Date:06-Jun-14

DAILY PROGRESS REPORT FOR NC186, NC115 AND I/R FIELDS


El-Sharara Oil Fields
Construction Department
NC - 186 Highlights
I/R M1: Roxar fiber optic termination damage, visited by Telecom Department, no repair as yet. Now with Telecom Tripoli 13/05/13 (J&P).
I/R M2/M4: Construction activities on GS facilities. On hold.
I/R: Fibre Optic system investigation, completed and report sent to Tripoli Engineering for resolution.
IR Field M1/M2/M3: Ongoing field checks in preparation for commissioning (Air System). M2 Air Package checks.
H-Field South: Asphalt road: Laying and compaction of asphalt binder course in progress.
NC186 H-South: Inspection made of General Condition of Roxar control panel, PCS control panel, general area.
H' North to 'H' South 12" Trunk line: Excavation works and backfilling of trunk line in progress.
J-GS1/J-GS2/J-GS3: Construction activities on GS facilities, ongoing (J&P).
J-GS3: Electrical activities ongoing.
NC186 GOSP to Black Top Mainline welding completed, approximate 80 joints
NC186 to H North from black top at NC186 to H North: Tie-in welding, Coating and lower & lay complete. Backfill complete.
NC186 to H North to H South: Tie-in welding and coating in progress/ongoing
K-GS: Construction activities on GS facilities in progress (FIA). WI Manifold reinstatement ongoing, MPFM and Pig Launcher piping hydro testing - preparation ongoing.
NC186 WSW 21 to J-GS3 6" Flow line: Mechanical/Piping activity completed.
Survey on NC186 H-South Oil Manifold submitted
B-Field Chemical injection, awaiting OPS to tie-in to Manifold
B-Field Sector C: Fabrication/installation of instrument air piping and raw water piping ongoing. Instrument Air Piping completed.
B Field Sector C Control Building: Shuttering and steel fixing of roof slab, complete. Preparatory works for casting concrete in progress.
WIW J23i to JGS2 (FIA) pipe hauling started, still waiting on Tripoli for the OK to start welding. Pipe hauling completed.
B field Sector C Chemical injection skid, function test/commissioning in J&P yard, complete. Skids will be transported to location for hook-up on completion of civil activities.
Preparation for commissioning the 'B' Field raw water package in J&P Yard.
B Field: excavation works for OHTL (5 Nos.) for flow line GOSP B to B43, complete.
NC - 115 Highlights
CCX: New Accom Blocks: Block 52/54/55/56: Tiling works almost complete. Blocks 53 Tiling works in Progress.
Airport Electrical System & Navigation Lights: Plastering activities in progress at block walls of Electrical building. Hand excavation works for cable trench from CCX switchgear building to Airstrip
electrical building, in progress.
Landfill Building: Painting works for internal walls ongoing. Tiling works ongoing (awaiting additional delivery of tiles).
Extension of Departure Building: Removal of roof beam props, complete.
GOSP B to B43 Oil Flow line (J1P) approximate 4.017 KM: Pipe stringing in progress. Main line welding in progress.
NC-115 EPC of Electrical system: Fibre optic cable pulling from Admin Building (CCX) to airport area in progress.
H-Field OW N03 Transport of OHTL material in progress. Installation of "take-Offs" at Terminal Tower ongoing.
Action Points / General Information
Production from all fields has shutdown indefinitely. All protesters have now struck camp and have moved off site but valves on export line are still closed.

Page 1 of 11
Date: 06-Jun-14 DAILY PROGRESS REPORT FOR NC186, NC115 AND I/R FIELDS
El-Sharara Oilfields
Construction Department
PROGRESS %
PROGRESS Remarks

Prev To Date %
%

GATHERING STATION M1

Oil Manifold Extension


Area grading using sub-base materials ongoing. 60% 60%
AREVA Electrical Building B
Installation of breaker - Bus tie 80% 80% AREVA to advice this scope
ABB PANEL
Instrument - Pre-commissioning
Instrument - Commissioning
GATHERING STATION M2
Electrical Switchgear
Installation of A/C units (BUS A) 90% 90% AC Remote control not supplied by Areva
Installation of 110V DC Batteries (BUS A) 65% 65%
Instrument Air System
Instrument Compressor multicore cable installation 90% 90%
Asphalt Road M4 to M2
Laying and compaction of binder and wearing course and embankment of side shoulders 100% 100% Remaining paint markings for road C/L and edges
ABB PANEL (PCS)
Instrument - Cable loop check 90% 90%
Instrument - Pre-commissioning 90% 90%
Instrument - Commissioning
Installation and glanding of control and FO cable to Roxar panel 75% 75%
GATHERING STATION M3
DOL PAD-1, 2 & 3
Area grading using sub-base material ongoing. 30% 30%
AREVA Electrical Building A
Installation of bus tie 95% 95% By Vendor
AREVA Electrical Building B
Received Battery Terminal Connections for UPS Battery Bank from ALSTOM 50% 50% 12V Battery shortage = 12 nos.
Main Transformer ET1831 A/B
Assembled as per instructions. The off-center 6.6KV insulation bushing on secondary side voltage output on transformer ET-1831A. Report forwarded to Engineering. AREVA to witness
Construction, testing and pre-commissioning 1 No. 3 slots WI manifold
Glanding & Termination of instrument cables in Field JB 98% 98%
ABB PANEL (PCS)
Instrument - Pre-commissioning

Page 2 of 11
PROGRESS %
PROGRESS Remarks

Prev To Date %
%

Instrument - Commissioning
GATHERING STATION M4
Electrical Switchgear
110V DC Charger Battery 10% 10% Battery shortage = 12 nos. (On-Hold)
Installation of Instrument multi-core cables from JBs at Water Manifold area to Switchgear Containers, glanding cables, etc. 95% 95%
Installation of earthing system for marshaling cabinet (ABB) 95% 95%
Switchyard Area

ABB PANEL (PCS)


Instrument - Cable loop check 90% 90%
Instrument - Pre-commissioning 90% 90%
Instrument - Commissioning
ACTIVITIES IN OTHER AREAS
GRE PIPING SYSTEM - MAN / FIA - NC115 GOSP-A & NC115 GOSP-B

Fuel Gas heater Commissioning activities E & I Control Panel 1 x 2 98% complete. PCS Mod's complete. E132B
98% 98% Await test. Availability Production
NC186 - GOSP 'A'
NC186 - B-FIELD
Chemical Injection Skid 'B' Field Oil Gathering Manifold
Tubing from C.I. skid to manifold 90% 90%
Earthing system for Chemical Injection skid Z-1151 unit 2 100% 100%
Installation of cable trays for Chemical Injection skid Z-1151 unit 2 100% 100%
Installation of power cables for Chemical Injection skid Z-1151 unit 2 100% 100%
NC186 - SECTOR C
NC186 - ''B' Field SECTOR C
Shuttering, steel fixing and cast concrete to ground beams (2nd half section of Control building) 100% 100%
Shuttering, steel fixing and cast concrete to floor slab (1st half section of Control building) 100% 100%
Scaffolding and formworks for roof slab of control building 100% 100%
Steel fixing to roof slab beams (Control Building) 95% 100%
Sump Tank: Bitumen coating and backfilling around walls 50% 50%
Sump Tank: Cast concrete to walls of valve chamber 100% 100%
Chemical Injection skid Z-116: Shuttering and steel fixing and cast concrete. 100% 100%
Fabrication / installation of drain piping to Sump tank 90% 90%
Fabrication / installation of instrument air piping 90% 90%
Fabrication / installation of raw water piping 90% 90%
Perimeter Lighting Pole Foundation: Excavation and base course compaction 100% 100%
Installation of Ducting for Compressor 100% 100%
Installation of 10 Slot Oil Manifold, structure and piping 100% 100%

Page 3 of 11
PROGRESS %
PROGRESS Remarks

Prev To Date %
%

Installation of perimeter fences 100% 100%


Installation of gates 100% 100%
Electrical
Glanding and termination of power cables in the Electrical DBs 100% 100%
Laying of power cables for the flood lights 95% 95%
Insulation, resistance and continuity tests of power cables 30% 30%
Installation of power cables from Main DB to Sub DBs 100% 100%
Installation of PVC boxes and pipes (for electrical works) in roof slab of control building 80% 90%
Instrumentation
Instrument Installation 90% 90%
Cable installation and glanding 60% 60%
JB installation 100% 100%
Instrument termination 50% 50%
NC186 - B Field 10" Trunk Line From Sector C to B-GS (5833M)
Tie-in to Pig Launcher
Sector 'C' Manifold Anchor Block
Tie-in to Pig Receiver
B' Field Manifold Anchor Block
Trunk line Stringing 100% 100%
Trunk line Welding 95% 95%
Trunk line Trenching 100% 100%
Trunk line Wrapping 100% 100%
Laying of Fibre Optic cable 90% 90%
Trunk line Backfill 100% 100%
Trunk line Section Tie-In Welding 95% 95%
Trunk line Cleaning and Hydro Test
Reinstatement of piping
CP Installation & Cad Weld 100% 100%
Installation of CP Post 100% 100%
Instrument Installation 90% 90%
Painting Well Head & Manifold Piping
NC186 - H-FIELD
Asphalt Road to H-South
Preparation of sub-base layer and base-course layer (first & second layer) 100% 100%
Spraying of MCO 100% 100%
Preparation & stock piling of Base-course materials 100% 100%
Laying and compaction of asphalt binder course 82% 89%
Fixing of reference points for slope and elevation of binder course 93% 95%

Page 4 of 11
PROGRESS %
PROGRESS Remarks

Prev To Date %
%
H - South 66KV T-Junction Sub-station
Inspection of ABB Control Container, issue with incoming cable glanding, informed FIA of modifications required 0% 0% Awaiting gland plates (FIA)
H-South - 66KV OHTL Tower Extension / Power Supply to J&K Fields (10 Nos)
Pretest of earthing resistance 80% 80%
Stringing between DT-37H-3 to AT-37H-2 50% 50% On Hold
NC186 GOSP to H North - H South 12" Trunk Pipeline:
Above Ground piping in GOSP-A 0% 0%
Above Ground piping in H-North 0% 0%
Above Ground piping in H-South 0% 0%
Manifold piping supports 0% 0%
Flow line stringing, GOSP-A to H-North 100% 100%
Flow line stringing, H-North to H-South 97% 97%
Flow line welding, GOSP-A to H-North. Main Line welding completed. 100% 100%
Flow line welding, H-North to H-South 92% 92%
Flow line trenching 70% 72%
Flow line wrapping Factory coated pipe/joint coating only, GOSP-A to H-North 95% 95%
Flow line wrapping Factory coated pipe/joint coating only, H-North to H-South 25% 50%
Flow line reinstatement 0% 0%
Flow line section tie-In welding GOSP A to H North 75% 75%
Flow line cleaning & hydro test 0% 0%
Flow line backfill 65% 65%
Installation of CP post & CAD weld 0% 0%
Painting well head & manifold piping 0% 0%
NC115 B - FIELD
GOSP B TO B43 OIL Flow Line 4.07 KM
Flow line welding 0% 10%
Flow line Trenching 0% 0%
Flow line Wrapping 0% 0%
Flow line Stringing pipes 0% 25%
Flow line Backfill 0% 0%
Flow line Section Tie-In Welding 0% 0%
Flow line Cleaning and Hydro Test 0% 0%
Reinstatement of piping 0% 0%
Oil Well B43 - OHTL Towers assembling 10% 10%
Excavation works for (5 Nos) of OHTL foundation 0% 0%
NC115 N - FIELD

N-03 Flow Line Electrification (OHTL 33KV) SWW-28-390, DWW-28-400, TWW-28-400-10 (FIA)

Page 5 of 11
PROGRESS %
PROGRESS Remarks

Prev To Date %
%

Rebar works for foundation of Towers 100% 100%


Cast concrete to foundation of Tower (base and pedestals) 100% 100%
Backfilling around Tower foundations 100% 100%
Installation of tower base 100% 100%
Installation of pre-assembled OHTL Towers 100% 100%
Installation of earthing system 100% 100%
Transport of OHTL Material 40% 60%
Stringing of conductors at OHTL towers 0% 0%
Installation of terminal tower take-offs 0% 40%
Shutdown / tie-in works of new OHTL to existing 33Kv OHTL 0% 0%
Excavate and lay REDA power, control and earth cables from TT to WH junction box 0% 0%
NC115 O - FIELD
OW-014 to Oil Manifold
Above Ground Well Head Piping 100% 100%
Well Head Pipe Supports 100% 100%
Well Head Anchor Block 100% 100%
Filter Foundation: Excavation, backfilling with base course & compaction & blinding concrete N/A N/A
Filter Foundation: Shuttering & steel fixing for foundation N/A N/A
Above Ground Manifold Piping 100% 100%
Manifold Piping Supports 100% 100%
Manifold Anchor Block Existing
Flow line welding 100% 100%
Flow line Trenching 100% 100%
Flow line Wrapping 100% 100%
Flow line Stringing 100% 100%
Flow line Backfill 100% 100%
Flow line Section Tie-In Welding 100% 100%
Flow line Cleaning and Hydro Test 100% 100%
Reinstatement of piping 100% 100%
CP Installation & Cad Weld 100% 100%
Instrument Installation 10% 100%
Painting Well Head & Manifold Piping 100% 100%
O&P Gathering Station - Oil Manifold 5 Slot Extension (J&P)
Civil works for Oil Manifold 5 slot extension 100% 100%
Installation of Oil Manifold 5 slot extension 100% 100%
Final tie-in of Oil Manifold 5 slot extension with existing manifold 100% 100%
J&K FIELDS
J-GS1 - JK Fields

Page 6 of 11
PROGRESS %
PROGRESS Remarks

Prev To Date %
%

Trenching for Underground Electrical and Instrument Cables 95% 95%


Backfilling for Underground Electrical and Instrument Cables 95% 95%
Installation of Process DB, cable gland and termination 40% 40%
Sub-Station
Transformer Shelter: Plastering works for Transformer firewall 15% 15%
Installation of precast concrete EDG culvert 80% 80%
Oil Manifold
Multicore cable installation 80% 80%
Multicore cable glanding and termination 30% 30%
WI Manifold
Cable glanding instrument to JB 90% 90%
Piping works manufacturing and prepare pipework for oil manifold M2 in workshop 0% 0%
DOL Pads
Earthing and CAD weld 90% 90%
Glanding and Termination of MV Power Cables at DOL Pad and Manifold area DBs 80% 80%
WIW J-22i to J-GS1 (1700 M)
Instrument Installation 50% 50%
J-GS2 - JK Fields
Formworks and rebar for metering slab foundation 60% 60% On-hold
Commissioning of C.I. Skid 50% 50% Await Sun Shelter ongoing
Pre-casting of EDG cable Culvert 40% 40%
Base course compaction for foundation of Transformer Shelter 50% 50%
Instrument Air & Compressor Shelter: Installation of precast foundation 100% 100%
Instrument Air & Compressor Shelter: Backfilling around foundations 50% 50%
Assembly of Gantry 33KV for Switchyard (J&P Yard) 40% 40%
WSW J-20 to J-GS2 WI Manifold (FIA)
Above Ground Well Head Piping 100% 100%
Well Head Pipe Supports 100% 100%
Well Head Anchor Block 100% 100%
Above Ground Manifold Piping 100% 100%
Manifold Piping Supports 0% 0%
Manifold Anchor Block Existing
Flow line Trenching 100% 100%
Flow line Wrapping 100% 100%
Flow line stringing 100% 100%
Flow line welding 100% 100%
Flow line Backfill 100% 100%
Flow line Section Tie-In Welding 100% 100%

Page 7 of 11
PROGRESS %
PROGRESS Remarks

Prev To Date %
%

Flow line Cleaning and Hydro Test 100% 100%


Reinstatement of piping 100% 100%
CP Installation & Cad Weld 100% 100%
Instrument Installation 100% 100%
Painting Well Head & Manifold Piping 100% 100%
6.6kV UG power cable pulling 100% 100% Await for Hi-Pot test
Hand excavation and lay cable from Fence to MVJB inside J-GS2 Manifold 0% 0%
Installation of wellhead disconnector switch 100% 100% Await for Ductor/Megger test
J-GS3 - JK Fields
Transformer Shelter: Precast foundation for Transformer shelter 20% 20%
Installation of DB's & JB's in the Pig Receiver area 85% 85% One DB stolen / shortage
FIA have completed installation of field supply cables for Wells J-10, J-14, J-15, J-18 & J-19. Received additional Instrumentation materials from FIA, to enable
J&P install Pressure Switches on Oil Lines J-14, J-15, J-18 & J-19. J&P to complete installation. Query ongoing. Awaiting reply from Tripoli
Installing Instrument Air System 15% 15%
Installation of Disconnector switches, current Transformers, surge arrestors 90% 90%
Switch Yard - Installation of Al bus bars and conductors / jumbers between 33kV devices 70% 80%
Installation of power DB in compressor shelter 100% 100%
Switch Yard - cable trays installation for control cables 65% 70%
Oil Manifold
E & I survey of works starting in this Gathering Station. Modification to E & I on 10 slot Oil Manifold 80% 80%
WSW 21 to J-GS3 6" Flow Line
Well head anchor block 100% 100%
Well head above ground pipe supports 100% 100%
Above Ground well head piping 100% 100%
Above Ground manifold piping 100% 100%
Flow line stringing 100% 100%
Flow line welding 100% 100%
Flow line wrapping 100% 100%
Flow line trenching 100% 100%
Flow line section tie-in welding 100% 100%
Flow line backfill 100% 100%
Flow line Cleaning and Hydro Test 100% 100%
Reinstatement of piping 100% 100%
Instrument Installation 100% 100%
Painting Well Head & Manifold Piping 100% 100%
Electrification of WSW J-21 to J-GS3 (FIA)
Tentatively laying of power cable into trench 100% 100%
Preparation for installation of MV Disconnection switch box 100% 100%

Page 8 of 11
PROGRESS %
PROGRESS Remarks

Prev To Date %
%

Installation of Test Post including pin brazing for Cathodic Protection 100% 100%
Laying of MV cable 100% 100%
Cable connection to DS at well head side 100% 100%
Termination of MV power cable to the WH disconnector switch 100% 100%
Splicing of MV power cable 100% 100%
Fabrication/Erection and Installation of Main 66/33 kV Sub-station at Gathering Station J-GS3 - (J&P)
Installation of cable trays in the switch yard area for control cables 0% 0%
Installation of aluminum bus bars 33kV in the switch yard 0% 0%
K-GS1 - K Field
Installation of precast cable culvert walls 100% 100%
Shuttering & steel fixing for DOL Pad 1 80% 80%
Cast Concrete to 1st DOL Pad 1 80% 80%
Shuttering & steel fixing to DOL Pad 2 80% 80%
Cast Concrete to DOL Pad 2 80% 80%
Base course compaction for 2 remaining DOL Pad foundations 100% 100%
Formworks for blinding concrete for 2 remaining DOL Pads 100% 100%
Electrical Building precast foundation: Cast concrete to foundation Type I (10 Nos), Type (2), Type (3) 100% 100%
Electrical Building precast foundation: Cast concrete to foundation Type 4 0% 50%
Precast septic tank base 100% 100%
Instrument Air Package Foundation: Excavation, backfill with base course and blinding 100% 100%
Instrument Air Package Foundation: Installation of precast foundation and backfilling 60% 60%
Installation of Instrument Air piping 50% 50%
Installation of Utility Water piping 50% 50%
Installation of Drain piping 17% 17%
8" Inter connecting pipe line tie-in going to J-GS3 100% 100%
Installation of Multi Phase flow meter piping 100% 100% MPFM outstanding
Cleaning and hydro-testing of Multi Phase flow meter piping 100% 100%
Reinstatement of multi phase flow meter piping 10% 10%
Painting of multi phase flow meter piping 10% 10%
Installation of L-2001 Pig Launcher Piping 100% 100%
Cleaning and hydro-testing of L-2001 Pig Launcher piping 100% 100%
Reinstatement of L-2001 Pig Launcher piping 60% 60%
Painting of Pig Launcher piping 10% 10%
Fabrication / installation of Roxar Flow Meter shelter 70% 70% Fabrication complete, installation remaining
Installation of earthing system in Shipping Area foundation 100% 100%
Installation of JBs to DOL pads 35% 35%
8'' TRUNKLINE FROM K-GS1 TO J-GS3
L-2001; 8'' Pig Launcher; Formworks, rebar and cast concrete to anchor block 100% 100%

Page 9 of 11
PROGRESS %
PROGRESS Remarks

Prev To Date %
%

Trunk line pig cleaning and hydro-test 100% 100%


Trunk line reinstatement 100% 100%
WI Manifold K-GS1
Blinding concrete to Manifold foundation 100% 100%
Shuttering, steel fixing and cast concrete for WI manifold foundation 100% 100%
Pre-casting of foundation for above ground Pipe Support of WI Manifold 100% 100%
Installation of WI Manifold piping 100% 100%
Cleaning and hydro-testing of WI Manifold piping 100% 100%
Reinstatement of WI Manifold piping 60% 60%
Painting of WI Manifold piping 10% 10%
Installation of precast pipe support Type-I 100% 100%
Excavation, base course compaction and blinding concrete for JB foundations 100% 100%
CCX NC115
6 NEW ACCOMODATION BLOCKS - RAS AKHDER (CIVIL WORKS)

Block 51/52/53/54/55/56: Plastering to internal and external walls 100% 100% Remaining door/window opening
Block 51/52/53/54/55/56: Tyrolean finish to external walls 0% 0%
Block 51/52/53/54/55/56: Waterproofing works to roof slab 80% 80%
Block 51/52/53/54/55/56: Sealing of water proofing membrane overlap joints 0% 25%
Block 54/55/56: Tiling works for floors and walls 100% 100%
Block 54/55/56: Installation of wash basin, W/C and shower tray 100% 100%
Block 51/52: Tiling works for floors and walls 95% 95%
Block 53: Tiling woks for floors and walls 70% 90%
6 NEW ACCOMODATION BLOCKS - RAS AKHDER (ELECTRICAL WORKS)

Block 55: Installation of internal wiring for Lighting, Socket, Telecom and TV 85% 85%
Block 56: Installation of internal wiring for Lighting, Socket, Telecom and TV 85% 85%
Block 51/52/53: Excavation for perimeter grounding cables 100% 100%
Grounding cables pulling 100% 100%
LANDFILL BUILDING - ASAS

Block works for external/internal non-load bearing wall (full height). 100% 100%
External/Internal plastering to approximate 1.5m below roof level 100% 100%
Internal Plastering 100% 100%
Walkway: Backfilling and compaction of base course material for slab 100% 100%
Walkway: Formworks, reinforcement and cast concrete to walkway slab 100% 100% access ramp required in front of sliding steel door
Construct Sewer Manholes 100% 100%
Installation of Conduits and DBs (kitchen, bathroom, office ) 100% 100%
Tiling works for floor and wall 60% 60%
Internal Painting works to block walls 39% 39%
DEPARTURE BUILDING EXTENSION - ASAS

Page 10 of 11
PROGRESS %
PROGRESS Remarks

Prev To Date %
%

Shuttering, steel fixing and cast concrete to pad foundations 100% 100%
Scaffolding and formworks and cast concrete to columns 100% 100%
Backfill and compact internal area of ground beams 100% 100%
Steel fixing and cast concrete to floor slab 100% 100%
Formworks, rebars and cast concrete to roof slab and beams 100% 100%
Formworks, rebar and cast concrete to parapet walls 100% 100%
Concrete curing for roof slab 100% 100%
Removal of roof formwork and props 100% 100%
External walkway: Formworks and rebar 6% 6%
AIR STRIP - Airport Electrical System & Navigational Lights (BOSNA Contractor)

New Electrical Building: Concreting works to foundation base, footing, columns and walls below Ground level & basement slab 100% 100%
New Electrical Building: Concreting works to columns, 1st floor slab & roof slab 100% 100%
Installation of insulation board and cast blinding concrete for roof slab 100% 100%
Transformer Foundation: Cast concrete to Transformer slab 100% 100%
Shuttering, steel fixing and cast concrete to Transformer walls 100% 100%
Screeding to Transformer slab 100% 100%
Shuttering, steel fixing and cast concrete to Electrical Building columns 100% 100%
Excavation for Diesel Generator Foundation 100% 100%
Backfill inside area of Diesel Generator Foundation 50% 50%
Backfill and compact new diesel generator foundation and shelter 100% 100%
Formworks and reinforcing bars to Generator Shelter foundation 100% 100%
Cast concrete to Generator Shelter foundation 100% 100%
Base course compaction and blinding concrete for fuel tank 100% 100%
Formworks and rebar for base of generator fuel tank and cast concrete. 100% 100%
Formworks and Rebars works to ground beams of generator shelter 100% 100%
Cast concrete to ground beams of generator shelter 100% 100%
Removal of existing fence interfering with new Diesel Generator Foundation 100% 100%
Internal plastering works 80% 80%
External plastering works 75% 75%
Water proofing works for roof slab 100% 100%
Fibre optic cable pulling from Admin. Building (CCX) to airport area 6% 6%
INSTALL NEW ACCOMMODATION TRAILERS FOR AOO CCX (J&P) - Service Order

Excavation of cable trenches for electrical cables 0% 100%


Installation of precast foundation 70% 70%
Excavation and blinding concrete for sewer manholes 50% 50%
Power cable fixing from MDB to DB 100% 100%
Installation of branch power cables and earthing net 50% 75%
Installation of DB and JBs and Gland & Termination 75% 75%