Professional Documents
Culture Documents
257757 ) 32
12/11/2020 5:50 PM
DEEPAK KUMAR
(DIRECTOR(RMCD) , CWC)
12/11/2020 9:46 PM
APOORVA RAJ
(DD-I (RMCD) , CWC)
पत्र जारी कर दिया गया है एवं संबंधित अधिकारीयों को ई-मेल से भेज दिया गया है |
12/11/2020 10:27 PM
KAUSHIL MATHIYA
(AD (RMCD)-1 , CWC)
4. Total expenditure of Rs. 18.4227 crore has been incurred upto March, 2021 as
detailed below:
2019-20 5.1229
2020-21 4.5826
Total 18.4227
5. Since the work was likely to extend beyond March, 2021, in the draft SFC memo
for the period 2021-26 (5 years), outlay of Rs. 3.46 crore for this project has been
proposed.
6. In the letter dated 25.05.2021, it has been mentioned that total balance fund
amounting to Rs. 3.3839 crore is required to complete the construction work of CWC/
GFCC building at Adalatganj, Patna. The completion of work was expected in July,
2021, but due to Covid pandemic situation, work got hampered and it is being
delayed by few months. As per current scenario Rs. 2.50 crore (Rupees Two crore
Fifty Lakh) is essentially required for clearing of pending bills and to speed up off few
balance peripheral work up to the July, 2021. However, in August 2021 remaining
fund will be required immediately for final completion of work, which is expected up to
September-2021, if the Covid situation subsides.
10. Therefore, it is proposed to seek the concurrence of Director (Finance), CWC &
approval of Chairman, CWC on following:
• Expenditure Sanction of Rs. 3.3839 crore and authorization of Rs. 2.50 crore
to PAO (EZ), CPWD, Nizam Palace, Kolkata for construction of CWC/GFCC
building at Patna for FY 2021-22
Submitted for seeking the concurrence of Director (Finance), CWC & approval
of Chairman, CWC.
01/06/2021 3:29 PM
KAUSHIL MATHIYA
(AD (RMCD)-1 , CWC)
2. It is proposed to send the efile to Director (F), CWC for concurrence and further
obtaining approval of Chairman, CWC on the above proposal for Expenditure
Sanction of Rs. 3.3839 crore and authorization of Rs. 2.50 crore to PAO (EZ),
CPWD, Nizam Palace, Kolkata for construction of CWC/GFCC building at Patna for
FY 2021-22 for construction of Office Building (G+3 floors) of CWC/GFCC at Patna.
01/06/2021 4:29 PM
APOORVA RAJ
(DD-I (RMCD) , CWC)
01/06/2021 5:45 PM
N K MANGALIK
(DIRECTOR(RMCD) , CWC)
Releases beyond the above limit shall be with the approval of Minister (Jal
Shakti).”
2. Further, it has also been noted that the instant proposal pertains to the
matter of stage payment in respect of administrative approval amounting
to Rs.21.81 Crore granted by the Ministry. Accordingly, instant proposal
may be sent to the Ministry, along with the submission of proper response
towards the previous observations of the undersigned, for approval of the
Minister (Jal Shakti) in consultation with Ministry’s IFD.
03/06/2021 9:26 PM
PRADEEP KUMAR SHUKLA
(DIR-FINANCE(CWC) , CWC)
Put up for approval of Chairman, CWC before sending the case to Ministry for
release of Rs 2.5 Cr to CPWD.
04/06/2021 10:58 AM
N K MANGALIK
(DIRECTOR(RMCD) , CWC)
Proposal recommended.
04/06/2021 11:22 AM
RANJAN KUMAR SINHA
(MEMBER(RM) , CWC)
Approved.
04/06/2021 11:54 AM
S K HALDAR
(CHAIRMAN-CWC , CWC)
04/06/2021 11:55 AM
RANJAN KUMAR SINHA
(MEMBER(RM) , CWC)
04/06/2021 1:12 PM
N K MANGALIK
(DIRECTOR(RMCD) , CWC)
4. Total expenditure of Rs. 18.4227 crore has been incurred upto March, 2021 as
detailed below:
Amount in Rs. crore
FY/ Period Expenditure incurred
Upto March, 2019 8.7172
2019-20 5.1229
2020-21 4.5826
Total 18.4227
5. Since the work was likely to extend beyond March, 2021, in the draft SFC memo
for the period 2021-26 (5 years), outlay of Rs. 3.46 crore for this project has been
proposed.
8. Head of account: The expenditure of Rs 2.50 cr. to be incurred in the above works
is chargeable to the Head of Account 4711.01.800.07.00.53 (Major Works) of ID
Scheme. Sufficient fund is available under the Head of account.
10. The proposal was submitted for concurrence of Director(F), CWC and further
approval of Chairman, CWC. However, as per the advise of Director(F), CWC vide
Note#98, the instant proposal pertains to the matter of stage payment in respect of
administrative approval amounting to Rs.21.81 Crore granted by the
Ministry. Accordingly, instant proposal may be sent to the Ministry.
11. Following is submitted for the comments of Director(F), vide letter dated
25.05.2021, it has been mentioned that total balance fund amounting to Rs.338.39
lakh is required to complete the construction work of CWC/GFCC building at
Adalatganj, Patna as per AA&ES of Rs 21.81 Cr. The completion of work was
expected in July, 2021, but due to Covid pandemic situation, work got hampered and
it is being delayed by few months. As per current scenario Rs. 2.50 crore (Rupees
Two crore Fifty Lakh) is essentially required for clearing of pending bills and to speed
up off few balance peripheral work up to the July, 2021. However, in August 2021
remaining fund will be required immediately for final completion of work, which is
expected up to September-2021, if the Covid situation subsides. Work is being
regularly monitored by Chief Engineer, LGBO at field and Member, RM at HQ level.
12. The proposl has the approval of Chairman, CWC vide Note#101 and it is
proposed send the efile to Director(ID), DoWR,RD&GR for obtaining the approval of
the Competent Authority on following:
• Expenditure Sanction of Rs. 3.3839 Crore and authorization of Rs. 2.50
crore to PAO (EZ), CPWD, Nizam Palace, Kolkata for construction of
CWC/GFCC building at Patna for FY 2021-22
04/06/2021 3:53 PM
APOORVA RAJ
(DD-I (RMCD) , CWC)
04/06/2021 4:16 PM
N K MANGALIK
(DIRECTOR(RMCD) , CWC)