WEEKLY PROGRESS REPORT NO.

04
PROJECT: AL FARDAN TOWER 2 PROJECT DETAILS: G+4 PARKINGS+11
CLIENT: AHMED AL FARDAN PLOT NO: 243
ENGINEERING: Gulf International Engineering Consultants & Project Management AREA: QASMIYAH,MAHATA -SHARJAH
MAIN CONTRATCOR: Alserh Alkabeer Construction LLC PERIOD: (July 18,2020 to July 24,2020)
MEP CONTRACTOR: MASTER LINK TECHNICAL SERVICES LLC SUBMITTED BY: MASTER LINK TECHNICAL SERVICES LLC
1. AVAILABLE MANPOWER Per Day 2. SHIFT DETAILS

SKILLED UN-SKILLED Total Weather:


HVAC & CHWP 0
ELEC. 4 4 8 Work Shift A C
GAS 0 0 0 Working Hours
PLUM. 1 1 2
FLS 0 0 0
TOTAL 5 5 10

3. WORK PERFORMED

S/N SCOPE OF WORK LOCATION CUM Completed Last Report Precent Completed CUM REMARKS

Installation of containment for electrical, SMATV & ETISALAT and PVC


1 level 1 0% 40% 40% ongoing
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
2 level 2 100% 0% 100% COMPLETED
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
3 level 3 0% 0% 0% Awaiting Civil Clearance
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
4 level 4 100% 0% 100% COMPLETED
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
5 level 5 0% 0% 0% Awaiting Civil Clearance
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
6 level 6 100% 0% 100% COMPLETED
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
7 level 7 0% 0% 0% Awaiting Civil Clearance
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
8 level 8 100% 0% 100% COMPLETED
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
9 level 9 65% 35% 100% Completed
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
10 level 10 0% 0% 0% Awaiting Civil Clearance
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
11 level 11 0% 0% 0% Awaiting Civil Clearance
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
12 ROOF 100% 0% 100% COMPLETED
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
13 TOP ROOF 100% 0% 100% COMPLETED
sleeves
Installation of containment for electrical, SMATV & ETISALAT and PVC
14 PARAPET 100% 0% 100% COMPLETED
sleeves
4. QA/QC INSPECTIONS. 5. DRAWINGS AND SUBMITTALS
S/N Description Location Ref NO Date Status S/N Description Location Ref NO Date Status
July
1 MEP Clearance for prior to start the slab concrete Work 1
Top Roof CL NO:010 21,2021 Approved
IR for containment of light,power socket(FCU& Preaction
2 System),F.A,Rain Water Pipe, SMATV Riser Sleeves, Lift
July 2
Room Isolator
Top Roof MLP/243/014 22,2020 Approved

3 IR for containment of power socket,SMATV &Telephone July 3


9th floor MLP/243/015 22,2020 Approved
4 4
5 5
6 6
7 7
8 8
9 9
10 10

6. PLANNED/ACTUAL MANPOWER

Planned Manpower Calculation/Day No. Hrs T. Hrs. Actual Manpower Calculation/Day No. Hrs T. Hrs.
HVAC/CHWP 0 8.0 0 HVAC/CHWP 0 8.0 0
Skilled 0 8.0 0 Skilled 0 8.0 0
Unskilled 0 8.0 0 Unskilled 0 8.0 0
PLUM. 0 8.0 0 PLUM. 0 8.0 0
Skilled 0 8.0 0 Skilled 1 8.0 8
Unskilled 0 8.0 0 Unskilled 1 8.0 8
ELEC. 0 8.0 0 ELEC. 0 8.0 0
Skilled 0 8.0 0 Skilled 4 8.0 32
Unskilled 0 8.0 0 Unskilled 4 8.0 32
GAS. 0 8.0 0 GAS. 0 8.0 0
Skilled 0 8.0 0 Skilled 0 8.0 0
Unskilled 0 8.0 0 Unskilled 0 8.0 0
FLS. 0 8.0 0 FLS. 0 8.0 0
Skilled 8.0 0 Skilled 8.0 0
0 0
Unskilled 0 8.0 0 Unskilled 0 8.0 0

TOTAL 0 0 TOTAL 10 80.0

480

7. Remarks

RECEIVED BY:

Contractor : Alserh Alkabeer Construction LLC

Signature :

Date

Page 1 of 1