INSPECTION RESULT
2. Check switchgear nameplate details and labels. Confirm supplied as per the data
sheet
3. Ensure that the installation meets the requirements of the hazardous area.
7. Inspect switchgear assembly for alignment, level and check foundation fixing details.
9. Inspect to ensure that all the internal parts, bus bar chambers and terminal bases are
clean and free from dirt, dust, moisture, and hygroscopic or metallic materials.
10. Inspect all bus bar bolted connections for tightness., record torque
11. Check to ensure that the recommended clearances have been attained.
14. Check wiring, ferruling and connections against panel wiring/schematic diagrams.
MISFAH- SF – E 08
LARSEN & TOUBRO (OMAN) LLC
INSPECTION RESULT
Between phases
C REMARKS/OBSERVATIONS:
MISFAH- SF – E 08