Rangit-IV HE Project (120 MW), Sikkim

HIGHLIGHTS FOR THE MONTH OF NOVEMBER’ 2021

Diversion Channel Dam

▪ River Diverted through Diversion channel. ▪ Excavation work at Dam Site is in progress.
Power House U/S Coffer Dam

▪ Dewatering & slush removal at Power ▪ Construction of U/S Coffer Dam is in


House Area is in progress. progress.
Cumulative Progress of Major activities up to November 2021:
❖ 1st Milestone of River Diversion accomplished on 07.11.2021.
❖ Construction of Upstream Coffer dam completed.
❖ Already constructed Dam structure, exposed partially by removal of RBM.
❖ Dewatering in Face 2 of HRT completed up to 1850 m (out of total 1900 m length)
❖ Dewatering in DC 1 & DC 2 Completed and dewatering in DC 3 is in progress.
❖ Dewatering in Power House completed up to EL 336 m, manual slush removal is in
progress.
❖ Tendering of balance E&M Packages are under progress.
❖ Removal of old equipment’s from HRT (face3&4) has been completed.
*****