JACK-UP DRILLING RIG CORRECTIVE ACTIONS
Content Page
A. APPLICABLE STANDARDS _______________________________________________________________________________ 6
B. OBSERVATION CRITICALITY______________________________________________________________________________ 8
SECTION 1 – Drilling Equipment ______________________________________________________________________________________ 9
1.1 Derrick & Structure _________________________________________________________________________________________________________ 9
1.2 Drawworks ________________________________________________________________________________________________________________ 9
1.3 Crown Block _______________________________________________________________________________________________________________ 9
1.4 Travelling Block ____________________________________________________________________________________________________________ 9
1.5 Elmagco Brake ____________________________________________________________________________________________________________ 9
1.6 Deadline Anchor ___________________________________________________________________________________________________________ 9
1.7 Top Drive Unit _____________________________________________________________________________________________________________ 9
1.8 Rotary Table ______________________________________________________________________________________________________________ 9
1.9 Pipe Spinning Wrench ______________________________________________________________________________________________________ 10
1.10 Manual Tongs ____________________________________________________________________________________________________________ 10
1.11 Slips, Collars, Elevators _____________________________________________________________________________________________________ 10
1.12 Ezy-Torq Unit _____________________________________________________________________________________________________________ 10
1.13 Iron Roughneck/Hawk Jaw __________________________________________________________________________________________________ 10
1.14 Drill String _______________________________________________________________________________________________________________ 10
1.15 Drill Subs ________________________________________________________________________________________________________________ 10
1.16 Fishing Tools _____________________________________________________________________________________________________________ 10
1.17 Well Testing Equipment _____________________________________________________________________________________________________ 11
1.18 Casing Stabbing Board _____________________________________________________________________________________________________ 11
1.19 Tuggers, Sheaves and Man-Riding Winches ____________________________________________________________________________________ 11
SECTION 2 – MUD SYSTEM _________________________________________________________________________________________ 12
2.1 Main Mud Pumps __________________________________________________________________________________________________________ 12
2.2 Centrifugal Pumps _________________________________________________________________________________________________________ 12
2.3 Degasser / Desilter / Desander _______________________________________________________________________________________________ 12
2.4 Shale Shaker _____________________________________________________________________________________________________________ 12
2.5 Mud Agitators _____________________________________________________________________________________________________________ 12
2.6 Mud Preparation System ____________________________________________________________________________________________________ 12
2.7 Bulk Air System, Tanks & Hoppers ____________________________________________________________________________________________ 12
Asset: Inspected By: Inspection Date:
Doc Title: Rig Inspection Report Revised By: Approved By;
template
Doc Numbe Revision: A Approval Date:
Page 2 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
2.8 Cement Unit ______________________________________________________________________________________________________________ 12
2.9 Standpipe Manifold & Rotary Hoses ___________________________________________________________________________________________ 13
SECTION 3 – WELL CONTROL EQUIPMENT ____________________________________________________________________________ 14
3.1 Ram Type BOP ___________________________________________________________________________________________________________ 14
3.2 Annular Type Preventer _____________________________________________________________________________________________________ 14
3.3 Gate Valves ______________________________________________________________________________________________________________ 14
3.4 Cameron Style Hub Clamps _________________________________________________________________________________________________ 14
3.5 Hydraulic BOP Control Unit __________________________________________________________________________________________________ 14
3.6 BOP Remote Control System ________________________________________________________________________________________________ 14
3.7 Choke and Kill Manifold _____________________________________________________________________________________________________ 14
3.8 Flexible High Pressure Hoses ________________________________________________________________________________________________ 14
3.9 Diverter System ___________________________________________________________________________________________________________ 15
3.10 BOP Hoisting System ______________________________________________________________________________________________________ 15
3.11 Mud Gas Separator ________________________________________________________________________________________________________ 15
SECTION 4 – MARINE EQUIPMENT ___________________________________________________________________________________ 16
4.1 Ballast and Preload System__________________________________________________________________________________________________ 16
4.2 BOP Hoisting System ______________________________________________________________________________________________________ 16
4.3 Jacking System ___________________________________________________________________________________________________________ 16
4.4 Anchor Winch System ______________________________________________________________________________________________________ 16
4.5 Overflow and Vent Checks __________________________________________________________________________________________________ 16
4.6 Navigation Equipment (Fog, Lights) ___________________________________________________________________________________________ 16
4.7 Watertight Integrity and Compartments _________________________________________________________________________________________ 16
4.8 Communications Equipment _________________________________________________________________________________________________ 16
4.9 General Operations ________________________________________________________________________________________________________ 17
4.10 Towing Systems __________________________________________________________________________________________________________ 17
SECTION 5 – POWER PLANT ________________________________________________________________________________________ 18
5.1 Main Diesel Engines _______________________________________________________________________________________________________ 18
5.2 Emergency Generator ______________________________________________________________________________________________________ 18
5.3 Third Party Auxiliary Engines_________________________________________________________________________________________________ 18
5.4 Air Compressors __________________________________________________________________________________________________________ 18
5.5 HVAC (Heating, Ventilation, Air-Conditioning ____________________________________________________________________________________ 18
5.6 Salt Water Service System __________________________________________________________________________________________________ 18
5.7 Cranes __________________________________________________________________________________________________________________ 18
5.8 Watermakers _____________________________________________________________________________________________________________ 18
Asset: Inspected By: Inspection Date:
Doc Title: Rig Inspection Report Revised By: Approved By;
template
Doc Numbe Revision: A Approval Date:
Page 3 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
5.9 Fuel Oil Purifier ___________________________________________________________________________________________________________ 19
5.10 Pipework & Piping Systems __________________________________________________________________________________________________ 19
5.11 Rig Skidding Systems ______________________________________________________________________________________________________ 19
SECTION 6 – ELECTRICAL __________________________________________________________________________________________ 20
6.1 Main Generators and Controls _______________________________________________________________________________________________ 20
6.2 Main Transformers _________________________________________________________________________________________________________ 20
6.3 SCR Systems ____________________________________________________________________________________________________________ 20
6.4 Main Switchboards ________________________________________________________________________________________________________ 20
6.5 Distribution Panels _________________________________________________________________________________________________________ 20
6.6 DC Motors _______________________________________________________________________________________________________________ 20
6.7 AC Motors _______________________________________________________________________________________________________________ 20
6.8 Motor Control Centres ______________________________________________________________________________________________________ 20
6.9 Lighting System (Main) _____________________________________________________________________________________________________ 21
6.10 Lighting System (Emergency) ________________________________________________________________________________________________ 21
6.11 Portable Lighting __________________________________________________________________________________________________________ 21
6.12 Batteries, Chargers and UPS ________________________________________________________________________________________________ 21
6.13 Fire, Gas, General _________________________________________________________________________________________________________ 21
6.14 Telephone and PA System __________________________________________________________________________________________________ 21
6.15 Electrical Outlets __________________________________________________________________________________________________________ 21
6.16 Cables/Cable Supports _____________________________________________________________________________________________________ 21
6.17 Earth Protection ___________________________________________________________________________________________________________ 22
6.18 Welding Equipment ________________________________________________________________________________________________________ 22
6.19 Instrumentation ___________________________________________________________________________________________________________ 22
6.20 Explosion Proof Equipment __________________________________________________________________________________________________ 22
SECTION 7 – SAFETY ______________________________________________________________________________________________ 23
7.1 Automatic Fire Detection System _____________________________________________________________________________________________ 23
7.2 Flammable Gas Detection ___________________________________________________________________________________________________ 23
7.3 H2S Gas Detection ________________________________________________________________________________________________________ 23
7.4 Fire Suppression CO2/Halon _________________________________________________________________________________________________ 23
7.5 Fixed Fire Fighting System __________________________________________________________________________________________________ 23
7.6 Portable Fire Extinguishers __________________________________________________________________________________________________ 23
7.7 Breathing Apparatus _______________________________________________________________________________________________________ 23
7.8 Helideck Foam Systems ____________________________________________________________________________________________________ 23
7.9 Helicopter Operations ______________________________________________________________________________________________________ 24
Asset: Inspected By: Inspection Date:
Doc Title: Rig Inspection Report Revised By: Approved By;
template
Doc Numbe Revision: A Approval Date:
Page 4 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
7.10 Abandon Rig and Escape routes/Equipment_____________________________________________________________________________________ 24
7.11 First Aid and Sick Bay Facilities_______________________________________________________________________________________________ 24
7.12 Emergency Procedures _____________________________________________________________________________________________________ 24
7.13 Survival and Lifesaving Equipment ____________________________________________________________________________________________ 24
7.14 Lifeboats and Davits _______________________________________________________________________________________________________ 24
7.15 Liferafts and Davits ________________________________________________________________________________________________________ 24
7.16 Lifting and Handling ________________________________________________________________________________________________________ 24
7.17 Decks, Walkways and Ladders _______________________________________________________________________________________________ 25
7.18 Accommodation ___________________________________________________________________________________________________________ 25
7.19 Pollution Control and Containment ____________________________________________________________________________________________ 25
7.20 Housekeeping ____________________________________________________________________________________________________________ 25
7.21 Permit to Work System _____________________________________________________________________________________________________ 25
7.22 Drilling Safety _____________________________________________________________________________________________________________ 25
7.23 COSHH _________________________________________________________________________________________________________________ 25
SECTION 8 – PREVENTATIVE MAINTENANCE SYSTEM __________________________________________________________________ 26
8.1 Maintenance Network ______________________________________________________________________________________________________ 26
8.2 Maintenance Recording System ______________________________________________________________________________________________ 26
8.3 Equipment History Files/Records _____________________________________________________________________________________________ 26
8.4 Critical Spares ____________________________________________________________________________________________________________ 26
SECTION 9 – TRAINING _____________________________________________________________________________________________ 27
9.1 Personnel Concerns _______________________________________________________________________________________________________ 27
9.2 Additional Training Requirements _____________________________________________________________________________________________ 27
9.3 Positive feedbacks _________________________________________________________________________________________________________ 27
Page 5 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
A. APPLICABLE STANDARDS
Manufacturers
AREA OF OPERATION APPLICABLE STANDARDS
Recommended Practices
API, ASME, IEE, IEC, *IADC, Caterpillar, Shaffer,
Modu Code, ABS, SOLAS Cameron, EMD, National,
International Rigging & Lifting Baylor
Handbook (IRLH),
* Note:
To accompany the above listed codes of practice, regulations and legislature the IADC Drilling Manual will also be referenced as being representative of the
current “good oilfield practice”.
API Spec 4G Recommended Practice for Use and Procedures for Inspection, Maintenance, and Repair of Drilling and Well Servicing Structures
API Spec 7-2 Specification For Threading and Gauging of Rotary Shouldered Thread Connections
Page 6 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
API Spec 7K Specification for Drilling & Well Servicing Equipment
API Spec 7B-11C Specification For Internal-Combustion Reciprocating Engines For Oil Field Service
API RP 7L Procedures for Inspection, Maintenance, Repair, and Remanufacture of Drilling Equipment
API RP 7C-11F Recommended Practices For Installation Maintenance and Operation of Internal Combustion Engines
API RP 49 Recommended Practices For Safe Drilling of Well Containing Hydrogen Sulfide
API STD 53 Recommended Practices For Blow Out Protection Equipment Systems For Drilling Wells
API RP 54 Recommended Practices For Safety and Health For Oil and Gas Well Drilling and Servicing Operations
API RP 500 Recommended Practice for Classification of Locations for Electrical Installations at Petroleum Facilities Classified as Class 1, Division 1 and
API RP 505 Recommended Practice for Classification of Locations for Electrical Installations at Petroleum Facilities Classified as Class 1, Zone 0,
Zone 1, and Zone 2
Page 7 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
B. OBSERVATION CRITICALITY
Critical:
An observation defined as critical relates to a serious failure of equipment or system which has the potential to cause
injury to personnel, damage to the environment or compromise the current operation.
Major:
An observation defined as major relates to a significant failure of equipment or system which has the potential to cause
capital equipment downtime or adversely affect the current operation.
Minor:
An observation defined as minor relates to an equipment or system defect which cannot be categorised as above and
which does not meet the requirements of the referenced standard or other codes of practice in use at the time of the survey.
Page 8 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 1 – Drilling Equipment
1.1 Derrick & Structure
1.1.1
1.2 Drawworks
1.2.1
Page 9 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 1 – Drilling Equipment
1.9 Pipe Spinning Wrench
1.91
Page 10 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 1 – DRILLING EQUIPEMENT
1.17 Well Testing Equipment
1.17.1
Page 11 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 2 – MUD SYSTEM
2.1 Main Mud Pumps
2.1.1
Page 12 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 2 – MUD SYSTEM
2.9 Standpipe Manifold & Rotary Hoses
2.9.1
Page 13 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 3 – WELL CONTROL EQUIPMENT
3.1 Ram Type BOP
3.1.1
Page 14 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 3 – WELL CONTROL EQUIPMENT
3.9 Diverter System
3.9.1
Page 15 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 4 – MARINE EQUIPMENT
4.1 Ballast and Preload System
4.1.1
Page 16 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 4 – MARINE EQUIPMENT
4.9 General Operations
4.9.1
Page 17 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 5 – POWER PLANT
5.1 Main Diesel Engines
5.1.1
5.7 Cranes
5.7.1
5.8 Watermakers
5.8.1
Page 18 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 5 – POWER PLANT
5.9 Fuel Oil Purifier
5.9.1
Page 19 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 6 – ELECTRICAL
6.1 Main Generators and Controls
6.1.1
6.6 DC Motors
6.6.1
6.7 AC Motors
6.7.1
Page 20 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 6 – ELECTRICAL
6.9 Lighting System (Main)
6.9.1
Page 21 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 6 – ELECTRICAL
6.17 Earth Protection
6.17.1
6.19 Instrumentation
6.19.1
Page 22 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 7 – SAFETY
7.1 Automatic Fire Detection System
7.1.1
Page 23 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 7 – SAFETY
7.9 Helicopter Operations
7.9.1
Page 24 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 7 – SAFETY
7.17 Decks, Walkways and Ladders
7.17.1
7.18 Accommodation
7.18.1
7.20 Housekeeping
7.20.1
7.23 COSHH
7.23.1
Page 25 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 8 – PREVENTATIVE MAINTENANCE SYSTEM
8.1 Maintenance Network
8.1.1
Page 26 of 27
JACK-UP DRILLING RIG CORRECTIVE ACTIONS
No. Recommendations Standards Criticality Completed Verified
SECTION 9 – TRAINING
9.1 Personnel Concerns
9.1.1
Page 27 of 27