVA
(CE/P&D/ENGG/HQ/NCR)

Note No. #165

For n a & put up proposal

12/07/2021 10:29 AM
P. K. PALIWAL
(DY.CE/P&D/ENGG/HQ/NCR)

Note No. #166

Sub: Approval of proposals for sanction under Umbrella work 2019-20"

From Note # 163

CE/RSW has processed 10 works for sanction under main "Umbrella Works
2019-20" (Note No.#163) under Plan Head-30 (Road Safety-ROB/RUB works)

The details/status "Umbrella works 2019-20" i.e. North Central Railway


Construction of Road Over/under Bridges (PB:#281/2019-20/NCR) (PB Item
No.240/2021-22)) is as under-
(Cost in crores of Rs.)

erated from eOffice by OMKAR VIJAY, OS-OMV/BRG/ENGG/HQ/NCR, GM OFFICE on 14/07/21 04:42 PM


Allo-Total Admissible Cost Works Balance RemarksS
cation 2021-22 already Ceiling Cost|
sanctioned|
RRSK 260.00 Nil 260.00 10 proposals are proposed|

for approval of GM as

follow

Details of the proposed works are as under-


SN Name of Work Cost in "000"

Rly. Share State


Share
EBR)
1 MKP-NYN: - Construction of double barrel RUB in lieu 165680 NA
of LC 428 at KM 1338/7-8 in Manikpur- Naini section.

284492 NA
2 MKP-NYN: Elimination of 04 nos. manned Level
crossing No 405, 411, 412 8& 414 by providing RUB
in NYN-MKP section.

3 MKP-NYN:- Elimination of 04 nos. manned Level 284492 NA


No 410,413, 416 & 419 by providing RUB
Erossing in

MKP-NYN section

4 Construction of 2 lane ROB in lieu of LC No. 22 C at KM 199760 258347


Mathura Alwa section
1423/4 -

5 on

LC no. 57 between 199079 265676


5 Construction of Road Over Bridge at
KM 82/4-5 in Idgah Bandikui section.

lieu of 406618 NA
6 Idgah Bayana
Construction of subway in
26, 27, 31, 69
14, 17, 19, 23, 25,
level crossing No 100000
having TVU upto (09Nos.)

453756 NA
Construction of subway in lieu of level
7 Idgah-Bandikui-
91, 93, 94, 95, 96,
crossings LC no. 49, 78, 79, 88, Nos
having TVU up to 100000 (10
98
Fle N
NCR-HGQ0ENGG(BRID)/19/2020-0/o CBE/HQ/NCR (Computer No. 4151)

8 Mathura-Alwar-Construction of subways in lieu of Level| 222868 NA


crossing no 3,60,69,83, 103 (O5 Nos.)

9phansi- Manikpur section-Construction of ROB in lieu of| 135534 224000


Level crossing No. 369 at Km 1131/1-2

10 phansi- Manikpur section-Construction of ROB in lieu of| 135534 224000


Level crossing No. 379 at Km 1158/11-12

Total 2487813|
L
Justification of above proposed works are downloaded from IRPSM and
placed at P-91 to P-100 respectively. All proposals are related with safety of
train operatiot and road user hence essential & inescapable.

As per item No. (ii) of Railway Board's letter No. 2020/F(X)II/PN/3 dated
04.05.2021 (P-101), "Umbrella Works of 2019-20 and 2020-21: For unutilised
portion of Umbrella works under the Plan Heads 17, 33, 36, 41, 42, 51, 53 and
64, the proposals will be examined by the Additional Members committee w.r.to
the essentiality of the proposed works before obtaining sanction of the
competent authority as per delegation of powers. The works under other Plan
Head may be prOcessed in the usual manner".

GM is requested to kindly approve the proposals costing Rs.248.80 cr. as


proposed by CE/RSW so that it may be forwarded to Railway Board for approval
of Nodal Plan Head Coordinator after concurrence of HQ finance before sanction
through IRPSM.
CE/P&D
PCE
GM

Dgaly Signed
12/07/2021 12:58 PM
P.K. PALIWAL
(DY.CE/P&D/ENGG/HQ/NCR)

Note No. #167


File No. NCR-HQOENGG(BRID)/19/2020-O/o CBE/HQ/NCR (Computer No. 4151)

GM may kindly approve the proposals costing Rs.248.80 Cr. so that these may
be forwarded to Railway Board through IRPSM for approval after concurrence or
HQ finance.

haly Sgned
12/07/2021 1:28 PM
SANJAY KUMAR SRIVASTAVA

(CE/P&D/ENGG/HQ/NCR)

Note No. #168

The proposal for itemised works for ROB and RUB in Non GQ/GD routes under
sanctioned Umbrella work of 2019-20 in PH 30( PB Item No 240/2021-22) has
been put up vide Note#163 above.
Proposals for ROB at LC No 22C in Mathura-Alwar section (item no 4)
RUB
represented by local leaders during Annual GM Inspection as well as for the
for LC No 428 at Iradatganj for providing Long Loop in MKP-NYN section as
decided during meeting by GM in June'21 have been incorporated in above
Umbrella work.
Put up for kind approval of Note#163 above so as to send the proposal to Rly
Board for sanction after obtaining concurrence from PFA/NCR.

ialy Signod
12/07/2021 5:10 PM
SANJAY KUMAR MISHRA
(PCE/HQ/NCR)

Note No. #169

note #163 approved.

ghaly Signed
13/07/2021 5:05 PM
VINAY KUMAR TRIPATHI
(GM/NCR)

Note No. #170

13/07/2021 5:56 PM
SANJAY KUMAR MISHRA
(PCE/HQ/NCR)

Note No. # 171