Professional Documents
Culture Documents
DRILLING DEPARTMENT
DULIAJAN
Annual Report 2020-21
DRILLING DEPARTMENT
CONTENTS
Page No.
1.0 PREAMBLE 3
6.0 CEMENTING 26
12.0 ADMINISTRATION 63
14.0 ACKNOWLEDGEMENT 66
15.0 ANNEXURES 67
1.0
1.0PREAMBLE
PREAMBLE
MEMBER, IADC,SOUTH CENTRAL ASIA CHAPTER
Page 2 of 79
Annual Report 2020-21
DRILLING DEPARTMENT
Oil India Limited being an E&P Public Sector company of India, with its rich legacy, it bears
moral and corporate responsibility to contribute it’s best for strengthening country’s energy
security and hence the organization has its primary objective to continuously endeavor for
accretion of reserves and maintenance of production level. This calls for drilling in logistically
difficult and geologically complex boundary conditions.
Drilling Department is fully committed to achieve the organizational goals and the whole work
force is relentlessly engaged as a team with dedication in carrying out the following
operations/ tasks to fulfill the targeted objectives.
The challenges range from drilling shallow wells to deep Eocene wells, sub normal to
abnormal (high) pressure & temperature wells, development of ranked wildcat wells, wells
having straight, directional trajectories are drilled having high displacement profile.
To carry out its drilling activities in the development and exploratory fields of Assam,
Arunachal Pradesh & Mizoram, Drilling Department utilized eleven (11) in-house drilling rigs
of varying capacities –six (06) 1400 HP, three (03) 2000 HP and one (01) each of 600 HP, DM-
5 (for WDW) and 3000 HP. In addition to in-house fleet, eight (08) nos of Charter-Hire Drilling
Rigs (03 nos 1400 HP & 05 nos 2000HP) were also utilized for different periods for drilling
activities.
Number of wells drilled during the FY 2020-21 was 30 numbers against a BE target
(FHQ) of 41 numbers which is 73.17% and corresponding drilling meterage achieved was
80,719 m against BE target of 1,68,286 m which is 47.96 % of BE target. This shortage in
number of wells drilled and meterage achieved was mainly due to the unprecedented
environmental issues encountered by Oil India Limited during the FY 2020-21 like COVID-
19, Baghjan#5 blow out incident related issues, Abduction of crew & threat by terrorist outfit,
bandh over various local issues along with non-availability of drilling location/allied services
etc.
It is also worth mentioning that adherence and compliance of more and more stringent Safety
& Environmental regulations and policies by statutory bodies like DGMS, OISD, SPCB, CPCB,
MoEF&CC etc also remained a major challenge with limited supervisory staff. All efforts were
being made for full compliance of the statutory regulations and to ensure safety of men &
machines.
ADOPTION OF NEW TECHNOLOGY:
Procurement of 05 nos. of new 2000 HP VFD drilling rigs is on the process (Project Cost =
1274 Cr).
Hiring of RSS with Mud Engineering Service is on the process (Project Cost = 340 Cr).
e-RTMAC under Project Drive is on the process (Project Cost = 126 Cr).
Three (03) Mud Pump System will be installed at Rig: S#8, E-3000.
Hiring of HSE Bundle Services is in the process, Purchase requisition released.
Commissioning of Iron roughneck unit at Rig: V-2.
Complete over-hauling of both Top Drive Systems of rig: V-1 & V-2.
Construction of over-head shed at Draw works maintenance yard.
Complete health check-up & refurbishment of Skytop mast & sub-structure of Rig S-3 (E-
1400).
Increasing the exhaust stack height of power pack engines (CAT 3512 B with acoustic
enclosure) of rigs V#1, V#2 and DM#5 to 9.31 mtrs above ground level in order to meet the
guidelines prescribed by CPCB regarding exhaust stack height is in the process.
Limiting sliding mode to the maximum extents during drilling of tangent section by
suitably designing BHA and Hydraulics in directional wells.
PDC bit extensively used wherever feasible to reduce the drilling time.
Utilization of RSS (Rotary Steerable system) in highly complicated wells resulted in better
well profile with lesser complication and reduction in rig time.
“One Bit One Section” successfully implemented in many directional wells, which had
saved immensely in terms of Rig time.
Effective utilization of hired directional services saved substantial amount of well cost.
Installation of mud flow line from Header box to trip tank directly by-passing the shaker
units in VFD rigs having MI-SWACO solid control system which reduced idle running of
shakers during Tripping and thereby preventing damage of the screens and other parts .
This modification helped in saving approximately 5.5 hours per section drilled and
approximately Rs. 2,05,787.00 (Cost of screens) per well drilled.
Fabricated /repaired in-house damaged Acoustic Enclosure of 3 Nos. Powerpack of S#2 rig
at LOC:HRX-1. This resulted in cost saving of INR 45,000.00 as against service quote by
M/s GCPL.
2.0
2.0PERFORMANCE
PERFORMANCE&&ACHIEVEMENTS
ACHIEVEMENTS
For smooth and effective functioning of all the above activities, the department comprises of
the following sections.
a. Drilling Operation
b. Directional Drilling
c. Cementing
d. Rig-building
e. Drilling Technical Service
f. Equipment & Fishing
g. Health, Safety and Environment
h. Planning and Data Section
i. Administration
j. Well Control Training School
k. Project
TARGET VS ACHIEVEMENT
180000
160000
140000
120000
Meterage
100000
80000
60000
40000
20000
0
EXPLORATORY DEVELOPMENT WDW TOTAL
Target 71886 83600 12800 168286
Achivement 32622 38515 9582 80719
QUARTERLYACHIEVEMENT
25000
20000
METERAGE
15000
10000
5000
0
Quarter 1 Quarter 2 Quarter 3 Quarter 4
Exploratory 5736 9918 10138 6830
Development 9697 8569 9879 10370
WDW 2826 408 3245 3103
Total 18259 18895 23262 20303
Assembling of Capping stacks for BGN#05 as per M/S Alert design and pressure testing of
the same.
All other related well control equipments like BOP, BOPCU, Choke Manifold , Valves were
serviced, pressure tested and provided to BGN # 05.
Carried out directional drilling jobs in 33 nos. of wells which includes 16 no. of “J”-Bend
wells (12 full + 04 partial), 17 no. of “S”-Bend wells (14 full + 03 partial) during the
financial year.
Inspite of lock down scenerios around the globe, timely mobilized the Whipstock setting &
Window milling services for re-entry wells without hampering progress of drilling
operations.
With inhouse design, successfully carried out 04 nos. of window cutting and milling job at
Loc: KUAS, Loc: HRX-1, Loc: NLT, Loc: DGF-1 and window cutting job was in progress at
Loc: HUN-1.
Total numbers of 201 cementation jobs were carried out during the FY 2020-21 This
comprises of 81 Primary jobs and 117 secondary jobs.
12 nos. of Leak Off Test carried out using cementing unit at various drilling locations.
Total 04 nos. of cementing jobs were performed using in-house cementing facilities for well
control at BGN#5 under the supervision of M/s Alert.
Carried out Physical verification of 3710 assets pertaining to Drilling Services as per
schedule.
Carried out NDT of mast and substructure of Rig: S-7 , E-2000.
One no of Disc Brake unit commissioned at E-3000 Draw-works of Rig S-8 at LOC: DIF.
Commissioned 2 sets of ELECTRIC CASING LINE SPOOL at Rig S-6, LOC: NLT and at rig
S-8, LOC: DII.
Three numbers of new Drill-pipe spinners commissioned at rig V-1, V-2 and S-8 at LOC:
DGF-1, LOC: MGE & LOC: DII respectively.
A Mast High Stand of Rig: S-8, E-3000 was modified as the original High Stand of Rig: S-8
was damaged beyond repair.
Rig S2: Replaced existing Gauging water pump (Make: BEACON WEIR) by new 02 Nos. of
Multi stage Gauging Water Pump (I&C of GRW Pump) at Loc: HRX-1. Commissioned
engine online monitoring system.
In Rig S#3, Rig S#4 and Rig S#6: inhouse fabricated Venturi Jet Pump is used for cellar
suction in all completed wells.
In Rig S#2, fabricated centrifugal pump for cellar suction.
Inhouse Design & Fabrication of hydraulic BOP landing system for BGN#05 in Central
Workshop.
Applied 32 number of CTE/CTO for the various Drilling Location in the portal of State
Pollution Control Board –Assam.
It may be noted that there has been considerable constraints in following areas, which
resulted in reduced drilling meterage
G. Consequential Losses:
Total Loss of Rig Days: 14.13 Days
Loss of Planned Rig Year: 0.04
Total Loss of Meterage: 365.12 m
Note:
1. 168286 m drilling planned with 17.84 Rig Year for 2020-21. Hence, prorated per day loss
has been considered to be 25.84 M.
2. Thus a loss of 53693 m has been recorded due to the above reasons for the year FY
2020-21 for the available rigs.
In addition to the above mentioned reasons for the available drilling rigs, delay in
mobilization of following Charter Hire rigs due to various issues caused shortfall of
performance as follows:
i) Delay in mobilization = 274 days of rig: CH-E-3000 by which 8250 m was planned to be
drilled at loc: Sadiya-1 & W. Mesaki-A.
ii) Delay in mobilization = 365 days of rig: CH-4, E-2000 by Contractor (SINDHU) by which
9900 m was planned to be drilled, (as per LOA, date of mobilization was 10.02.2020;
not mobilized till 31.03.2021).
iii) Delay in mobilization = 132 days of rig: CH-5, E-2000 by Contractor (FORESIGHT)
mainly due to COVID-19 lock down (as per LOA, date of mobilization was 31.03.2020;
mobilized on 10.08.2020).
iv) Delay in mobilization= 12 days of rig:CH-2, E-2000 at loc:KUAS by Contractor
(QUIPPO).
However, Oil and Gas potential build up achieved during the year was
more than the BE target :
Oil & Gas Production Target vs Achievement of Drilling wells during FY 2020-21
Achievement
Build up Target as per TDP (BE)
dated 31.03.2020 Potential
build up % of BE Target
Oil (klpd) 755 757 100.26
Gas
(mmscumd) 0.092 0.4809 522.72
1200
COMPARISON OF LOSS OF RIG DAYS
1000
800
600
400
200
0
Capital
Waiting for Extended repairing/Ri
Environmen Consequenc Waiting for
Allied Sub Surface Surface Production g
t e loss Location
Services Testing Foundation
Sinking
2019-20 211.57 60.17 91.27 66 259.06 7.96 285 419
2020-21 296.6 2.39 111.08 196.24 1133.22 14.13 0 324.25
Column1
A GRAPHICAL COMPARISON OF AVAILABLE RIG YEAR VIS A VIS LOSS OF RIG YEAR FOR
LAST SIX YEARS
14
12
10
6 5.16
4.54
3.76 3.83
4 3.43
2.83
0
2015-16 2016-17 2017-18 2018-19 2019-20 2020-21
Information/ Data in details on the following aspect of Drilling operation are enclosed at the
end as Annexure:
Preface:
Gone are the days of easy oil. Due to the gradual increase of problems pertaining to land
acquisition as well as environmental clearances most of the wells have been planned for
Directional Drilling in the financial year 2020-21. During the last financial year, except 01
water disposal well and some wells in Mizoram block, all the wells were directional wells i.e in
other word around 90% wells were deviated.
Moreover, most of the wells released were found to be challenging looking into the fact that we
have to drill with greater TVD and greater displacements.
The Directional section of Drilling Department, with its very limited manpower, is directly
associated with vast job of planning and designing of Directional wells along with supervising
execution during actual drilling operation. Directional section plans to meet the geological
targets and supervises the drilling operation with help of Landmark directional software and
hired directional services. The Directional drilling section of FHQ, also helps and supports
with respect to technical feedback, design, torque & drag analysis and other drill ability
issues as and when sought by various projects in pan India.
This section plan & design the optimum well profile for minimum torque, drag, anti-collision
and hydraulics issues as per the surface and sub-surface coordinates given in the draft
DDDP (Depth Data Drilling Policy) prior to finalization of the same. It is also to be noted that
Directional Drilling Section also has to give the inputs related to Directional section in EDP
(Executive Drilling Plan) which is currently implemented for exploratory locations.
Whenever directional service provider declines to accept a well profile due to torque, drag or
anti-collision issues, this section takes up the responsibility and assists the service provider
for drilling by providing look ahead correction plan with a new BHA and hydraulics.
Hence the responsibility lies on this section to approve the drillability of the well.
2. Field operations:
A. With continuous effort and proper monitoring, the Directional section contributed in
carrying out directional drilling jobs at 33 nos. of wells which includes 16 no. of “J”-
profile wells (12 full + 04 partial), 17 no. of “S”-profile wells (14 full + 03 partial)
during the financial year 2020-21
B. The section has taken the responsibility of providing support to the Logistic
department during inter location movement of the directional tools & equipment of
the service providers. The section took help of Security and Administration
department whenever felt necessary for prompt uninterrupted ILM of the tools and
equipment.
D. The section has also taken the additional responsibility of transferring all old DPRs
and well data stored in CDs to hard disk. These were properly indexed, location
wise and well wise for easy retrieval and access whenever needed in future.
E. The section also has carried out On-hire survey, inspection of tools and equipment
of the directional services at the time of mobilization or whenever replaced with new
one.
F. The Directional drilling section has the responsibility of supervising and monitoring
the directional drilling operations in co-ordination with the service providers for
ensuring completion of the wells as per approved plan smoothly.
G. The section is also involved in assisting the operation teams to complete the wells
as and when required, once directional service is withdrawn.
H. The section has completed all the directional wells in spite of many wells
encountering downhole stability issues which caused several stuck up and fishing.
In fact, in couple of wells, direction tools and equipment got lost in the hole due to
downhole wellbore instability despite best effort was been tried to fish out the lost
tools and equipment. However, it was also to be noted that although there was
lack of information on geo-mechanical stresses and wellbore instability,
sidetracking in those challenging wells was successfully completed.
B. Guide service providers with the necessary look ahead plans and decision based
upon real time simulation on landmark software on the following parameters /
issues such as
a. Hydraulics for hole cleaning/drag/tight spot
b. Torque & Drag
c. BHA behavior & design
d. Well trajectories
e. Guide the service providers to give a limit of geological target radius for
smooth hole profile
C. Well design and construction with the help of in-house LANDMARK software.
D. Feasibility study for future directional wells based on surface position proposed in
LAF-III prior to selection of the final surface location.
List of directional wells drilled by Directional section during the year 2020-21:
10 CH2 (JB) BGY J-BEND 12.25/8.5 4164 4 986.83 1800 28.42 In progress
CH-
11 DHO J-BEND 17.5/12.25/8.5 3864 4 1140 600 21.57 Completed
5/FST-19
12 V-1 HZB J-BEND 12.25/ 8.5 4455 4 840.76 2000 21.32 Completed
WHIP-STOCK JOBS:
Whip-stock Whip-stock
Sl. No. Loc: Window Range
Size setting depth
1. KUAS 9-5/8″ 2858.5 m 2852.5m- 2856 m
A.
i. Contract no. 6111084/CDG2661/DRLG /2Ol7 for RSS from M/s Halliburton.
ii. Contract no. 6112634/CDG7192P18/DRLG/19 for SDMM from M/s Newsco
International Energy services Inc.),
iii. Contract no. 6113389/CDG7192P18/DRLG/2019 for SDMM from M/s Baker
Hughes) under execution for directional drilling at FHQ.
B. New contract no. 6113879/CDG1170P20/DRLG/20 of M/s Weatherford for 02 kits of
tools and equipment including personnel of 9-5/8″ and 13-3/8″ sizes for whip-stock
and window cutting/milling job was mobilized on 14/10/2020 and 03/01/2021
respectively.
C. Contract No. 6111084/CDG2661/DRLG /2Ol7 has been extended for a period of
another 01 year i.e. up to 26.01.2022 or till commencement of replacement contract,
whichever is earlier.
During financial year 2020-21, the Directional section has undertaken many challenging
wells and successfully completed those. Due to the consistent rise in issues related to
land acquisition associated with OIL’s exploration in deeper depth in designing of wells
had become more challenging having high displacement, inclination and deeper in depth
which were efficiently handled by the section.
The following were some of the many achievements that were been highlighted herein. .
Loc: KUAS:
The well was designed as “S” profile with kick off at 1250m with a horizontal displacement
of 647.93m. Although the initial well profile seemed to be simple to drill, later on it was
observed that the formation encountered at Kumchai area was highly complex due geo
mechanical instability of sub-surface formation and ROP attained was very poor. The well
encountered severe downhole instability in 8.5-inch section. Due to unsuccessful fish
recovery the mother hole had to be cement plugged. Consequent to cement plug it was
decided to side-track the well in 8.5-inch section as per G & R department requirement.
After successful side-track job by directional drilling section, the well was handed over to
operation section for remaining vertical drilling to reach to the target depth at 4140m.
While Open Hole survey was carried through TLC by M/s. Schlumberger, the tool with
radio-active source got stuck resulting of a fish of 942 m with radio-active source
remained in the hole. As per AERB guideline the well was abandoned by placing three
cement plugs. It was decided to drill a replacement well utilizing technology of whip-stock
setting and window milling in 9.5/8” casing.
The well was successfully completed by setting 9-5/8 Whip-stock at 2858.5m and exiting
through the casing by window milling. The profile of the well was S-Profile having
Horizontal displacement of 674m at MD 3686m. The well was subsequently brought onto
production and currently producing.
Loc: HRX-1
The development location HRX-1 (proposed as Loc. A) is a replacement well for well
HJN-41, lies at a distance of around 30 m towards SE of well HJN-41 (Loc. HRX) in the
North Hapjan Structure. However, Loc. HRX-1_Revised (S/S) lies at a distance of
around 26 m towards SE of well HJN-41 (S/S) drilled as S-bend deviated well from the
existing cellar of Well Hapjan-41 (Loc. HRX). Accordingly whip-stock was set at the
depth of 1305.5m using services from M/s Weatherford. After exiting by cutting a
window through 9.5/8″ casing directional services from M/s Halliburton was utilized to
drill ahead to the target depth of 2954m. The well was successfully drilled and brought
onto production. It is to be noted that during drilling of 8.1/2″ hole section a very high
torque was experienced, however, with proper and constant monitoring and supervising
the well was successfully completed.
Loc: NLT
The Loc: NLT has been proposed to drilled from existing cellar of abandoned well NHK:
649 (Loc:NLO) by window cutting of 13.3/8″ casing at around 900m. Accordingly whip-
stock was set at 901.5m. After cutting the window at 13.3/8″ casing in the range of 892
m- 897.5m directional services of M/s Halliburton was utilized and drilled the well
successfully to its TD at 2795m with a horizontal displacement of 452.54m.
Subsequently 9.5/8″ casing was lowered through the window and cemented the casing
annulus. Finally M/s Baker Hughes services BHA was utilized to drill the remaining
8.1/2″hole section and completed the well successfully. The well NLT had collision
issue with the neighboring well which was closely monitored by directional team during
the whole drilling processes to prevent from collision.
Loc: CAD
Loc: HZB
The location is planned to be drilled as a deviated (J-bend) well from an independent
plinth to probe the hydrocarbon prospects in the Lakadong + Therria Sand Group as
primary objective. Drill string comprising M/s Halliburton’s directional tools of 8.5 inch
section at Loc-HZB got stuck at the depth of 3900m during tripping out. At 3900 m
(MD), severe tight zone was observed which could not be cleared by scrapping, hence it
was decided to back ream. While back reaming string got stuck at the depth of 3900 m.
Rigorous work on string was carried out with down jarring but the string could not
released. The string was backed off at 3857m and match on the string was run with
bumper sub for the first time having special BHA, designed by the directional team.
Finally string was retrieved and successfully drilled ahead to the target depth and
brought the well into production.
o Limiting sliding mode to the maximum extents during drilling of tangent section by
suitably designing BHA and Hydraulics in directional wells.
o PDC bit was extensively used wherever feasible to reduce the drilling time.
o Utilization of RSS (Rotary Steerable system) in highly complicated wells resulted in
better well profile with lesser complication and reduction in rig time.
o Proper monitoring of tools and equipment of service providers and ensuring timely
maintenance of the same has led to minimization of downhole tool failures and un-
planned round trips.
o Major challenge was encountered in many directional wells in terms of hole
instability which was addressed by the section to a greater extent by proper
monitoring of wells as well as modification of designs as and when required.
o Effective utilization of hired directional services saved substantial amount of well
cost.
o After expiry of drilling software consultant tenure from March’15, this section has
managed and handled directional software on its own and deliver the quality
service to its stake holder and saved humongous amount of company’s financial
outgo.
This refers mainly to the land acquisition problem. Many directional wells were
drilled from existing plinth saving a huge amount against land procurement. Due
to the success of the high displacement and high angle J-Bend well, targets once
inaccessible are now been drilled with ease and geological targets are being drilled
with accuracy.
The section has also been proactive in incorporating advance technologies as far as
directional services and logging while drilling is concern.
Due to the incorporation of RSS (rotary steerable system), deeper and complicated
wells are being drilled with the help of existing rigs with smoother well profile. Also
due to the adoption of LWD (Logging while drilling) real time logging data are being
received which helps co-relating with post wire line survey data.
The section has proactively incorporated state of the art LWD (Logging While
Drilling) systems, Real time monitoring system (both computer as well as mobile
based) which enhanced landing accuracy in horizontal wells.
This section is headed by GM-Directional Drilling seconded by DGM- Directional Drilling and
03 (Three) numbers of executives in Level-1, who are responsible for carrying out the entire
directional drilling operation pertaining to designing and planning of directional wells as well
as execution of directional wells by monitoring during drilling consistently.
6.0 CEMENTING
In searching of liquid gold, Cementing Section plays a definitive vital role in successful
completion and thereby the ultimate potential of a drilling well. Internationally it is
considered as a High Tech Operation.
During the FY 2020-2021 Cementing section successfully completed 201 nos. of cementing
jobs. Screening & blending of oil well cement required for these entire Primary and Secondary
jobs as well as responsibility of transportation of screened virgin/ blended cement to various
wells are done in-house by Cementing section.
Cementing section also played a major role in providing prompt & efficient back up services to
drilling & work-over wells like Torque Turn services, Rig up & Rig down of present
instrumentation system, well killing pumps hook up and maintenance services, maintenance
of compressors, power subs, various packers, Liner Hangers, Cement Retainers etc.
Hook up & maintenance of weight indicators, SPM meters, RPM meters, Torque gauges,ROP
gauges, pressure gauges along with Record-O-graph are also carried out by Cementing
section as a part of Instrumentation System. Furthermore, splicing of wire line sling of
various sizes used for different wells and requirement of different sizes of slings to various
departments are also catered by cementing section.
Manpower:
1.Executive
2.Workman
Sanctioned Actual
Year Shortfall
man power strength
2012-13 103 67 36
2013-14 103 66 37
2014-15 103 78 25
2015-16 103 72 31
2016-17 103 65 38
2017-18 103 60 43
2018-19 103 76 27
2019-20 103 72 31
2020-21 103 58 45
Tabulated forms of cementing jobs performed during last five financial years are given below.
A comparative study of nature and number of jobs carried out during the last four financial
years is depicted below graphically:
CEMENT USED:
Cement used in last eight years for carrying out Primary & Secondary cementing jobs is
shown below. 2020-21
2011-12
2013-14
2015-16
2017-18
2019-20
2010-11
2012-13
2014-15
2016-17
2018-19
Year
MTCement used,
6250
6328.7
6365.3
5080.7
7160.4
7254.2
10160
6457
7740
6260
8106.5
Major Achievement:
1) Total numbers of 201 cementation jobs were carried out during the FY20-21 inspite of the
COVID-19 pandemic. This comprises of 81 Primary jobs and 117 secondary jobs.
3) Cementing section has started using Microbond-HT for both 9.5/8” and 5.1/2” casing
cementing jobs. Microbond is a post set expansive additive which expands the setting
cement instead of allowing it to shrink and thus avoid micro-channels through which the
gas may migrate upwards. This reaction during the hydration process of the cement
would provide better results in terms of cement bonding to the casing and to the
formation. A good cement bond would avoid any problems such as ‘Sustained Casing
Pressure’ & ‘Annular Pressure Build ups’ and reduce the cost involved in the remedial
jobs for zonal isolation.
4) 12 nos. of Leak Off Test carried out using cementing manpower and cementing unit at
various drilling locations.
5) Cementing section has supplied most of the chiksan joints and other necessary
equipments used at Baghjan#5, along with manpower for the special taskforce formed
during the emergency crisis situation in the FY 20-21.
7) Total 04 nos. of cementing jobs were performed using in-house cementing facilities for
well control at BGN#5 under the supervision of M/s Alert.
Provide workshop and calibration services for all measuring instruments used in
Drilling, Workover and Cementing activities.
Ensure that the required safety guidelines are followed as per statutory norms.
The jobs carried out in the section categorically are as follows in brief during the
aforementioned period.
[A] In-house maintenance Services
As per statutory requirement, 9(nine) numbers of Online Gas Monitoring Systems are in
operation for 9(nine) numbers of in-house Drilling Rigs. The Gas monitoring system
were commissioned and decommissioned as per statutory norms to the Drilling Rig
operations. Installations during Rig up and dismantling during Rig down of these
systems were carried out along with the respective rigs with in-house crew members of
instrumentation section. 6 no. of rig up of such Online Gas Monitoring system were
carried out and 6 no. of Rig Down operation were carried out during the period.
4. Reports attended in Drilling TS
Instrumentation Services were also provided for maintenance of Control systems of Air
Dryers in Drilling Rigs and Control systems of Generator Sets in Workover Rigs in
association with Drilling Technical Services section.
• Total no. of such jobs carried out: 40
We have also provided service to Equipment section of Drilling service for calibration of
gauges and pressure switches of BOP unit.
Total no. of such jobs carried out: 25
During that emergency situation, many critical jobs were carried out as follows-.
Before fire caught in the well, calibration of pneumatic pressure switch of BOP
control unit was done mechanically without any delay.
After fire caught in the well, all BOP control unit pressure switches (electrical)
calibration jobs were carried out without any delay.
Emergency maintenance of Air compressor in equipment section & cementing
section.
Calibration of all Pressure gauges of manifold and accumulator were carried out
as requested by user departments/sections.
Apart from the above, Instrumentation services were provided to various subsystems in
Drillometer Workshop for calibration and maintenance of various instruments of all
Drilling and Workover Rigs as well as other ancillary facilities. Total 92 numbers of
calibration jobs had been carried out during this year.
MANPOWER No.
Executive 3
* One workman (JE-1) was demised on 12.01.2021 reducing total manpower strength from 11
to 10.
Participant Organised
S.N Training Date
name By
Online training" ELECTRICAL
Anup Jyoti IIPM,
1 SAFETY – CHALLENGES 07.11.2020
Tamuly Kansbahal
& LEARNING FROM INDUSTRY"
Online training"INDUSTRIAL
Dhurba Jyoti IIPM,
2 HYDRAULICS 21.10.2020
Handique Kansbahal
& PNEUMATICS"
Online training"INDUSTRIAL
Ranjan IIPM,
3 HYDRAULICS 21.10.2020
Chawrok Kansbahal
& PNEUMATICS"
Rig building section played a major role in achieving the Drilling & Work-over operation
progress for the financial year 2020-21 by timely completing Rig-up & Rig-down, Preventive &
Schedule Maintenance along with Installation of new equipment’s within planned time period.
The section also provided day-to-day onsite maintenance support for round the clock drilling
and work over operations in both In-house & Rigs under MMC.
1. A total of 09 nos. of Rig-up & 09 nos. of Rig-down operations for In-house Drilling Rigs.
2. Technical support for 10 nos. of Rig up operation and 12 nos. Rig down operation in
Drilling Rigs under MMC.
3. Rig up & Rig-down also carried out in 04 nos of in-house Work-over Rigs & technical
support to Rigs under MMC.
Write-off & Disposal of 02 no of scrap materials lot (1697 & 1691) from NIA.
1. Process of Invoice against PO-7907901 for “Modification of NAT-110MA rig mast & sub-
structure for compatibility with E-1400 AC-SCR rig”.
Installation of mud flow line from Header box to trip tank directly by-passing the
shaker units in VFD rigs having MI-SWACO solid control system. Which reduced idle
running of shakers during Tripping and thereby preventing damage of the screens and
other parts . This modification helped in saving approximately 5.5 hours per section
drilled and approximately Rs. 2,05,787.00 (Cost of screens) per well drilled.
A Mast High Stand of Rig E-3000 HP rig S-8 has been modified as the original High
Stand of Rig: S-8 got damaged beyond repair. It is worth-mentioning that by
modifying/redesigning the High Stand to use in E-3000 rig, we have not only discarded
an unsafe practice but also saved money from our exchequer for buying a new High
Stand from the original equipment manufacturer (OEM). Also we saved crucial
operational time.
Modified of suction line of vacuum degasser of Rig S-1, S-2, S-3, S-4, S-5 and S-6 for
effective degassing of Mud system.
1. Carried out major overhauling of the Draw-works of Rig: S1, S3, S4, S5, S7, S8 and V1
at Central Workshop.
2. Carried out repairing of the Independent Rotary Drive units of Rig: S4, S5, S7 and S8 at
Rig-Building yard.
3. Replaced input shaft of Rig S-7 and S-8 draw works at central workshop.
4. Repaired I-BOP of top drive system of drilling rig VFD-1 with in-house resources.
5. Repaired damaged Racking board of Rig: V-1 with support from Central work shop
(CWS) followed by NDT.
6. Carried out NDT of mast and substructure of Rig: S-7 under contract no.6110910.
7. Repaired cracked link tilt arm of TDS of Rig V-1 with in-house expertise.
8. Repaired broken piston rod connecting part of link tilt cylinder of Rig V-2 with in-house
expertise & support from CWS.
9. Repaired / interchanged mud-tank system in Rig S-8 , S-6 & S-5
10. Repaired & carried out complete overhauling of KEMTRON shale shaker unit, which is
currently installed at rig S-6.
Installed & commissioned the following new equipment as a replacement of existing old
equipment during the financial year:
Disc Brake:
One no of Disc Brake in E-3000 Draw-works of Rig S-8 at LOC: DIF on 22/03/2021 under
P0-7908488/SDG/P7.
Installed & commissioned 2 sets of ELECTRIC CASING LINE SPOOL at Rig S-6 LOC: NLT and
at rig S-8 LOC: DII under PO-7951214.
DRILL-PIPE SPINNERS:
Three numbers new Drill-pipe spinners commissioned at rig V-1, V-2 and S-8 under PO-
7951258 at LOC: DGF-1, LOC: MGE & LOC: DII respectively.
Workman:
As on 01.04.2021, total work persons in the section are 105. A total of 15 (fifteen) nos. of
work persons have superannuated during the year.
Promotions: A total of 15 nos. of work persons were promoted to their eligible higher grades
in which 02 no’s promoted to Supervisor grade.
Joining: NIL
Training:
01 no. executive attended training cum technology sharing session with ONGC-Tripura
on MANAGE PRESSURE DRILLING.
02 no’s executives attended two days’ webinar on “Dark alleys in Industries leading to
accidents” conducted by ICW-Group.
01 no. executive attended webinar on “operation and maintenance of mechanical seals”
by ICW-group.
04 no’s work-persons attended Mines Vocational Training conducted by L&D
department.
Provided apprenticeship trainings to 30 no’s Poly. Technic & ITI candidates in various
groups.
Pre medical examination of all 15 work-persons were carried out prior to their
retirement in the financial year giving utmost importance towards their health and
hygiene.
Future Projects:
Burnt /replaced Lube oils from all operational Draw-works and other equipment’s are
collected & disposed through contractual service provider as per norms.
Operating philosophy
Besides the day to day on site maintenance jobs to support the round the clock uninterrupted
drilling operations, the major jobs done by the rig section to enhance performance are
highlighted below:
ii) Fabricated /repaired in-house damaged Acoustic Enclosure of 3 Nos. Powerpack of S#2 rig
at LOC:HRX-1. This resulted in cost saving of INR 45,000.00 as against service quote by
M/s GCPL.
iii) Replaced by fabricating existing corroded leaky mud mixer, hopper lines /6’’ bend etc. in
S#2 rig.
iv) Repaired 3 Nos. leaky Vertical Valves & replaced by fabricating 2 Nos. corroded/damaged
leaky Vertical valves in Mud tank system of S#2 rig
v) Fabricated canopy for Vol pump at Loc: CAE ,S#2 rig. Replaced engine of Vol pump.
vi) All engine staircases, canopy of fire trailer pump, decanting pump pillow of rig S#3 are
replaced with permanent iron structure to reduce civil cost and Rig up time.
vii) Rig V#2: Turbochargers of Engine 1 & 4 have been replaced. Injector 'O' Rings have been
replaced with in all CAT 3512B Engines.
viii) Rig S#6: Replaced, Modified Mud & Water Tankage system with existing tankage system
of S#5 rig.
x) Two Nos. CAT Engines Sl. No. CTE00386 & CTE00384 were overhauled in ICE shop
i) Rig S2: Replaced existing G/water pump (Make: BEACON WEIR) by new 02 Nos. of
Multi stage Gauging Water Pump (I& C of GRW Pump) at Loc: HRX-1
ii) Installed and commissioned online monitoring system.
iii) Rig S8: Installed and commissioned Disc Brake cooling unit.
iv) Rig S6: Commissioned 2 Nos. of Water Booster Pump.
iv) Rig V2 : Decanting Pump commissioned.
h) Lube oil dispensing & Evacuating pump : OIL's tender no. KID
4330L21/08 dtd 07.08.2020 for 2000 HP VFD rig : TSR report submitted on
08.12.2020.
New innovation:
i) In Rig S#3, Rig S#4 and Rig S#6: Inhouse fabricated Venturi Jet Pump is used for
cellar suction in all completed wells.
ii) In Rig S#2 fabricated centrifugal cellar pump for cellar suction.
1. Push bottom Switch installed (as a solution for battery
charging & starting problem) in place of damaged panel of 30 KVA DG set of S#2 rig
at LOC: CAE.
Energy Consumption Pattern in Drilling Rigs (Excluding the Chartered Hired Rigs)
EQUIPMENT AVAILABILITY:
MUD PUMPS
RIG S1 S2 S3 S4 S5 S6 S7 S8 V1 V2 DM#5
RHRS 1351 1595 2609 3417 1994 2982 5086 4030 4122 2269 1818
#BREAK NIL NIL NIL 72 NIL 21 NIL NIL 8 92 NIL
DOWN
HOURS
Availability 100 100 100 97.9 100 99.3 100 100 99.8 96.1 100
%
POWER PACKS
RIG S1 S2 S3 S4 S5 S6 S7 S8 V1 V2 DM#5
RHRS 451 490 881 1223 609 994 14792. 1130 983 788 6755
4 9 9 9 8 2 5 0 8 3
#BREAK NIL NIL NIL NIL NIL NIL NIL NIL NIL 241 NIL
DOWN 5
HOURS
Availabilit 100 100 100 100 100 100 100 100 100 76.5 100
y%
RIG S1 S2 S3 S4 S5 S6 S7 S8 V1 V2 DM#5
Maint 26 78 106 119 26 98 49 89 26 116 28
Orders
MANPOWER TRAINED
No of Attendee
Name of the training
Executive Employee
EFFICIENT MANAGEMENT OF
INDUSTRIAL PUMPS 03 -
MECHANICAL SEAL 2 -
MVT(REFRESHER)-ONLINE(B/NO-10) - 9
MANPOWER STRENGTH
Sl Designati Reqd. Total Rig Yard Strength/ Strength/ Strength/ Strength/ Strength/ Strength/
. on/Grad Per Prese and Shift No. of No. of No. of No. of No. of No. of
N e Rig nt Room operable operable operable operable operable operable
o stren requirem strings by strings by strings by strings by strings by strings by
gth ent the end of the end of the end of the end of the end of the end of
2020 2021 2022 2023 2024 2025
Jr.
1 1 5 (1+1) 2 3 3 3 3 2 2 2 2 1 1 0 0
Engineer
Mech.
/Asst.
2 2 21 2 19 9.5 19 9.5 16 8 13 6.5 13 6.5 9 4.5
Mech.
(ICE)
Mech.
/Asst.
3 6 28 (2+4) 6 22 3.7 13 2.17 7 1.17 5 0.83 2 0.33 0 0
Mech.
(Pump)
Technici
4 an 1 7 1 6 6 6 6 5 5 4 4 4 4 3 3
(Welder)
Operator
5 4 14 - 14 3.5 9 2.25 6 1.5 3 0.75 2 0.5 1 0.25
(DDO)
Asst.
6 4 21 - 21 5.25 20 5 16 4 14 3.5 13 3.25 12 3
Operator
Tradesm
an
7 (Pump, 16 66 8 58 3.6 51 3.19 45 2.81 41 2.56 35 2.19 31 1.94
ICE,Weld
er)
8 Total 34 162 19 143 121 97 82 70 56
ADDITIONAL SERVICE :
Drilling Technical Service provided the following support services in BGN#5 in the following
areas:
a) Inhouse Design & Fabrication of hydraulic BOP landing system in Central Workshop.
b) Manning 4 Nos. ONGC & 2 Nos. OIL CMT pumps by Engineers and work persons in both
day and night shifts.
During the financial year 2020-21, the Equipment & Fishing Operation Section of Drilling
Department has played a vital role for overall performance of the department by providing
constant support on 24x7 basis for both Drilling and Work-over activities of the department.
The main jobs that were carried by E&F Section are stated as under:
1. Assembly of Capping stacks for BGN#05 as per M/S Alert design and pressure testing
of the same.(Refer photographs in Annexure)
2. All other related well control equipments like BOPCU, Choke Manifold , Valves were
pressure tested and provided to BGN # 05.
3. Necessary tools and accessories for well killing activity provided to BGN#05.
4. Supplying of various consumables to the Drilling and Workover locations on daily basis
liaising with Materials department.
5. Supplying of all handling gears and other requirements for daily use at Drilling and
Work-over sites.
6. Servicing, maintaining (preventive, scheduled & breakdown) and testing of all rotating,
hoisting, surface & sub-surface equipment/tools and handling gears used at Drilling
and Work-over sites.
7. Servicing, maintaining (preventive, scheduled & breakdown) and testing of all Well
Control Equipment (BOPs, BOPCUs, C & K Manifolds etc.) used at sites
8. Carrying out of NDT of Drilling & Work-over handling gears and all types of tubular
under equipment custody.
9. Servicing and maintaining all types of fishing gears and fabrication of new tools as per
the requirement.
10. Transferring of all heavy equipment and all types of tubulars liaising with Logistics
department with proper scheduling so that all items reach the site in time.
11. Liaising with Field Engineering department for repairing, servicing and fabricating jobs
of drilling equipment at Central Workshop (CWS)
12. Developing Infrastructure of the yard with the available crew and with the help from
Civil Engineering department.
13. Carried out regular office administrative jobs for the work persons (18 permanent
employees, 34 WCLs).
(A) Some of the note-worthy contributions of Equipment & Fishing Operation Section
during the financial year 2020-21 are given below:
Servicing, Repairing & Hydro Testing of BOP and related tools/equipment at Drilling
Yard and Fields-
(1) BOP repairing & testing
13.5/8" x 5M Annular BOP -04 nos.
13.5/8" x 5 M Double Ram BOP -03 nos.
13.5/8" x 10 M Double Ram BOP -03 nos.
13.5/8" x 10 M Annular BOP (New) -02 nos.
13.5/8”x 5M Single Ram BOP -02 nos.
13.5/8” x 10M Single Ram BOP -10 nos.
7 1/16” x 5 M Double Ram -06 nos.
7 1/16” x 10 M Double Ram -15 nos.
NDT Inspection of Drill Pipes/Tubular and Handling Tools: During the year following
NDT inspections were carried out (M/s NDT Laboratories Pvt. Ltd): -
1. 5" OD x G-grade x Drill Pipe (both 6.5/8" & 6.1/2" T/jt) -1382 joints.
2. 5" OD x S-grade x Drill Pipe (6.1/2" T/jt) -451 joints.
3. 5" HWDP -61 joints
4. 6.1/2" OD Drill Collar -29 joints.
5. 8" OD Drill Collar -12 joints
(E) Details of various capital/stock items received / inspected and prepared suitability
report during the year:
Capital items: - -50 No
Stock items: -150 No
Total: - -200 No
The section ensures that Capital and stock items are inspected and suitability reports are
provided at least possible time so that GRN can be made and items be delivered for field
applications. Also Installation & commissioning of the items (wherever applicable) are carried
out as early as possible coordinating with drilling-planning section.
(G) SAP Notifications issued by Equipment & Fishing Section during the year:
Notification to Logistics Dept
1. VTR (M 5) -339 nos.
2. Logistics support (M 1) -12 nos.
3. CWS notification (M 8) -163 nos.
4. Electrical notification(M 9) -18 nos.
5. Civil notification (M 9) -18 nos.
Conclusion:
With the increase in Drilling and Work-over activities over the last few years, there has been a
manifold increase in in-house activities with the existing work force. The present Work Force
is as under:
Executives:04 (Four ) (Level1=02, Level2=01, Level3=01)
Employees: 18 (Eighteen)
WCL: 34 (Thirty four)
It may be mentioned here that besides the conventional day-to-day jobs, the jobs like creation
of E-way Bills, issuance of materials on rental to CH- rigs, record keeping for stringent safety
norms, regular servicing of age-old equipment/tools etc has pressurized the section for
shortage of manpower. To add to its woes, the section has on the contrary been handicapped
due to superannuation of experienced personnel in the recent past. With the present man-
power strength, it is a herculean task to deliver the quality of service that has come to be
expected from the section. A review of the manpower strength allocated to the section is the
need of the hour to enable the section to continue providing quality service in the coming
days. In spite of so many constraint as stated above, tried to put the best and continued to
perform to the best of the ability.
Preamble:
HSE being of paramount importance in E&P Sectors. HSE Section of Drilling Department is
committed to enhance HSE standard and emphasize on Loss Control Management in order to
achieve objectives and operational target of Drilling Department and OIL as a whole.
Purpose
The purpose of this report is to provide factual information related to HSE and within the
HSE SECTION of DRILLING DEPARTMENT covering Drilling Mine for the year 2020-2021. It
details the recent advances, current activities and continuing plans to take forward and
improve the management of HSE. We believe that a business’ full of commitment to its
employees’ health, safety and environmental protection should be its primary concern. it is
our aim to be as clear and transparent as possible when communicating our performance
over the past 12 months (April 2020 – March 2021).
In order to fulfil the objectives, the following roles/ activities are undertaken.
1. Safety
(i) Communicate HSE policy & goal through various medium, prepare guidelines to fulfil the
intention of policies and analyses its implementation
(ii) Inspections and audits of installations and suggest corrective measures.
(iii) Monitoring of HSE measures.
2. Environment
Monitoring & Implementation of EC conditions.
3. Occupational health
Centralized record keeping of employee’s Bio data, Training, IME/PME
IME & PME of the employees
05(Five set) of PA (public addressing system – Intercom) system for In- house drilling Rig has
arrived and commissioning at well site (Rig: S#5, S#7) is in progress by liaisoning with Field
Communication department. The point was closed in Mines Safety committee meeting on
06/02/2020 – after seven years. The remaining three set of PA system will be commissioned
in phase wise at different in house Rigs.
The following is the details of successful steps in bringing PA system in drilling wells
PR-1418446 dated 01.12.2018 (Raised by Field Communication department)
Tender: SDI0827P19 dated 13.03.2019 (through Materials department)
TSR submitted on 25.09.2019 (by Field Communication department)
PO: 7910123 dated 23.01.2020
Date of delivery: 31.07.2020
Landed in Duliajan: 05.02.2021 (Delay due to pandemic situation) and ultimately the five no
of sets were received by Drilling department on 05.02.2021.
The presence of hazards is inevitable in drilling and workover operations and even though
utmost care is taken to prevent incident; it does happen leading to injury to person working
in site. In addition to it, drilling operation is generally carried out in isolated place and
established medical facilities are away from it. In such condition, First Aid is the only
assistance which could be given to any person suffering a sudden illness or injury, with care
provided to preserve life, prevent the condition from worsening, and/or promote recovery.
L&D Department conducts three-day First Aid Training Certificate Program through St John
Ambulance as per Mines Rules 1955. This is restricted to only permanent employees and not
for contractual employees. However, sufficient number of employees could not be trained due
to inability to release participants for operational constraints.
To an extent to overcome above constraints and restrictions for contractual employees, Team
– Drilling HSE has provided “Onsite First aid Training Program” to the contractual personnel
through Civil Defence, Dibrugarh. Also, three-day First Aid Training Certificate Program
through St John Ambulance St. John Ambulance was arranged and trained 120 no of
contractual employees in 2017-18.
Earlier, a joint effort was made by Drilling-HSE section and L&D Department for approval of
the day long “Onsite First Training Program” by Civil Defence, Dibrugarh. The competent
authority has approved for 12 Nos of such training for the Financial year 2019-20, named as
“JIVAKA”, to be conducted on continuous basis for benefit of our company. However due to
COVID-19 pandemic situation we could not carried out the said program in Drilling Mines for
the FY 2020-2021.
Team Drilling-HSE prepared the code of practice for NEAR MISS as part of “LEARNING
FROM EVENT” SYSTEM of Drilling Mine since 2018. The purpose of this code of practice is
to provide a board guideline to establish a uniform and standard NEAR MISS REPORTING,
INVESTIGATION AND AWARD SYSTEM in Drilling HSE office as well as Drilling & Workover
Installations as a proactive step for LEARNING FROM EVENT” SYSTEM for incident /
accident prevention.
Near Miss Winners were selected by a permanent committee constituted under code of
practice as per the sub clause (5.9) of Code of Practice for Near miss- - as “Learning from
Event (LFE)” System.
Accordingly, the first full-fledged ceremony for distributing the awards for the best NEAR
MISSES for the calendar year 2018 was held on 2nd April 2019 at Auditorium of Drilling
Services. However due to COVID-19 pandemic situation we could not carried out the said
award program in Drilling Mines for the FY 2020-2021.
e. HSE Documents
i. Checklist – Total 20 Nos
ii. FORMATS – Total 35 Nos
iii. Rig & Equipment Data – Total 17 Nos (for Drilling Rigs)
iv. Code of Practice (Cop) – Total 05 Nos namely:
1. Cop for Document Management
2. Cop for Record Management and Need Analysis
3. Cop for Near Miss as Learning from Event System
4. Cop for Management of Meeting
5. Cop for Hydrogen Sulphide (H2S) Gas
v. Emergency response plan (ERPs) – Total 03 Nos namely
1. ERP for Blowout - Drilling Mine
2. ERP for Fire Building and Go down of Drilling Services, NIA
(Applicable for Drilling Services, NIA)
3. ERP for Medical Evacuation - Drilling Mine
vi. OIL Mines Regulations – 2017 – 02 Nos (English version & Assamese version)
The inauguration was done by CGM-Drilling Services with felicitation of the IT department’s
personnel on 10th January 2020 at drilling services conference room.
PME is a statutory requirement for all employees working in mine. Operational constraint and
shortage of manpower, restricts release of employees and in turn hampers timely PME
process. In order to comply PME process for ensuring good health of employees, TEAM
DRILLING HSE facilitated and arranged for carrying out PME in a batch of 08 no’s with
representation from each section on daily basis starting in the month of December 2019. This
effort has been made possible due to the extensive support of Occupational Health Services
Team of OIL Medical in carrying out PME & timely release of employee by the various sections
of Drilling Services. The break of the PME for employees of drilling services is as below:
PME of Drilling Services employees could not been complete for emergency health situation
due to COVID-19 .PME OF Drilling Services executive started w.e.f. Jan’2021 and we have
completed 21 Nos of executives till 31.03.2021.
The following formats were introduced for compliance as per ISRS requirement
a. Shift Handover cum record of management Tour cum IM instruction: Shift handover,
IM instructions & Recorded instructions for Management Tours were prevalent in our system
through informal written instructions on register books or back side of DPRs. There was no
approved standards format which was highlighted by DNV-GL auditors during the ISRS audit
review. Accordingly, a Formal FORMAT for Shift Handover cum record of management Tour
cum IM instruction was developed and introduced for use in the installations w. e. f.
February 2020.
LTIF:
For the FY 2020-21, LTIF of 0.045 is recorded in Drilling Mines whereas Company’s (OIL)
LTIF was 0.357. Drilling Services made all possible efforts for minimizing the LTIF and this
milestone has been made possible by employees and executives of drilling services by
ensuring a safe working environment and behavioural safety. Please refer below the accident
statics in Drilling Mines in last eleven years.
2010-11 10 4 0 14
2011-12 3 7 1 11
2012-13 5 5 0 10
2013-14 3 6 0 9
2014-15 2 3 1 6
2015-16 1 5 0 6
2016-17 0 3 1 4
2017-18 1 1 0 2
2018-19 0 1 0 1
2019-20 0 1 0 1
2020-21 0 2 0 2
* Considers Incident from Drilling Mines Only
Awards/Accolades:
Amidst the challenges faced by Drilling Department we never lost our passion to achieve
more. The following awards and accolades received during the FY 2020-21 proves our claim.
plant efficiency in
petroleum sector
S&E department carried out and coordinated various safety audit and inspection during the
period covering all the installations spread over Assam and Arunachal Pradesh. To add value
and increase effectiveness to our Pre spud and Pre workover Safety Audit, the system of
inspection is reworked and new checklists are adopted which covers not only OIL’s policy
commitment on HSE, but also statutory requirement of oil Mines and requirement of OISD.
Following are the various audit carried out during 2020-21.
I. Pre-spud safety audit : 42
II. Internal/surprise safety audit : 13+10 =23
III. Special audit (02 installations) : 02
IV. OISD External Safety Audit : 02
V. DMS Safety Inspection :
i. DRILLING: 02
Total Audit/Inspection: 71
Training:
Statutory and non-statutory training program like Mines Vocational Training (MVT), Refresher
MVT, Gas Testing and Work Permit (GT & WP) Training, First Aid and Fire Fighting Training
were carried out both in-house (MTDC) and WCL and CP with close liaison with L & D
Department. Similarly, First Aid Fire Fighting (FAFF) training was also conducted at well-
sites by the Fire Service Department. Given below is the number of work-persons undergone
training during the year
a. TRAINING: (DEPARTMENT EMPLOYEES)
i. MVT: 16
ii. MVT (R): 60
iii. First Aid and Fire Fighting: 30
iv. Gas Testing and work permit: 27
v. SWAYAM - ON SITE HSE: NIL (not conducted due to COVID)
vi. JIVAKA – ON SIT FIRST AID TRAINING: NIL (not conducted due to COVID)
Though full effort was made, no more OIL- employees, WCL & CP could be trained during the
FY 2020-21 due to COVID pandemic reason.
8. Accident Records:
FY category Name of
Date of Time of Part
2020- of injured Age
accident accident injured
2021 accident person
Sri Shayamal Right
2020- 53 15.08.2020 10.25
Serious Ghose Hand
21 Years at Loc:DGT hrs
(R/No.103775) wrist
cumulative performance/ wellwise performance upto the reporting month, rig count
etc.
Reports/ documents for various departments within OIL like Corporate Office,
Planning, F&A, Administration etc and to different sections within drilling
department on regular basis and as and when required.
Properly maintaining NPT records of drilling rigs/operation in FHQ.
Data Management for Drilling & Work over Operations.
My Annual Plan (MAP): Annual Revenue budgeting for the Department (including well
cost, maintenance cost) for 2020-21 was done as per the developed Excel Format and BPC
and it has been submitted on time. The voluminous job involves cost planning for 38 cost
centers and 41 (including 8 No WDW) Wells, each divided into Rig up – Drilling –
Production Testing – Rig Down phases for multiple direct cost elements for the year.
Inspite of lock down scenerios around the globe, timely mobilized the Whipstock setting &
Window milling services for re-entry wells without hampering progress of drilling
operations.
Carried out Physical verification of 3710 assets pertaining to Drilling Services as per
schedule.
Management Information System (MIS): All the related work done within the stipulated /
scheduled time and hence department has earned reputation of providing all the MIS
related information in time. In addition, planning section submits comprehensive report
on Drilling performance to DGH on monthly basis.
1. Procurement of 05 nos. of new 2000 HP VFD drilling rigs (Project Cost = 1274 Cr),
Tender no. SDG4874P21 published on 14.08.2020, BOD : 11.06.2021.
2. RSS with Mud Engineering Service (Project Cost = 340 Cr),
Tender no. CDG5704P21 published, BOD : 13.05.2021.
3. e-RTMAC under Project Drive, (Project Cost = 126 Cr),
Tender no. CDH6605P21 published on 31.03.2021, BOD: 06.05.2021.
MANPOWER POSITION:
Executives: 08 (Eight ) (Level 3 = 01, Level 2 = 04, Level 1= 03)
Employees: 04 (Four)
Contractual Clerk: 01 (One)
WCL: 02 (Two)
12.0 ADMINISTRATION
Administration Section of the Drilling Department plays a vital role in achieving the Drilling
Target. The main functions of Administration Section are listed below:
1. Personnel and Administration related activities of all executives and Operations Section
Employees of Drilling Department which includes
a. Managing and maintaining record of leave/sick etc.
b. Joining, Absorption, Confirmation, Transfer and separation at departmental level.
c. Processing of career progression at departmental level.
d. Disciplinary actions as and when required.
2. Allocation of shift personnel (both executive and employees) to Drilling locations. A
control room is run on 24 hrs basis to cater to crew deployment, vehicle allocation, any
urgent need like relief crew, emergency vehicle, etc.
Manpower Strength
Training Data
Description No. Of Executives No. Of Employees
MVT/ First Aid/ Gas Testing 3 73
Online training 63 52
In house training 9 06
In Country Training 00 00
Abroad Training / Inspection / 00 00
Conference
* Training records of all sections of Drilling Department, excluding Drilling TS in FHQ.
Apart from this, Job rotation of Executives was done in a phase wise manner as per
requirements as advised by HOD. Also, industrial/apprenticeship training etc. was arranged
for about 85 nos. students from various technical institutions / universities during the year.
4. Developing R&D activities in Drilling & Allied services for methodical and
structured studies of drilling activities and challenges to find out solutions.
5. Bhuban Mitra: Integrated Drilling Environment Management Services as an
integrated solutions for different environment challenges.
6. Managed Pressure Drilling (MPD) as new technological induction.
7. Compact Wellhead as new technological induction.
8. Multilateral Drilling and Multilateral Completions as new technological
induction.
9. Introduction of SOBM as new technological induction along with Chemical
Department.
ACKNOWLEDGEMENT
At the very outset, I take this opportunity to acknowledge the sincere and dedicated efforts put in
by each one of Drilling Department during the year.
Team Drilling hereby expresses its gratefulness to the Corporate Management, Local
Management for their active support and guidance. We would like to acknowledge the support
and co-operation received from various departments.
We would also like to place on record our deep appreciation and acknowledge the intangible
support from various associated departments for their instant and continuous support as and
when required to maintain continuous progress of operations.
ANNEXURES
12 CH-1 (JB) C-HIRED E-2000 1 4677 1 2356 2 7033 15.77 257.79 41.91 0 49.53 31
13 CH-2 (SIL) C-HIRED E-1500 0 0 0 2501 0 2501 20.00 46.62 18.00 0 280.38 84
14 CH-2 QP1 NEW C-HIRED E-2000 0 0 1 149 1 149 61.33 81.33 10.00 0 34.34 15
15 CH-3 (JB) C-HIRED E-1500 1 212 0 0 1 212 0.00 41.89 42.97 0 128.14 84
16 CH-4 (SIL) C-HIRED E-1500 1 450 0 0 1 450 0.00 84.79 0.00 0 4.21 84
17 CH-5 (Quippo) C-HIRED E-2000 0 0 0 0 0 0 0.00 24.21 0.00 0 19.79 24
18 CH-5 (FST-19) C-HIRED E-2000 1 3866 0 153 1 4019 26.00 95.18 25.00 0 96.82 14
20 CH-3 QP2 NEW C-HIRED E-2000 0 4350 0 0 0 4350 94.00 107.35 0.00 0 10.65 20
ANNEXURE – II
1 MFY S-3 Exp J 3950 3955 19-12-2019 28-04-2020 15-05-2020 4 4 22 25 90 99.5 27 16 856 1209
2 DIJ S-8 Exp S 4347 4352 05-11-2019 28-04-2020 03-05-2020 4 4 19 25 120 150.69 27 4 737 879
CH-6
3 MZ-8 (Qp)Ne Exp V 4000 4011 25-07-2019 06-05-2020 14-12-2020 4 4 0 0 250 287 27 125.5 296 425
w
4 TBM CH-3 Exp J 4257 4257 21-11-2019 21-05-2020 31-10-2020 4 4 12 15 120 183 27 42.97 537 708
5 MGJ S-7 Exp J 3860 3872 19-01-2020 28-05-2020 13-06-2020 4 4 18 24 120 131 27 15 693 899
WDW-
6 DM-5 Dev S 1618 1624 07-05-2020 02-06-2020 05-06-2020 2 2 15 16 25 27 5 2 1098 1830
195
7 MFF1 CH-4 Exp J 5032 5022 21-07-2019 29-06-2020 5 4 15 25 120 305 27 463 501 Abandoned
8 MGF S-5 Dev J 3620 3577 14-03-2020 10-07-2020 18-07-2020 3 3 25 25 90 118 10 7 725 922
WDW-
9 DM-5 Dev V 1600 1610 20-06-2020 12-07-2020 20-07-2020 2 2 15 14 25 23 5 2 1256 2129
196
10 DHU S-6 Dev J 2622 2622 01-06-2020 18-07-2020 28-07-2020 3 3 15 23 90 47 10 9 1010 1697
11 NLU S-3 Dev J 3040 3043 15-06-2020 18-08-2020 17-09-2020 3 3 20 23 90 65 10 29 791 1424
CH-6
12 MZ-2 (Quippo Exp V 4000 2735 15-11-2018 04-08-2020 4 2 0 0 250 288 27 289 289 Abandoned
)
13 TBI CH-1 Dev J 4250 4284 10-02-2020 26-09-2020 07-10-2020 4 4 0 0 120 184.29 10 11 667 707
14 DHT S-6 Dev S 3428 3430 13-08-2020 02-11-2020 21-11-2020 3 3 10 7 90 68 10 18 1122 1534
WDW-
15 DM-5 Dev S 1618 1625 08-10-2020 06-11-2020 14-11-2020 2 2 14 13 25 31 5 8 951 1595
200
16 HZB VFD-1 Exp J 4428 4450 23-02-2020 11-11-2020 10-12-2020 4 4 45 43 120 216 27 30 468 627
17 DHO CH-5 Exp J 3864 3866 10-08-2020 18-11-2020 14-12-2020 4 4 0 0 120 90 27 27 1005 1307
18 DII S-8 Exp S 4430 4445 21-05-2020 25-11-2020 25-01-2021 4 4 14 18 120 159 27 57 578 850
19 NLV S-3 Dev S 2580 2582 10-10-2020 30-11-2020 07-12-2020 3 3 19 23 90 51 10 7 970 1540
Window cut
Dev
at 1303m on
20 HRX1 S-2 (Side S 2954 2958 07-10-2020 14-12-2020 21-12-2020 1 1 25 50 60 60 10 7 430 839
9.5/8"
Track)
casing.
Window cut
CH-2 Dev
at 2856m on
21 KUAS QP1 (Side S 3686 3686 26-09-2020 17-12-2020 28.12.2020 4 4 0 17 210 332 10 10 312 338
9.5/8"
NEW Track)
casing.
22 DHW-1 S-4 Dev J 4098 4098 18-06-2020 04-01-2021 09-03-2021 4 4 25 28 120 159 10 44.33 539 784
WDW-
23 DM-5 Dev S 1618 1623 10-12-2020 10-01-2021 13-01-2021 2 2 15 20 25 31 5 3 914 1593
206
24 MGA S-7 Exp J 4174 3915 24-06-2020 21-01-2021 4 3 15 11 120 202 27 0 559 590 Abandoned
Window cut
Dev
at 892m on
25 NLT S-6 (Side S 2795 2802 06-01-2021 21-02-2021 03-03-2021 1 1 14 44.5 50 46 10 7.5 592 1261
13.3/8"
Track)
casing.
WDW#
26 DM-5 Dev S 1618 1623 28-01-2021 21-02-2021 24-02-2021 2 2 12 15 25 24 10 4 1148 2057
205
Production
27 DIW CH-1 Exp J 4640 4677 24-10-2020 28-02-2021 4 4 14 16 137 126 27 32 818 1129 testing is on
progress.
28 DGT S-1 Dev S 3217 3223 10-12-2020 04-03-2021 15-03-2021 3 3 21 66 62 95 10 10 573 1032
29 DIY S-3 Dev S 2945 2952 06-01-2021 08-03-2021 18-03-2021 3 3 15 14.5 62 68 10 9.1 980 1321
WDW# Testing is on
30 DM-5 Dev S 1468 1477 09-03-2021 30-03-2021 2 2 14 11 25 22 10 1 1321.48 2042.29
203 progress.
ANNEXURE – III
Shut Down analysis of Drilling Operation for 2020-21
(Sindhu)
CH-5
(Quippo)
0 0 0 0 19.79 0 0 0 0 19.79 0 19.79
CH-5
(FST- 8000 4019 0 0 0 12.82 0 0 84 0 96.82 0 96.82
19)
CH-6
(Quippo)
4000 0 0 0 0 86.29 0 0 0 0 86.29 0 86.29
CH-6
(QP) 1 0 0 113.67 0 6 0 0 120.67 98.5 219.17
New
CH E-
3000
8250 0 0 0 0 0 0 0 0 0 0 0
TOTA
L
168286 80719 111.08 2.39 0 1133.22 14.13 296.6 324.25 0 1881.67 196.24 2077.91
Rig Days 111.08 2.39 0 1133.22 14.13 296.6 324.25 0 1881.67 196.24 2077.91
Rig Year 0.30 0.01 0.00 3.10 0.04 0.81 0.89 0.00 5.16 0.54 5.69
ANNEXURE – IV
TARGET Percent Rig Year Rig Year Rig Days Actual Rig Year
RIGS
(M)
ACTUAL (M)
Achievement Rig Year lost
Target Available Lost utilized
S-1 9000 3223 35.81 1 1 196.08 0.54 0.46
S-2 10700 3898 36.43 1 1 139.24 0.38 0.62
S-3 9000 8577 95.30 1 1 61.09 0.17 0.83
S-4 7600 4098 53.92 1 1 101.69 0.28 0.72
S-5 9250 4310 46.59 1 1 107.41 0.29 0.71
S-6 8600 7962 92.58 1 1 40.92 0.11 0.89
S-7 9900 7651 77.28 1 1 41.11 0.11 0.89
S-8 9400 4445 47.29 1 1 65.56 0.18 0.82
V-1 8300 3358 40.46 1 1 49.81 0.14 0.86
V-2 10606 4071 38.38 1 1 128.57 0.35 0.65
DM-5 12800 9582 74.86 1 1 97.41 0.27 0.73
CH-1 (JB) 9080 7033 77.46 1 1 62.66 0.17 0.83
CH-2 (SIL) 1500 2501 166.73 0.17 1 280.93 0.77 0.23
CH-2 QP1 NEW 11500 979 8.51 1 0.51 35.28 0.10 0.41
CH-3 (JB) 3700 212 5.73 0.25 0.59 134.91 0.37 0.22
CH-3 QP2 NEW 7200 4350 60.42 1 0.32 11.22 0.03 0.29
CH-4 (SIL) 450 NA 0 0.25 4.21 0.01 0.24
CH-4 (Sindhu) 9900 0 0.00 1 0 0 0.00 0.00
CH-5 (Quippo) 0 0.00 0 0.12 19.79 0.05 0.07
CH-5 (FST-19) 8000 4019 50.24 0.67 0.64 96.82 0.27 0.37
CH-6 (Quippo) 4000 0 0.00 0 0.35 86.29 0.24 0.11
CH-6 (QP) New 0.00 1 1 120.67 0.33 0.67
CH E-3000 8250 0.00 0.75 0 0 0.00 0.00
TOTAL 168286 80719 47.97 17.84 16.78 1881.67 5.16 11.62