You are on page 1of 160

Doha Regional Plastic Solutions

MATERIAL SUBMITTAL
FOR

HDPE PIPES & FITTINGS


PROJECT : ROADS AND INFRASTRUCTURE IN UMM SLAL MOHAMMED

CLIENT : ASHGHAL

CONTRACTOR : HBK CONTRACTING CO.

APPLICATION : HDPE PERFORATED PIPE SDR 17

DRPS Head Office


Zone 81, St. No. 03, Bldg. No. 282, New Industrial Area
P.O. Box: 40613, Doha, Qatar
Tel. No: +974 4436 6244 Fax No: +974 4436 6277
E-mail: info@drps.com.qa

Manufacturer of HDPE Pipes, Fittings & Welding Services


www.drps.com.qa
Manufacturer of HDPE Pipes, Fittings & Welding Services

MATERIAL SUBMITTAL
FOR
HDPE PIPES & FITTINGS
Application: TSE -SDR 11
Client: ASHGHAL

DRPS Head Office


Zone 81, St. No. 03, Bldg. No. 282, New Industrial Area P.O. Box: 40613, Doha, Qatar
Tel. No: +974 4436 6244 Fax No: +974 4436 6277E-mail: info@drps.com.qa

Prepared & verified

Sabyasachi Pattanayak
QA / QC Technical Officer

Page:1
Material submittal INDEX
Cover letter (Required to Provide your reference No.)

Table of Contents

Supplier & Manufacturer's company Profile

Supplier and Manufacturer’s

• ISO Certificate
• Company License / Certificate
• Register License / Certificate
• Chamber License / Certificate
• Quality Certificate
• Safety Certificate

Suppliers and Manufacturers Catalogues / Brochure

List of Approved Materials

Method Statement

Material Manufacturer’s Installation procedure

the specific material required)


Material Safety Data Sheet

Contractor and Supplier


Warranty Certificate

Test Certificate / Report

Previous Approval

Material Submittal Forms

Material Compliance Statement (As per QCS 2014)

Page:2
Cover letter (Required to Provide your reference No.)

Page:3
Contractor Scope

Page:4
Table of Contents

Page:5
TABLE OF CONTENTS

1. Supplier & Manufacturer’s company Profile


2 Supplier and Manufacturer’s
ISO Certificate, Company License / Certificate, Register License / Certificate
,Chamber License / Certificate , Quality Certificate , Safety Certificate
3 Suppliers and Manufacturers Catalogues / Brochure
4 List of Approved Materials
5 Method Statement
6 Material Manufacturer’s Installation procedure
7 Material Safety Data Sheet
8 Warranty Certificate
9 Test Certificate / Report
10 Previous Approval
11 Material Submittal Forms
12 Material Compliance Statement (As per QCS 2014)

Page:6
Supplier & Manufacturer's company Profile

Page:7
DRPS
Company Profile

Page:8
Doha Regional Plastic Solutions

Manufacturer of HDPE Pipes, Fittings & Welding Services


Page:9
www.drps.com.qa
Index
Introduction
Vision
Mission
Our Commitment
Compliance Standards - Qatar Construction Standards [QCS]

Products & Services


HDPE Pipes
Injection Molded Fittings
Fabricated Fittings
Butt Fusion Welding Services
HDPE Perforated Pipes
Raw Materials

Technology & Certification


Machinery & Lab Equipment’s
Approvals
Certificates
DRPS Factory Location Map.

Page:10
www.drps.com.qa
1
Introduction
The Doha Regional Plastic Solution (DRPS) is a pipe manufacturing company registered and incorporated in the State of Qatar,
which produces High Density Polyethylene (HDPE) pipes and provides welding services for its customers.

DRPS is the leading Qatari manufacturer of HDPE Pipes & Fittings for water, drainage and other uses by offering total HDPE system
solutions with integrated and diverse product portfolio all MADE in the STATE of QATAR, using advance automated manufacturing
equipment and systems.

DRPS concentrates its efforts and resources on innovation and continuously improving quality, service and competitiveness to
ensure it meets customer’s needs. It is also committed to ensure a safe and challenging workplace in which employees contribute
and develop to their fullest potential.

HDPE Pipe systems are designed and manufactured to meet the tropical weather conditions in the Middle East, making them
suitable for most applications.

DRPS is your only total HDPE solutions provider MADE in QATAR covering pipe, fittings production and installation in the client
site.

Our Vision
Vision of DRPS is to become the best provider of HDPE Solutions and products in GCC and West Asia region.

Our Mission
DRPS is passionate about delivering quality products & services to our customers and addressing their business needs. DRPS holds
high standards in delivering what it promises.

DRPS believes that with best planning & implementation of proper policies, it will enhance the use of all the company’s resources
and will help the company in becoming one of the best companies in Qatar and regions.

Page:11
www.drps.com.qa
2

Our Commitment
In support of its mission, DRPS is committed to:
Producing products as per customer and regulatory requirements.
Achieving customer satisfaction through supplying quality products on a timely basis.
Developing the business through continual improvement of our quality system.
Providing the best products & solutions to our valued customers.
Prompt delivery and quick response to customer’s inquiries.
Offering our customers, a wealth of information, technical supports & customer service
that meet customer requirements and satisfaction.

HDPE Pipes & Fittings Compliance with Qatar Construction


Standards (QCS) 2014 section 8, part 3 – as follows:

EN ISO 527: Plastics - Determination of tensile properties.


EN ISO 1133-1: Plastics - Determination of the melt mass-flow rate (MFR) and melt volume-flow rate (MVR) of thermoplastics.
EN 1519: Plastic piping systems for soil and waste discharge (low and high temperature) within the building
structure – Polyethylene (PE).
EN ISO 1167: Thermoplastic pipes, fittings and assemblies for the conveyance of fluids – Determination of the
resistance to internal pressure.
EN ISO 1183-2: Plastics – Methods for determining the density of non-cellular plastics – Part 2: Density gradient column method
EN ISO 2505: Thermoplastics pipes – Longitudinal reversion – Test method and parameters.
EN ISO 3126: Plastics piping systems – Plastic components – Determination of dimensions.
EN ISO 6259: Thermoplastic pipes - Determination of tensile properties.
EN ISO 9080: Plastic piping and ducting systems – determination of the long term hydrostatic strength of thermoplastics
materials in pipe form by extrapolation.
EN 12099: Plastics piping systems – Polyethylene piping materials and components – Determination of volatile content
EN ISO 12162: Thermoplastic materials for pipes and fittings for pressure applications - Classification and designation
– Overall service (design) coefficient.
EN 12666: Plastic piping systems for non-pressure underground drainage and sewerage – Polyethylene (PE).
EN ISO 13479: Polyolefin pipes for the conveyance of fluids. Determination of resistance to crack propagation.
EN ISO 15512: Plastics – Determination of water content
EN ISO 16871: Plastics piping and ducting systems – Plastics pipes and fittings – Method for exposure to direct (natural) weathering
ISO 18553: Method for the assessment of the degree of pigment or carbon black dispersion in polyolefin pipes, fittings and
compounds.
ISO 4065: Thermoplastic pipes – Universal wall thickness table.

ISO 4427: Plastics piping systems - Polyethylene (PE) pipes and fittings for water supply.
ISO 6964: Polyolefin pipes and fittings – Determination of carbon black content by calcination and pyrolysis
– Test method and basic specification.

Page:12
ISO9001-2015
www.drps.com.qa
3

ISO 9624: Thermoplastic pipes for fluids under pressure – mating dimensions of flange adaptors and loose backing flanges.

ISO 11357-6: Plastics – Differential scanning calorimetry (DSC) – Part 6: Determination of oxidation induction time (OIT).
ISO 11922-1: Thermoplastic pipes for the conveyance of fluids – Dimensions and tolerances - Part: 1: Metric series.
ISO 13761: Plastics pipes and fittings – Pressure reduction factors for polyethylene pipeline systems for use at temperatures
above 20oC.
ISO 13953: PE pipes and fittings – Determination of tensile strength and failure mode of test pieces from a butt-fused joint.
ISO 14236: Plastics pipes and fittings – Mechanical joint compression fittings for use with polyethylene pressure pipes
in water supply systems.

Products & Services:


HDPE Pipes:
Water is of vital importance, plants, animals and humans are composed of 50 – 80 % water, from polluted water or water scarcity
however, they suffer, fall ill or even die. Therefore, our common future is endangered when water is not available in sufficient
amount and quality.

To improve this situation and find solutions, a lot of governmental bodies, engineering and construction companies as well as pipe
manufacturers have focused in this world threatening issue. However, for years’ tremendous difficulties were observed when-
selecting the material of construction for infrastructure systems, which should be suitable to provide anticipated permanent
solutions.

Over the last decades the inherent weaknesses of concrete, clay, ductile, PVC and steel caused tremendous problems in existing
sewer pipe systems, as they tend to be brittle or are too sensitive to aggressive chemicals and soil conditions. Failures had become
a common occurrence worldwide in sewer and other large-diameter pipe applications. In addition, they have an unprofitable
relation between cost & benefit

DRPS derived benefit from the fact that the processing of HDPE is very easy and the plastic materials provide superior properties
against adverse effects of the ambient and the chemicals. In addition to the permanent solution that lasts through generations,
DRPS piping system is able to provide everlasting and economic solutions in wide-ranging fields of applications as for example
drain, storm drain and sewer system as well as sea outfall, manholes and reservoirs dewatering.

In order to meet the requirements of the infrastructure systems, DRPS has developed the most robust and advantageous
large-bore-pipe systems of which all features are described in detail in this brochure.

Page:13
ISO9001-2015
www.drps.com.qa
4

Lower life cycle costs:


Corrosion resistance. Does not rust, rot or corrode.
Leak tight, Heat-fused joints create a homogenous, monolithic system. The fusion joint is stronger than the pipe.
Maintains optimum flow rates. Does not tuberculate, has a high resistance to scale or biological build-up.
Excellent water hammer characteristics. Designed to withstand surge events.
High strain allowance. Virtually eliminates breakage due to freezing pipes.
Additional cost savings are achieved by lower instance of repairs.
With no exfiltration or infiltration, potable water losses and groundwater nuisance treatment costs.

Features & Advantages of HDPE Pipes


There are lots of technical & economic advantages in using HDPE pipes as compared to other conventional pipes.
Light weight
Safe to use
Strong and durable
Resistant to abrasion
Low thermal & electrical conductivity
Low cost of installation and maintenance
Long lasting life of minimum 50 years
Better flow characteristics
Smooth internal and external surface
No corrosion & abrasion, no scale formation. Inert to chemicals & hence can carry acidic & alkaline fluids.
Leak free joints, no repairs needed
Lower Surge Pressure - As compared to other conventional pipes, the HDPE piping system components are subjected to
a much lower surge pressure.
Lowest frictional losses, lower pumping cost
Zero Maintenance
LONG LIFE as against only a few years’ life of conventional pipes such as C.I., PVC, GI, Steel, Cement, etc.,
the calculated life of HDPE pipes is 50 years at normal working temperature and pressure

Page:14
ISO9001-2015
www.drps.com.qa
7

ISO-4427-2 :2007 / Ammendmend-1 / 15-04-2014.


Plastics piping systems — Polyethylene (PE) pipes and fittings for water supply
Dimensions in millimeters
Standard Dimension Ratio (SDR)
SDR 7,4 SDR 9 SDR 11 SDR 17 SDR 21 SDR 26
Nominal Pipe Series
size
S 3,2 S4 S5 S8 S 10 S 12,5
DN/OD
Wall Thickness b
S Mass in kg/m S Mass in kg/m S Mass in kg/m S Mass in kg/m S Mass in kg/m S Mass in kg/m

40 5.5 0.607 4.5 0.514 3.7 0.434 2.4 0.299 - - - -


50 6.9 0.945 5.6 0.796 4.6 0.673 3,0 0.458
63 - - 7,1 1.27 5.8 1.06 3.8 0.728
75 - - 8.4 1.78 6.8 1.48 4.5 1.03
110 - - 12.3 3,82 10 3.18 6.6 2.19 5.3 1.79 4,2 1.45
125 - - 14,0 4.92 11.4 4.12 7.4 2.79 6,0 2.29 4.8 1.86
160 - - 17.9 8.04 14.6 6.74 9.5 4.57 7.7 3.75 6.2 3.08
180 - - 20.1 10.2 16.4 8.51 10.7 5.77 8.6 4.71 6.9 3.83
200 - - 22.4 12.6 18.2 10.5 11.9 7.12 9.6 5.84 7.7 4.74
225 - - 25.2 15.9 20.5 13.3 13.4 9.03 10.8 7.37 8.6 5.96
250 - - 27,9 19.6 22,7 16.3 14,8 11.1 11,9 9.02 9,6 7.38
280 - - 31.3 24.6 25.4 20.5 16.6 13.9 13.4 11.4 10.7 11.9
315 - - 35,2 31.1 28,6 25.9 18,7 17.6 15,0 14.3 12,1 11.7
355 - - 39,7 39.5 32,2 32.9 21,1 22.4 16,9 18.2 13,6 14.8
400 - - 44,7 50.1 36,3 41.7 23,7 28.3 19,1 23.1 15,3 18.8
450 - - 50,3 63.4 40,9 52.8 26,7 35.8 21,5 29.3 17,2 23.7
500 - - 55,8 78.1 45,4 65.2 29,7 44.2 23,9 36.1 19,1 29.2
560 - - - - 50,8 81.7 33,2 55.4 26,7 45.2 21,4 36.6
630 - - - - 57,2 103,0 37,4 70.2 30,0 57,0 24,1 46.4
710 - - - - 42,1 89,0 33,9 72.6 27.2 59,0
800 - - - - 47,4 113 38,1 92,0 30.6 74.7
NOTE 1 bar = 0,1 MPa = 105 Pa; 1 MPa = 1 N/mm2 a PN values are based on C = 1,25.
b Tolerances in accordance with ISO 11922-1:1997, grade V, calculated from (0,1emin + 0,1) mm rounded up to the next 0,1 mm. For certain applications for e > 30
mm, ISO 11922-1:1997, grade T, tolerances may be used calculated from 0,15 emin rounded up to the next 0,1 mm.
"c The calculated value of emin according to ISO 4065 is rounded up to the nearest value of either 2,0, 2,3 or 3,0. This is to satisfy certain national requirements. For
practical reasons, a wall thickness of 3,0 mm is recommended for electrofusion jointing and lining applications."

Page:15
ISO9001-2015
www.drps.com.qa
9
Injection Molded Fittings:

Fabricated Fittings:

PN: 06, SDR: 26


PN: 08, SDR: 21
PN: 10, SDR: 17
PN: 16, SDR: 11
PN: 20, SDR: 09

Page:16
ISO9001-2015
www.drps.com.qa
10
Butt Fusion Welding Service
DRPS provides complete solution for welding of HDPE Pipes & Fittings using Butt-Fusion Welding technology. Butt Fusion is the
most important and widely used method of connection for HDPE Pipes & Fittings. It is a method of jointing pipe ends by way of
heating and cooling under pressure, resulting in pipe joints as strong as the pipe itself.

Butt-fusion jointing is a thermos fusion process which involves the simultaneous heating of the ends of two components which
are to be joined until a melt state is attained on each contact surface. The two surfaces are then brought together under
controlled pressure for a specific cooling time and homogeneous fusion is formed upon cooling. The resultant joint is resistant to
end thrust and has comparable performance under pressure to the pipe.

Page:17
ISO9001-2015
www.drps.com.qa
11
Butt Fusion Welding Machine
Butt welding employing fusion. Clean, leak- proof and permanent joints can be made by following the steps below:

Cleanly cut the pipes as required


Remove fibrous material and chamfer inner edges using a rough file
Heat welding mirror to 210-degree C, bring the cut surfaces to be joined into contact with mirror. The material will melt
Allow weld rims to form

HDPE Perforated Pipes


HDPE Perforated Pipe plays an integral role in many application and is generally used for gravity flow water management
application including storm water drainage, subsurface drainage, detention/retention systems, golf courses, athletic fields,
retaining and foundation walls and agricultural drainage projects.

HDPE pipes are produced with slots or perforations to collect and convey subsurface water to a more favourable location for
discharge and is an ideal material for underground drainage construction. HDPE pipe has enjoyed a long history of success in
roadway applications. HDPE is light weight when compared to other pipe materials, so its more economical to transport and install.
HDPE perforated pipe is very resistant to abrasion and chemical attack which can affect other materials. It is structurally strong
and proven to support large earth loads. HDPE is an environmentally sustainable material.

Raw Material
Polyethylene (PE100) thermoplastics with excellent properties for the application of water supply drainage & sewage surface
water, storm water, ducting. The environmental friendly polyethylene is resistant to many chemicals.

DRPS Produce pipes using thermoplastics materials – High Density Polyethylene [HDPE PE 100].

Page:18
ISO9001-2015
www.drps.com.qa
12
Technology & Certification
KraussMaffei Pipe Extrusion Machine
Lengths in front Single-screw extruders for pipe extrusion.

With two series that have processing units of different lengths, -


Kraussmaffei Berstoff has perfectly equipped itself to meet the market
demands for cost-effective pipe production and high-performance
extrusion.

The successful, long-proven 36D single-screw series combines extreme-


ly levels of product quality with cost-effective production.

The single-screw extruders with the 30L/D processing unit are made for
special extrusion and co extrusion application, in particular, they are
used for processing special materials.

Your benefits
The right machine and system configuration for all pipe extrusion
tasks.
Cost-effective production and an extremely high level of product
quality.
System supplier for customer-specific special solutions.

C6 Control System – flexible system for open- and closed-loop control and monitoring of an extrusion line with its new, innovative
C6 control system. Kraussmaffei Berstoff offers fast, direct access at all times to the individual units of an extrusion line, to the
extruders which work conjointly to produce the product and to integrated downstream equipment.

C6 control system is equipped with the latest multi-touch technology and state-of-the-art hardware components. A high resolution
24” full HD screen provides optimal overview. Synchronized operations of units, functions can easily be operated and activated via
touch screen display. World class extrusion lines, with automated technology for flexibility to deliver the operation products.

Product manufactured in compliance with Qatar Construction Standard (QCS) 2014 Section8 Part 3.

Page:19
ISO9001-2015
www.drps.com.qa
13
Injection Molding Machine
Powerful. Versatile. Durable
Machines in the MX Series

KraussMaffei MX Series is recognized around the world and is principally characterized by the hydro-mechanical dual platen
clamping unit. The performance spectrum ranges from compact Injection Molding units with basic automation through to highly
complex production cells and complete factory planning.

With the MX, we can increase our process quality and our production efficiency. Take advantage of our well-founded expertise,
individually customized solutions and a professional team.

Maximum speed combined with maximum precision


Outstanding melt quality and excellent shot weight consistency
High level of part quality
Customer-specific solutions
Platform for wide technology spectrum
Intelligent, user-friendly control system
Construction and components optimized according to load case
Low maintenance effort, simple retrofitting
Intelligent pairing of premium-quality materials
Clamping concept which works with speed and precision
Space-saving design
Reduced servicing effort
Ideal for high mold weights
Product manufactured in compliance with Qatar Construction Standard (QCS) 2014 Section 8 Part 3.

Page:20
ISO9001-2015
www.drps.com.qa
14

Workshop Butt Fusion Welding Machines – Heating Element


Application and Intended Use
The WIDOS 8000WA SPA is a workshop machine for the heating
element butt welding of pipes and T-90’ T-45’ And Elbow 0-90’
degree out of PE-100 pipes.

For dimensions from OD 250 mm up to 800 mm.

The machine is designed with enhanced quality and superior


technology for best outputs.

Workshop - Band Saw


The WIDOS BAND SAW RS_800
is a special machinery for straight cutting plastic pipes up to
the diameter of 800mm and for cutting angles 45 degree,
and 67.5 degree.

Butt Welding Machines


WIDOS 8000 WIDOS 5100 WIDOS 4600
WIDOS butt welding machine is designed for heating element
butt welding of pipes and fittings with a range of standard
diameters 63mm, 90mm, 110mm, 160mm, 200mm, 250mm,
315mm, 355mm, 400m, 450mm, 500mm, 560mm, 630mm,
710mm, 800mm.
It is a machine for construction sites and particularly designed
for the usage on site.

Page:21
ISO9001-2015
www.drps.com.qa
15

Customer Care & Quality Policy


The Quality Assurance Laboratory of DRPS is equipped with state-of-the-art equipment and staffed with trained quality control
inspectors. A continuous rigorous type test program is carried out including process verification and long terms pressure testing
to ensure our fullest commitment to the highest industry quality standards. We ensure the quality requirements of the client are
met at every stage. This is typically by way of project-specific Inspection and Test Plan.

DRPS is dedicated to continual improvement leading to maintaining high level of Customer satisfaction. We are fully committed to
consistently meet or exceed the customer expectations of the quality of services in all our activities. Providing the most cost
effective and efficient service and constantly looking at ways and means of improving the quality of our products and services.

DRPS reliability is the foundation for its good reputation on the market, which we will strive to continuously improve.

Quality Control Lab


We have a wide range of testing equipment’s from the world class manufacturer – Institute of Pruftecknik GmbH [IPT].

Test Bath for Hydrostatic Pressure Test


The IPT test baths are specially designed for test¬ing thermoplastic pipes
and fittings.

The high reliability, durability of the materials used and the constant
temperatures in the test tank with respect to both volume and time
provide particularly reliable test conditions. The efficient use of energy
with low servicing and maintenance costs guarantee efficient long-term
operation.

There are a wide range of tank dimensions and connection options,


enabling the tanks to be flexibly adapted to various operating.

Hydrostatic Pressure Test standard: QCS 2014, Section 8.3.10.4.


Reference standard: ISO 4427: Part 2, Cl 7.2, Table-3, EN 12201 part 1, Table 2, Table-3.ISO 1167-1&2, Cl 5,7.2,3, 9, 10.
EN 921: Cl 8 Table 1.
Properties: Mechanical characteristics, Hydrostatic Pressure Test for Mechanical strength and leaks, to determine and verify
pipe line integrity
Hydrostatic strength of Raw material grade PE100 MRS 10.0MPa, Service life 50 years at 20’C.

Test Unit for Determination of Density


The right raw material is essential for the desired quality of the end
products. With the IPT test units you can simply and effectively test
the quality of raw materials. For determination of the density of
plastics according to the buoyancy method.

Page:22
ISO9001-2015
www.drps.com.qa
16
Melt Flow Rate Tester
For determination of the melt flow rate (MFR) of thermoplastics with operational
temperatures up to 450 °C.

Melt Mass-Flow rate Test Method: ISO 1133 Condition T.

MFR Test for determine flow properties of material requirements value.

Test Ovens for Pipe Testing


IPT’s test ovens feature a high performance forced air system, which provides an extremely
constant temperature in the entire inner chamber. The high-quality insulation of the
double-wall oven housing and the microprocessor-controlled technology contribute to -
considerable energy savings.

The vertical arrangement of the test samples makes the best use of the space available
whilst also ensuring that the inner chamber remains easy to access. The functional
manifold systems with quick-release couplings and the sliding racks ensure that connecting
the samples is quick and convenient.

For conditioning test samples


Longitudinal Reversion Test:
Test Method: ISO 2505
Test for determine Reversion properties of material.

Marking Gauge
For determination of the change in length as a result of warm storage.

CNC Specimen Milling


For preparation of bar-shaped plastic samples. For tensile tester machine.
For Raw samples preparation by matching to finish Test samples for Tensile Tester.

Test samples shape and size preparation method as per standard ISO: 6295-3.

Page:23
ISO9001-2015
www.drps.com.qa
17
Universal Tensile Tester
The universal tensile tester is used for performing tension, pressure or bending tests.
The classic application is the tensile test. This involves subjecting a sample to an increasing
tensile load until it breaks. The force-deflection diagram generated during this test provides
information on the load-bearing capacity, elasticity and plastic deformation of the material
sample.

Tensile & Elongation Test to determine Physical characteristic of material.

Test Method: EN ISO 6259-1 & 3.

Oxidation Induction Time [OIT]


Test to determine the Thermal Stability of material & products.

For determination of Oxidiation Induction Time [OIT] of thermoplastics with operational


temperature up to 500 ° C.

Oxidiation Induction Time Test Method: ISO 11357-6.

Page:24
ISO9001-2015
www.drps.com.qa
41

Page:25
ISO9001-2015
www.drps.com.qa
42

Page:26
ISO9001-2015
www.drps.com.qa
43

Page:27
ISO9001-2015
Doha Regional Plastic Solutions

DRPS Location Map

DRPS
Trafic
Signal-3

Department of
New Industrial Area, Industrial
Zone 35. Doha Qatar Trafic Signal-2 Estate
Tel: +974 44366244, Fax: +974 44366277
Email: info@drps.com.qa
www.drps.com.qa
Trafic Signal-1

Route Direction:
a. Coming from Doha, take the Salwa Road
b. Drive straight until you reach the Industrial area Bridge,
then cross the Bridge & make a full right turn at Melberak
Interchange.
c. Continue crosed
New Industrial
sing the small Industrial Roundabout. Gate
d. Enter the New Industrial Gate and from 3rd signal left and
then take 3rd right.

To Doha End of
Mesamar Road

d
oa
To Old Industrial

eR
Safari
rvic
Se
Hypermarket

Salwa Road
Bridge

To Doha Industrial Bridge To K S A Border

To Villagio

DOHA REGIONAL PLASTIC SOLUTIONS


Head Office
Zone 81, New Industrial Area
P.O. Box: 40613, Doha- Qatar
Tel : +974 4436 6244
Fax : +974 4436 6277 w w w. d r p s . c o m . q a
Email:info@drps.com.qa
Page:28
Solid customer Satisfaction through our
Quality management system
Doha Regional Plastic Solution (DRPS) is the leading Qatari manufacturer of HDPE Pipes & Fittings for Water, Drainage
and other uses. We are offering total HDPE system solutions with integrated and diverse product portfolio locally made
in the State of Qatar with high quality raw material, using advanced automated manufacturing equipment, systems
and also we are providing a Welding services.

Doha Regional Plastic Solutions


w w w. d r p s . c o m . q a Page:29
Supplier and Manufacturer’s

• ISO Certificate
• Company License / Certificate
• Register License / Certificate
• Chamber License / Certificate
• Quality Certificate
• Safety Certificate

Page:30
DRPS ISO Certificate

Page:31
Page:32
Company License / Certificate

Page:33
Page:34
Register License / Certificate

Page:35
Page:36
Page:37
Page:38
Page:39
Chamber License / Certificate

Page:40
Page:41
Page:42
Quality Certificate

Page:43
Page:44
Safety Certificate

Page:45
Page:46
Suppliers and Manufacturers Catalogues / Brochure

Page:47
Doha Regional Plastic Solutions

Manufacturer of HDPE Pipes, Fittings & Welding Services


Page:48
www.drps.com.qa
www.drps.com.qa
www.drps.com.qa

Drainage Water supply ISO-4427


BLACK PIPE

ITEM CODE SIZE SDR PN


DRPS-P40-S7.4/BL 40MM X 5.5MM 7.4 25
DRPS-P40-S9/BL 40MM X 4.5MM 9 20
DRPS-P40-S11/BL 40MM X 3.7MM 11 16
DRPS-P40-S17/BL 40MM X 2.4MM 17 10
DRPS-P50-S7.4/BL 50MM X 6.9MM 7.4 25
DRPS-P50-S9/BL 50MM X 5.6MM 9 20
DRPS-P50-S11/BL 50MM X 4.6MM 11 16
DRPS-P50-S17/BL 50MM X 3.0MM 17 10
DRPS-P63-S9/BL 63MM X 7.1MM 9 20
DRPS-P63-S11/BL 63MM X 5.8MM 11 16
DRPS-P63-S17/BL 63MM X 3.8MM 17 10
DRPS-P63-S21/BL 63MM X 3.0MM 21 8
DRPS-P75-S7.4/BL 75MM X 10.3MM 7.4 25
DRPS-P75-S9/BL 75MM X 8.4MM 9 20
DRPS-P75-S11/BL 75MM X 6.8MM 11 16
DRPS-P75-S17/BL 75MM X 4.5MM 17 10
DRPS-P75-S21/BL 75MM X 3.6MM 21 8
DRPS-P75-S26/BL 75MM X 2.9MM 26 6
DRPS-P90-S9/BL 90MM X 10.1MM 9 20
DRPS-P90-S11/BL 90MM X 8.2MM 11 16
DRPS-P90-S17/BL 90MM X 5.4MM 17 10
DRPS-P90-S21/BL 90MM X 4.3MM 21 8
DRPS-P110-S9/BL 110MM X 12.3MM 9 20
DRPS-P110-S11/BL 110MM X 10MM 11 16
DRPS-P110-S17/BL 110MM X 6.6MM 17 10
DRPS-P110-S21/BL 110MM X 5.3MM 21 8
DRPS-P110-S26/BL 110MM X 4.2MM 26 6
DRPS-P125-S9/BL 125MM X 14.0MM 9 20
DRPS-P125-S11/BL 125MM X 11.4MM 11 16
DRPS-P125-S17/BL 125MM X 7.4MM 17 10
DRPS-P125-S21/BL 125MM X 6.0MM 21 8
DRPS-P125-S26/BL 125MM X 4.8MM 26 6
DRPS-P160-S9/BL 160MM X 17.9MM 9 20
DRPS-P160-S11/BL 160MM X 14.6MM 11 16
DRPS-P160-S17/BL 160MM X 9.5MM 17 10

ISO9001-2015 Page:49
www.drps.com.qa
www.drps.com.qa

DRPS-P160-S21/BL 160MM X 7.7MM 21 8


DRPS-P160-S26/BL 160MM X 6.2MM 26 6
DRPS-P180-S9/BL 180MM X 20.1MM 9 20
DRPS-P180-S11/BL 180MM X 16.4MM 11 16
DRPS-P180-S17/BL 180MM X 10.7MM 17 10
DRPS-P180-S21/BL 180MM X 8.6MM 21 8
DRPS-P180-S26/BL 180MM X 6.9MM 26 6
DRPS-P200-S9/BL 200MM X 22.4MM 9 20
DRPS-P200-S11/BL 200MM X 18.2MM 11 16
DRPS-P200-S17/BL 200MM X 11.9MM 17 10
DRPS-P200-S21/BL 200MM X 9.6MM 21 8
DRPS-P200-S26/BL 200MM X 7.7MM 26 6
DRPS-P225-S9/BL 225MM X 25.2MM 9 20
DRPS-P225-S11/BL 225MM X 20.5MM 11 16
DRPS-P225-S17/BL 225MM X 13.4MM 17 10
DRPS-P225-S21/BL 225MM X 10.8MM 21 8
DRPS-P225-S26/BL 225MM X 8.6MM 26 6
DRPS-P250-S9/BL 250MM X 27.9MM 9 20
DRPS-P250-S11/BL 250MM X 22.7MM 11 16
DRPS-P250-S17/BL 250MM X 14.8MM 17 10
DRPS-P250-S21/BL 250MM X 11.9MM 21 8
DRPS-P250-S26/BL 250MM X 9.6MM 26 6
DRPS-P280-S9/BL 280MM X 31.3MM 9 20
DRPS-P280-S11/BL 280MM X 25.4MM 11 16
DRPS-P280-S17/BL 280MM X 16.6MM 17 10
DRPS-P280-S21/BL 280MM X 13.4MM 21 8
DRPS-P280-S26/BL 280MM X 10.7MM 26 6
DRPS-P315-S9/BL 315MM X 35.2MM 9 20
DRPS-P315-S11/BL 315MM X 28.6MM 11 16
DRPS-P315-S17/BL 315MM X 18.7MM 17 10
DRPS-P315-S21/BL 315MM X 15MM 21 8
DRPS-P315-S26/BL 315MM X 12.1MM 26 6
DRPS-P355-S9/BL 355MM X 39.7MM 9 20
DRPS-P355-S11/BL 355MM X 32.2MM 11 16
DRPS-P355-S17/BL 355MM X 21.1MM 17 10
DRPS-P355-S21/BL 355MM X 16.9MM 21 8
DRPS-P355-S26/BL 355MM X 13.6MM 26 6
DRPS-P400-S9/BL 400MM X 44.7MM 9 20
DRPS-P400-S11/BL 400MM X 36.3MM 11 16

ISO9001-2015
Page:50
www.drps.com.qa
www.drps.com.qa

DRPS-P400-S17/BL 400MM X 23.7MM 17 10


DRPS-P400-S21/BL 400MM X 19.1MM 21 8
DRPS-P400-S26/BL 400MM X 15.3MM 26 6
DRPS-P450-S9/BL 450MM X 50.3MM 9 20
DRPS-P450-S11/BL 450MM X 40.9MM 11 16
DRPS-P450-S17/BL 450MM X 26.7MM 17 10
DRPS-P450-S21/BL 450MM X 21.5MM 21 8
DRPS-P450-S26/BL 450MM X 17.2MM 26 6
DRPS-P500-S26/BL 500MM X 55.8MM 9 20
DRPS-P500-S9/BL 500MM X 45.4MM 11 16
DRPS-P500-S11/BL 500MM X 29.7MM 17 10
DRPS-P500-S21/BL 500MM X 23.9MM 21 8
DRPS-P500-S26/BL 500MM X 19.1MM 26 6
DRPS-P560-S11/BL 560MM X 50.8MM 11 16
DRPS-P560-S17/BL 560MM X 33.2MM 17 10
DRPS-P560-S21/BL 560MM X 26.7MM 21 8
DRPS-P560-S26/BL 560MM X 21.4MM 26 6
DRPS-P630-S11/BL 630MM X 57.2MM 11 16
DRPS-P630-S17/BL 630MM X 37.4MM 17 10
DRPS-P630-S21/BL 630MM X 30MM 21 8
DRPS-P630-S26/BL 630MM X 24.1MM 26 6
DRPS-P710-S17/BL 710MM X 42.1MM 17 10
DRPS-P710-S21/BL 710MM X 33.9MM 21 8
DRPS-P710-S26/BL 710MM X 30.6MM 26 6
DRPS-P800-S17/BL 800MM X 47.4MM 17 10
DRPS-P800-S21/BL 800MM X 38.1MM 21 8
DRPS-P800-S26/BL 800MM X 30.6MM 26 6

ISO9001-2015
Page:51
www.drps.com.qa

Fabricated Fittings: Dimensions are in millimeter

SEGMENTED ELBOW PE 100 SDR 17, PN 10

Nominal Min. Nominal angle


outside tubular
L Z R Code of the fitting
Diameter length
a (22°)
(Dn) Le, min

250 250 299 323 375 FB-ELB-250-22-17

280 250 305 332 420 FB-ELB-280-22-17

315 300 362 392 472.5 FB-ELB-315-22-17 With a tolerance

355 300 370 404 532.5 FB-ELB-355-22-17 of + 2°

400 300 378 417 600 FB-ELB-400-22-17

450 300 388 432 675 FB-ELB-450-22-17

500 350 448 496 750 FB-ELB-500-22-17

560 350 459 514 840 FB-ELB-560-22-17

630 350 473 534 945 FB-ELB-630-22-17

710 350 488 557 1065 FB-ELB-710-22-17


The minimum
800 350 506 584 1200 FB-ELB-800-22-17
tolerance for pipe

bends shall be

+ 5°

ISO9001-2015
Page:52
www.drps.com.qa

Fabricated Fittings: Dimensions are in millimeter

SEGMENTED ELBOW PE 100 SDR 17, PN 10

Nominal Min. Nominal angle


outside tubular
L Z R Code of the fitting
Diameter length
a (30°)
(Dn) Le, min

250 250 299 323 375 FB-ELB-250-30-17

280 250 305 332 420 FB-ELB-280-30-17

315 300 362 392 472.5 FB-ELB-315-30-17 With a tolerance

355 300 370 404 532.5 FB-ELB-355-30-17 of + 2°

400 300 378 417 600 FB-ELB-400-30-17

450 300 388 432 675 FB-ELB-450-30-17

500 350 448 496 750 FB-ELB-500-30-17

560 350 459 514 840 FB-ELB-560-30-17

630 350 473 534 945 FB-ELB-630-30-17

710 350 488 557 1065 FB-ELB-710-30-17


The minimum
800 350 506 584 1200 FB-ELB-800-30-17
tolerance for pipe

bends shall be

+ 5°

ISO9001-2015
Page:53
www.drps.com.qa

Fabricated Fittings: Dimensions are in millimeter

SEGMENTED ELBOW PE 100 SDR 17, PN 10

Nominal Min. Nominal angle


outside tubular
L Z R Code of the fitting
Diameter length
a (45°)
(Dn) Le, min

250 250 299 406 375 FB-ELB-250-45-17

280 250 305 424 420 FB-ELB-280-45-17

315 300 362 496 472.5 FB-ELB-315-45-17 With a tolerance

355 300 370 521 532.5 FB-ELB-355-45-17 of + 2°

400 300 373 549 600 FB-ELB-400-45-17

450 300 388 580 675 FB-ELB-450-45-17

500 350 448 661 750 FB-ELB-500-45-17

560 350 459 698 840 FB-ELB-560-45-17

630 350 473 742 945 FB-ELB-630-45-17

710 350 489 792 1065 FB-ELB-710-45-17


The minimum
800 350 506 848 1200 FB-ELB-800-45-17
tolerance for pipe

bends shall be

+ 5°

ISO9001-2015 Page:54
www.drps.com.qa

Fabricated Fittings: Dimensions are in millimeter

SEGMENTED ELBOW PE 100 SDR 17, PN 10

Nominal Min. Nominal angle


outside tubular
L Z R Code of the fitting
Diameter length
a (60°)
(Dn) Le, min

250 250 299 467 375 FB-ELB-250-60-17

280 250 305 493 420 FB-ELB-280-60-17

315 300 362 573 472.5 FB-ELB-315-60-17 With a tolerance

355 300 370 608 532.5 FB-ELB-355-60-17 of + 2°

400 300 378 647 600 FB-ELB-400-60-17

450 300 388 690 675 FB-ELB-450-60-17

500 350 448 784 750 FB-ELB-500-60-17

560 350 459 835 840 FB-ELB-560-60-17

630 350 484 896 945 FB-ELB-630-60-17

710 350 489 965 1065 FB-ELB-710-60-17


The minimum
800 350 506 1043 1200 FB-ELB-800-60-17
tolerance for pipe

bends shall be

+ 5°

Page:55
ISO9001-2015
www.drps.com.qa

Fabricated Fittings: Dimensions are in millimeter

SEGMENTED ELBOW PE 100 SDR 17, PN 10

Nominal Min. Nominal angle


outside tubular
L Z R Code of the fitting
Diameter length
a (90°)
(Dn) Le, min

250 250 278 625 375 FB-ELB-250-90-17

280 250 282 670 420 FB-ELB-280-90-17

315 300 336 773 472.5 FB-ELB-315-90-17 With a tolerance

355 300 340 793 532.5 FB-ELB-355-90-17 of + 2°

400 300 390 811 600 FB-ELB-400-90-17

450 300 351 925 675 FB-ELB-450-90-17

500 350 406 1045 750 FB-ELB-500-90-17

560 350 413 1066 840 FB-ELB-560-90-17

630 350 421 1085 945 FB-ELB-630-90-17

710 350 430 1178 1065 FB-ELB-710-90-17


The minimum
800 350 440 1283 1200 FB-ELB-800-90-17
tolerance for pipe

bends shall be

+ 5°

Page:56
ISO9001-2015
www.drps.com.qa

Fabricated Fittings: All Dimensions are in millimeter

SEGMENTED TEE PE 100 SDR 17, PN 10

Nominal Min. Nominal angle


outside tubular
L Z1 Z2 Z3 Code of the fitting
Diameter length
90°
(dn) le, min

250 250 750 375 375 250 FB-TEE-250-90-17

280 250 840 420 420 280 FB-TEE-280-90-17

315 300 945 472.5 472.5 315 FB-TEE-315-90-17 With a tolerance

355 300 1065 532.5 532.5 355 FB-TEE-355-90-17 of + 2°

400 300 1200 600 600 400 FB-TEE-400-90-17

450 300 1350 675 675 450 FB-TEE-450-90-17

500 350 1500 750 750 500 FB-TEE-500-90-17

560 350 1680 840 840 560 FB-TEE-560-90-17

630 350 1890 945 945 630 FB-TEE-630-90-17

710 350 2130 1065 1065 710 FB-TEE-710-90-17


The minimum
800 350 2400 1200 1200 800 FB-TEE-800-90-17 tolerance for
pipe

bends shall be

+ 5°

Page:57
ISO9001-2015
List of Approved Materials

Page:58
Page:59
Page:60
Page:61
Method Statement

Page:62
INSTALLATION METHOD OF BUTT FUSION WELDING OF HDPE
PIPES & FITTINGS

WORK METHODOLOGY

1. Handling and Storage of PE pipes

Delivery

Although HDPE is an extremely tough material, the surface of the material may easily be scored
or gouged by careless handling. Particular attention shall be paid to stacking on vehicles and
excessive loads being imposed on pipes and fittings.Only non mettalic ropes or wide bank
webbing will be used to secure loads.

Handling and Storage of Polyethylene (PE) Pipes

PE pipes should be protected from direct sunlight if they are to be stored / stacked at site. This will
reduce exposure to UV light which over time can cause aging of the pipe surface. Any pipes
stored/stacked at site shall be covered by tarpaulin.
All pipes stacks will be made on sufficiently firm flat ground. Where individual pipe lengths are
stacked in pyramid fashion, such stacks shall not be greater than 1m high.
Under no circumstances will metal chains or slings be brought into direct contact with the material.
When lifting bundled pipes by crane, non-metallic wide band slings or ropes will be used, and for
pipe lengths greater than 6m,load spreading beams will be used.

2. Piping Installation

Prior to installation, the trench preparation shall be checked for the required elevation, slope and
freedom from rock, stones and other deleterious materials. Sand bedding to the required
thickness shall be checked and confirmed. Installation shall not be started until unsatisfactory
conditions have been corrected.
The polyethylene pipes, fittings, etc. shall be inspected for the sizes required as per drawing and
also for distortion, bending, damages, etc.

Page:63
Note: Electrofusion and butt fusion fittings should remain in original packaging until final
installation.

Each section of pipe and each fitting shall be thoroughly cleaned before it is installed.
The pipes shall be laid in the trench straight and with spacing required as per
specification/drawing.
Whenever pipe laying is discontinued for short periods, or when work is stopped at the end of the
day, the open ends of all mains shall be closed with water-tight plugs.
When lifting pipe with slings, only wide fabric choker slings capable of safely carrying the load to lift,
move, or lower pipe and fittings shall be used. Wire rope and chain shall not be used.

Page:64
HEAT FUSION
The principle of heat fusion is to heat two surfaces to a designated temperature, and then fuse
them together by application of a sufficient force. This force causes the melted materials to flow
and mix, thereby resulting in fusion. When fused according to the pipe and/or fitting
manufacturers' procedures, the joint area becomes as strong as or stronger than the pipe itself
in both tensile and pressure properties. As soon as the joint cools to near ambient temperature,
it is ready for handling. The following sections of this chapter provide a general procedural
guideline for each of these heat fusion methods.
One method, used for all three types of joints, uses special heating tools for heating the parts to
be joined. The other method, 'electro fusion', is used only for socket joints. Heat is generated by
inducing electric current into a wire coil that is a part of the fitting.

BUTT FUSION
The most widely used method for joining
individual lengths of large diameter
polyethylene pipe is by heat fusion of the
pipe butt ends as illustrated in Figure 1. This
technique, which precludes the need for
specially modified pipe ends or couplings,
produces a permanent, economical and
flow-efficient connection. Field-site butt
fusions may be made readily by trained
operators using specially developed butt
fusion machines (see Figure 2) that secure
and precisely align the pipe ends for the
fusion process.

Page:65
BUTT FUSION WELDING

Butt Fusion is the most common technique for producing fusion welds in HDPE piping.

Pre-Joint Checks

1. Correct jointing parameters for the machine & piping being welded shall be checked.
2. The generator shall be checked for sufficient fuel to complete the operation. Ensure that
the generator is positioned away from the welding area to avoid fumes.
3. The welding equipment shall be checked for :
· The clamps must be effective in holding pipe square.
· The trimmer blades must be clean and sharp and the trimmer must be well with
power in reverse to ensure a clean cut.
· The heater plate must have a control system capable of maintaining a uniform
temperature over the area in contact with the pipe.
· The hydraulic system must be effective and a gauge must be attached which can
accurately resolve pressure to be used.
4. Pipe shall be supported on pipe rollers or PE skids.
5. Equipment shall be cleaned to ensure that oil and grease do not contact pipe surfaces.
6. To control dust contamination, weldingshall be carried out in simple protective shelter.
The floor should be covered by tarpaulin (or similar material). Welding works shall not be
carried out on windy days.
7. To ensure that heater plate is fully clean it shall be washed when cold with a mild
detergent and then rinsed with cold water.

Page:66
The procedure for Butt Welding as follows.

The six steps involved in making a butt fusion joint are:

1. Securely fasten the components to be joined


2. Face the pipe ends
3. Align the pipe profile
4. Melt the pipe interfaces
5. Join the two profiles together
6. Hold under pressure

Secure
Each component that is to be fused will be held in position so that it will not move unless it will
be moved by the hydraulic clamping device.

Face
The pipe ends will be faced to establish clean, parallel mating surfaces. Facing is continued
until a minimal distance exists between the fixed and movable jaws of the machine and the
facer is locked firmly and squarely between the jaws. This operation provides for a perfectly
square face, perpendicular to the pipe centerline on each pipe end and with no detectable
gap.

Align
The pipe profiles will be rounded and aligned with each other to minimize mismatch (high-
low) of the pipe walls. This will be accomplished by adjusting the clamping jaws until the
outside diameters of the pipe ends match. The jaws will not be loosened or the pipe may slip
during fusion.

Melt
Heat the ends of the pipe to the pipe manufacturer's recommended temperature, interface
pressure, and time duration. By doing so, the heat will penetrate into the pipe ends and a
molten “bead” of material will form at the pipe ends. Heating tools, which simultaneously heat
both pipe ends, will be used to accomplish this operation.
Heating tools are equipped with suspension and alignment guides, which center them on the
pipe ends. The heater faces which come into contact with the pipe is coated by the
manufacturer to prevent molten plastic from sticking to the heater faces.

Page:67
Join
After the pipe ends have been heated for the proper time and to the proper temperature, the
heater tool will be removed and the molten pipe ends will be brought together with sufficient
pressure to properly mix the pipe materials and form a homogeneous joint.
The pipe manufacturer's instructions will be followed for interface pressure and bead size of
molten material as a guide for a proper joint.
Fusion machines will incorporate any of the following for proper application of pressure:
1. Manual with hydraulic hand pump.
2. Semi-automatic with motorized hydraulics including pressure reducing, selector, and
directional control valves.
3. Fully automatic with computer- or microprocessor-control of the heat and fusion cycles and
pressures.

Hold
The molten joint will be held immobile under pressure until cooled adequately to develop
strength. The proper cooling times for the joint are material-, pipe-diameter-, and wall-thickness
dependent and will be followed as established by the pipe manufacturer. Allowing proper times
under pressure for cooling prior to removal from the clamps of the machine is important in
achieving joint integrity.

INSTALLATION METHOD OF ELECTRO FUSION WELDING OF


HDPE PIPES & FITTINGS
This technique of heat fusion joining is somewhat different from the conventional fusion joining
thus far described. The main difference between conventional heat fusion and electro fusion is
the method by which the heat is applied. In conventional heat fusion joining, a heating tool is
used to heat the pipe and fitting surfaces. The electro fusion joint is heated internally, either by a
wire coil at the interface of the joint or, as in one design, by a conductive polymer. Heat is created
as an electric current is applied to the conductive material in the fitting. Figure 3 illustrates a
typical electro fusion joint and Figure 4 illustrates an electro fusion control box and fitting.

Page:68
CLEANLINESS

Under no circumstances will electro fusion be carried out in conditions that are unsuitable for
successful jointing. Trench side and trench conditions must be clean and dry and kept clear of
ground water and mud. When necessary an enclosed habitat will be utilized to alleviate
conditions of blowing sand.

ELECTRO FUSION WELDING

General steps to be followed when performing electro fusion joining are:


1. Prepare the pipe
2. Clamp the fitting and pipe(s)
3. Apply the electric current
4. Cool and remove the clamps

Page:69
ELECTROFUSION WELDING PROCEDURE

1. The insertion depths on the surface area covered by the electro fusion fitting will be
marked with an indelible marker.

2. The external oxide layer will be removed from the pipe by scraping using either a hand
scrapper or mechanical scrapper tool.

3. All swarf will be removed from the pipe and the inside and outside edge scraped.

4. The pipe surface and the inside of the pipe will be cleaned using a lint cloth impregnated
with a suitable cleaning solvent such as xylene.

5. The ends of the pipe or spigot end will be inserted up to the stop on the straight couplers
or to the marked inspection depths on the pipe.

6. Alignment clamps will be installed to clamp the fittings/pipe secure for the fusion cycle.

7. These clamps will remain in position until the entire fusion cycle including cooling has
elapsed.

8. The electro fusion leads will be connected, the bar code read using the scanner or 'pen'
supplied with the fusion box and the fusion cycle undertaken.

9. The fusion parameters will be recorded on the pipe together with the joint identification,
time and date using an indelible marker.

Page:70
INSTALLATION METHOD OF ELECTRO FUSION WELDING OF HOT
AIR WELDING

This is a plastic welding technique which is analogus to gas welding of metals, though the specific
techniques are different. A specially designed heat gun (hot air welder) produces a jet of hot air
that softens the parts to be joined, as well as the plastic filler rod.

Hot air/gas welding is a common fabrication technique for manufacturing smaller items including
and not limited to chemical tanks, water tanks (black, grey, fresh & ballast), heat exchangers, and
plumbing fittings. The materials being welded and the welding rod must be of the same or very
similar plastic. Welding PVC to acrylic is an exception to this rule.
The filler rod used for welding is the extruded rod that is used to weld plastic. Plastic welding rod
can be ABS, PVC, Polypropylene, polyethylene, and many other types of thermoplastic. Plastic
welding rod is available in a wide range of Colors to match your project requirements.

Page:71
HYDROSTATIC TESTING

Pressure Testing Outside the Trench:

If specified by the engineer, pressure testing may be conducted prior to pipe installation.
After the pipe has been joined, fill it with water, carefully bleed off any traped air. Subject the
pipe to a hydrostatic test pressure that is 1.5 times the system design pressure for a maximum
of 3 hours. During this time, add water periodically to maintain the test pressure; this
compensates for the initial stretching of the pipe. The line pressure tightness is determined by
visual observation. Therefore it is not necessary to measure the make-up of water. Examine
every fused joint, any leakage must be repaired and then retested.

Testing In The Trench:

Fill the pipeline with water after it has been laid; bleed off any trapped air. Subject the lowest
element in the system to a test pressure that is 1.5 times the design pressure and check for
any leakage. When in the opinion of the engineer, local conditions require that the trenches be
backfilled immediately after the pipe has been laid, apply the pressure test after backfilling
has been completed but not sooner than a time which will allow sufficient curing of any
concrete that may have been used. Typical minimum concrete curing times are 36hours for
early strengths and 7 days for normal strengths.
The test procedures consist of two steps: the initial expansion and the test phase. When test
pressure is applied to a water filled pipe, the pipe expands. During the initial expansion of the
pipe under test, sufficient make-up water be added to the system at hourly intervals for 3
hours to maintain the test pressure. After about 4 hours, initial expansion should be complete
and the actusl test can start.
When the test is to begin, the pipe is full of water and is subjected to a constant test pressure of
1.5 times the systemdesign pressure. The test phase should not exceed 3 hours, after which
time any water deficiency must be replaced and measyred. Add and measure the amount of
make-up water required to return to the test pressure and compare this to the maximum
allowance.

Page:72
Typical Excavation Sections In All Types of Soil

1. Excavation Depth Between 0 - 1.20 m 0 *1.2 m

^- -^
f Varies

0 - 1.3 m 1

2. Excavation Depth Between 1.20 - 2.5 m Vl


1.2 m

fsS-Vartes- .
^

> 1.3 m 1

3. Excavation Depth > 2.5 m %


12 m

{ -Vanes-

^ ^f

Page:73
Page:74
Risk / Impact Assessment and SHE Method Statements

Objectives:-
· To identify hazards and assess, eliminate or minimize and control Risks and
Environmental Impacts, both with regards to project site activities, office and work
premises, including routine and non routine activities.
· To document 'Safe Systems of Work' and prevent adverse environmental impacts
through the generation of SHE Method Statements.
· To ensure that information with regard to hazards and environmental aspects and
associated risks / impacts are communicated to employees and other affected
parties.
· Ensure that the requirements of local health and safety and environmental
regulations are met by adopting international best practice in the management of
health and safety risk and the environment.

Definitions:-
· Hazard – Source or situation with a potential for harm in terms of injury or health,
damage to property, damage to the workplace environment, or a combination of
these.
· Risk – Combination of the likelihood and consequence(s) of a specified hazardous
event occurring.
· Risk Assessment – Overall process of estimating the magnitude of risk and
deciding whether or not the risk is tolerable.
· Tolerable Risk – Risk that has been reduced to a level that can be endured by the
organization having regard to its legal obligations and its own health and safety
policy.
· Environmental Aspect – Activities, products or services that can interact with the
environment.
· Environmental Impact – Changes to the environment, whether adverse or
beneficial, wholly or partially, resulting from organizations environmental aspects.
· Method Statement – A detail step by step description of an installation or work
activity.
· SHE(Q) –Safety, Health and Environment (Quality)

Page:75
Risk & Impact Assessment - Guidance
Risk Assessment Matrix

Page:76
Risk and Impact Assessment – Guidance Notes:-
· Assess the risks by evaluating each hazard in turn.
· To assess the risk, the likelihood of the hazard or hazardous event occurring must
be determined.
· Guidance on risk and likelihood is provided with the risk assessment matrix above.
· A score of 1 to 3 must be selected from the risk assessment matrix, with 1
Meaning that the event is unlikely to occur and 3 meaning that the event is
Highly likely to occur.
· Following this, the consequence of the event occurring must be determined.
· This is the severity of the injury or damage that will be caused if the event takes
place.
· A low consequence of 1 on the risk assessment matrix means that no injury would
be sustained if the event happened. A high consequence of 3 for example, means
that a fatality is likely if the event occurs.
· The next step requires the selected likelihood to be multiplied by the selected
consequence to arrive at a Risk Rating. For example a likelihood of 2 multiplied by
a consequence of 3 will produce a Risk Rating of 6 (2 x 3 = 6). aRisk rating of 6 or
more is regarded as a high risk priority.
· In such cases effective risk control measures must be developed to control the risk.
Lower priority risk will not be ignored, however, control measures should be
appropriate to the Risk Rating and based on the principal of 'Reasonably
Practicable', a balance of risk and cost.
· Once control measures are applied the risk rating is again calculated. This
'Residual Risk' rating should show a reduction in the level of risk due to the control
measures. Ideally the residual risk will be low. Note that a task should not proceed
unless the residual risk has been reduced to 3.
· Note that the consequence will never change. What can be changed is the
Likelihood. This must be managed and must be 1, giving a maximum residual risk
of 3.
· The process is be used to also include environmental aspects. The matrix can be
used to manage environmental impacts and this is provided for on the assessment
sheet.
Action Plan: where a score rating is 6 or above further actions / preventative measures will be
required to ensure that the hazard and risks are irradiated or bought down to as low as
reasonably practicable. Responsibilities and actions noted must be completed prior, to works
/ activity commencing.

Page:77
SHE Method statements will be developed, but are not limited to, the following activities:

? Work in excavations over 1.2m deep.


? Working in confined spaces.
? Working at height (rope access works, scaffold towers in excess of 5m or roof works).
? Working at height using a MEWP (Boom lift / Scissor lift).
? Working with Mast Climbers / Cradles.
? Mechanical cable pulling.
? Working in lift-shafts.
? Working in risers (Assess risk of falling persons).
? Radiographic testing.
? Working with Electricity (ESSW).
? Use of Mobile Crane (for any operation)
? All lifting operations over 1 tonne.

Page:78
Working Safely in Excavations

Definition: - Excavations and trenches greater than 1.2m deep can cause serious
accidents form the collapse of their sides, resulting in the burial or crushing of workers
inside the excavation.

Key excavation terms include:-


· Shoring gives temporary support to the wall of a trench by placing sheeting along its
walls, with sufficient props both vertically and horizontally to support the length of the
excavation exposed.
· Battering-back requires the sides of the trench to be sloped back to a 35 – 45
degree angle to make the sides stable and to prevent collapse.
· Trench Boxes are proprietary support systems, which can be put in place without
requiring people to enter the excavation. Once in place, these allow safe access and
work from inside the trench box.
· Chocks/Stop Blocks are blocks/ structures that prevent a vehicle from approaching
too close to the side of an excavation, which could cause the sides of the excavation
to collapse or the vehicle to roll into the excavation.

Hazards Risks:-
· Unprotected edges Fractures / Crush injuries/
· Collapse of sides entrapment / death
· Machinery/materials falling over edges Electrocution/
· Contact with underground services Gas Inhalation, leading to consciousness /
death
Controls – Managing the risks:-
· Before any work commences in an excavation the excavation checklist will be a
prerequisite (it must be completed before work starts).
· Before any work takes place ensure that the site is inspected and surveyed to
ascertain the condition of structures, ground and services including overhead/
underground lines and gas pipes and tat digging operations will not cause other
structures to become unstable or collapse.
· Ensure that all excavations are inspected / controlled by a competent person i.e a
civil engineer, foreman, supervisor etc. Excavation must be inspected daily before
work commences. Please note – Excavation s must also be inspected after
inclement weather conditions e.g. High wind, Rain etc.

Page:79
· Provide at least one safe access / egress point to the excavation. 2 access / egress
points are better than 1. A 2nd access / egress point will act as an emergency exit.
· Ensure that trench controls are in place, shoring, battering back, trench boxes,
chock / stop blocks etc.
· Ensure that full PPE is worn in the excavation at all times.
· Suitable barriers must be in place around the excavation at all times. These barriers
act as edge protection & an exclusion zone, ensure that these barriers are placed 1
meter back from the edge of the excavation. Warning signage must also be posted
around the excavation to forewarn of the danger.
· Inspect the ground area around the excavation the ensure it is capable of taking the
weight of plant and equipment.
· Do not operate & any machinery too closes to the edge of excavations. Additional
weight of heavy machinery could cause the trench to collapse.
· Put in stop / chock blocks to prevent machinery driving too close to the edge of the
excavation.
· Store all material removed from the excavation at least the same distance away from
the edges as the depth of the excavation to prevent debris falling back in.
· Ensure that there is god communications / co-0rdinationbetween the machine drivers
and other workers during all operations in and around the excavation.
· Where combustion engines are used in an excavation, ensure that the exhaust pipes
extend clear of the excavation and that the work area is sufficiently ventilated.

A competent person must inspect excavations –


· At the start of each shift, before work begins.
· After any event likely to have affected the strength or stability of the excavation.
· After any accidental fall of rock, earth or other material

Page:80
Excavation Worksafe Checklist
Location:

Permit Number: Date:


Where items are not found to be in good condition or are not ticked “YES” then the excavation MUST NOT be operated in, and defects / comments
bought to the attention of the main contractor for corrective action.
Relevant box must be marked with a (tick). No blanks are not acceptable.

Item Description YES NO Comment


People
Do all operatives understand the Safety Standards n
place for these works?
Has the Supervisor given the necessary approved
Method statement, risk assessment and tool box talks
and obtained signatures?
Permits
Have Main Contractor Permits to Work been
completed.
Is the permit approved by the Main Contractor Permit
Officer ?
Equipment
Do operatives have adequate PPE?
Is there adequate lighting & ventilation?
Is there adequate access / egress?
Are adequate barriers & signage in place around the
excavation?
Has a competent person inspected the stability of the
excavation?
Is all machinery & equipment & spoil an adequate
distance away form the edges of the excavation?
Is there trench control in place –Shoring, Stepping etc?
Is there chock/stop blocks around the barriers to stop
machinery from operating too close to the excavation?
Has the atmosphere in the excavation been checked
for air deficiency, combustibles other contaminants?
Weather conditions:
Windy Sunny Rain Overcast Dark Fog Other: (Specify):
(*Circle as appropriate)
The below mentioned responsible persons confirm that the above checks have been carried out and that the
excavation identified above is considered to be in a safe and usable condition.
Operator 1 (Print Name) Operator (Signature) Date: / /

Operator 2 (Print Name) Operator (Signature) Date: / /

Operator 3 (Print Name) Operator (Signature) Date: / /

Supervisor (Print Name) Supervisor (Signature) Date: / /

Copy to: Safety Officer. Permit File.

Page:81
Material Manufacturer’s Installation procedure

the specific material required)

Page:82
Doha Regional Plastic Solutions

Manufacturer of HDPE Pipes, Fittings & Welding Services


Page:83
www.drps.com.qa
Buttfusion & Electrofusion
Welding Method

Doha Regional Plastic Solutions

Page:84
Butt Welding Preparation

BUTT WELDING
Quality of butt welding directly depends on operator's ability, quality of equipment, and to
supervisor who is responsible from related standards. The process should be observed carefully
from the beginning till the end.
Before starting butt welding process it is important to check and verify all parameters. Every
operator should be educated and certificated.

The issues should be considered before starting butt welding process

• The welding environment should be over +5 °C, and it should be done in a sheltered area at
rainy and cold weathers.
• Pipe ends should be closed to prevent air circulation and fast cooling.
• Before starting welding process for coil pipes, bending must be taken away from the pipes.
• Welding zone should be clean and free of damage.

Butt welding method

The principle of butt welding system is heating the welding surfaces for a certain time and
pressure, for the pipes at same diameter and outer diameter. The joining area of the welding
components should be cleaned smoothly and heated up to 200-220 °C. Then they bond together
under certain pressure. Welding pressure, heat and time should be properly chosen in order not
to change the chemical and mechanical properties of the welded parts.

In butt welding method, butt areas is pressed on the heater plate, left at zero pressure until
they arrive at welding temperature and joined together under pressure (welding).

At good welding applications, welded zone provides at least the same strength with the
original pipe. To have a quality welding application; butt welding pressure, temperature and time
parameters should be set carefully.

Figure 1: Pipes for butt welding

Page:85
Butt Welding Preparation

Temperature on the butt welding machine should be controlled just before starting butt welding
process. This must be done by an infrared thermometer. The heater plate should be left for a
minimum of 10 minutes after reaching the set temperature. To ensure an optimum welding
quality, the heater plate has to be cleaned before every welding operation. Cleaning should be
done by a soft cleaning material and using alcohol etc. The heater plate (Teflon coating) must be
free of damages.

The joining forces and joining pressures have to conform the machine working instructions.
These can be based on manufacturer information, calculated or measured values. Moving
pressure is taken from the indicators of the welding machine during the slow movement of the
part to be welded. This value has to be added to the determined joining pressure. Moving
pressure may change depending on machine, diameter of pipe, and length of pipe. Therefore,
before every welding process moving pressure should be read and added to joining pressure.

The joining areas have to be planed before the butt welding. (Figure 2) So with this way pipes
can be exact aligned and have clean surface.

The gap width and the misalignment have to be controlled. Misalignment must be avoided as
much as possible. Even in the worst circumstance, it may not exceed 1/10 of wall thickness.
The trimmed welding zones should not be touched and allow for further contamination.
Otherwise trimming should be repeated. The ribbon of shavings and any other cut pieces must be
cleared from the welding zone without touching the trimmed faces.

Figure 2: Trimming pipe surface

Page:86
Butt Welding Process

In butt welding process, the welding zones are heated-up to the welding temperature by the
heater plate and the pipes are joined under pressure after removing the heater plate. The heating
temperature should be 200 to 220 °C. Higher temperatures are required for thinner wall
thicknesses, and the lower temperatures for thicker wall thicknesses (Graph 1).

Graph 1 : Required temperatures for different wall thickness

Page:87
Alignment

The joining areas are aligned to the heater plate until all areas
are plane-parallel on it. This fact is visible on the kind of beads. The exact alignment should be
checked by type of the pipe circumference. If the alignment was faulty, optimum bead height will
not be obtained. The alignment is done in duration T1 time and with certain pressure (P1). T1
time is depending on the bead height. Required bead heights are shown in table 1, column 2.
Placement of heater and bead creation can be seen on diagram 3 and 4. P1 interfacial plane
pressure is 0,15 N/mm², but this value is not the one that read from welding machine's
manometer. The welder should determine or calculate the manometer pressure according to the
instructions given by the manufacturer of the welding machine to get the required interfacial
pressure.

Figure 3: Placement of heater

Figure 4: Pressurized heating (alig

Figure 4: Pressurized heating (alignment) and shape of welding faces afterwards

Page:88
Heating-up without pressure

For heating-up, the joining areas must contact the heater plate, and pressure must decrease.
Pressure between joining areas and heater plate is nearly zero (P2 ? 0.02 N/mm²). At this time the
heat penetrates during pipe axis. Heating up times (T2) are mentioned in table 1, column 3. If this
time is applied less than requirement, the deepness of plastic part will be shorter than needed;
contrary welding area will melt and corrode.

Removal of heater plate

After heating-up, the joining areas are to be detached from the heating plate. The heating plate
should be carefully removed and the heated joining faces should be free of damage and
contamination. The joining areas should be joined together quickly after heating tool removal. If
operator delays at joining the welding joint quality will be insufficient because of oxidation and
cooling. Maximum time for this process is given at Table 1, column 4.

Joining

After heater plate is removed, areas aligned closer. There must be no strike or hit during this
process. The demanded pressure (interfaced pressure) time is obtained possibly linear (Graph 2).
The required time (T4) is shown in table 1, column 5. The joining pressure (P3), is 0,15±0,01
N/mm 2.

Figure 5: Pipe alignment and joining, beads appear under pressure

Cooling

The joining pressure (P3-interfaced pressure) has to be kept during the cooling time. After
process, a regular double bead must appear. The bead size shows the regularity of welding.
Different beads could be caused by different MFR (melt flow rate) of the pipes. K must always be
larger than 0 (see figure 6). Minimum time (T5) for this phase is given at Table 1, column 5.

Figure 6: Cross section of beads

Page:89
Table 1: Suggested butt welding parameters for PE100 pipe and fittings

Step by step Butt Welding Processing


1. Prepare of working site (e.g. cover welding site)
2. Connect the welding equipment to the electrical net or generator and test the function
3. Adjust the pipes with easy axial movement
4. Scrape welding faces of pipe and/or fittings
5. Take off the scraper at the welding machine
6. Remove shaved parts from the welding area (use brush, paper towel)
7. Close the pipe's open ends to prevent air circulation
8. Check the alignment of surfaces by bringing together (misalignment must be maximum 0,1 x
wall thickness).
9. Check the heater plate surface temperature (figure 1)
10. Clean the heater plate with smooth and non-fuzzy rag or paper towel
11. Read the moving pressure from the welding machine
12. Determine the value for aligning, heating-up and joining pressures due to producers
Instructions
13. Apply the values to the machine according table 1
14. Set the heating tool to the welding position
15. Align the welding areas to the heating tool quickly and wait until minimum bead height
occurs (according table 2,column 2)
16. Decrease pressure to P2. This pressure is nearly zero? 0.02 N/mm². Wait during the time
shown at table 1 column 3, at P2 pressure.
17. Remove the connection areas to be welded from the heater plate without damage and
remove it from the welding position.
18. The joining areas should be joined together within the time (table 1, column 4) immediately
until directly before the contact. At contacting, they have to meet with a speed of nearly
zero and right then Build-up a linear joining pressure P3 in the time shown at (table 1,
column 5)
19. After joining with pressure 0.15 N/mm², a bead must exist. According figure 6, K has to be>
0 on every section
20. Wait during the time shown at table 2 column 5 for cooling
21. Remove the welded parts from the welding machine after cooling completes

Page:90
Important issues at butt welding

• Materials to be welded should match each other


• In order to maintain correct welding parameters at high humid, extreme temperature and
windy environments working place should be protected against such weather conditions.
• Pieces should be avoided from direct sun lights to keep the pipes at the same temperature.
• Pieces to be welded should be cleaned from dust, dirt, e.g.
• Pipes should be fastened carefully before welding. This is required both for an accurate
centering and to keep the operator away from any harm during cutting and welding.
• During butt welding (cooling included), pieces should never face to mechanical force or
rupture.
• Other end of the welding pipe should be on a slippery surface to move freely. This is required
to do back/forward feeding without applying any force on welding area.
• Cutter tool should be at required sharpness. Knife of tool should be changed or sharpened at
certain intervals.
• There should be no deep scratch, notch, etc. on Teflon surface of heater. Surface of heater
should be checked occasionally.

Butt welding problems and possible causes

Page:91
ELECTROFUSION WELDING
Electrofusion is safe and presents high performance. In this method, the most important
aspects are the preparation and assembly geometry. Another issue to take care is the welding
energy.

Welding is done by heating resistances at muff section. After pipes are placed in the muff,
cables of welding machines are connected to pins of the muff and resistances are heated by the
electric current. The muff wall thickness is usually higher than the pipe thickness, as a result of
this, the heat of pipe wall will be higher than the muff wall heat. Pressure is formed in the pipe,
because of the heat difference. The pipes weld to each other by the pressure on and in the pipe.

In electrofusion welding, only pipes made of same raw material may be welded. Solution flow
speed for HDPE electrofusion joining is 0,2-1,7 gr/10 min (190°C / 5 kg). Pipes and muff's solution
flow speed should be between these values. The area where the welding will be made must be
weather-proof. Temperature around the welding environment must be between -10°C and +40°C.

Main reasons to choose Electrofusion Welding

EF is accepted as a safe, easily assembling system for pressured fluids by today's gas and water
network companies.
Technically, electrofusion welding is done after assembly and parts gathered tightly. Thus almost
no movement occurs between pipe and muff during welding.
Practically, all pipe sizes between 20-315 mm could be welded with EF. It is the only method to
allow pipes (diameter up to 125 mm.) to be used for long distances. Besides, EF can be used in
all networking building areas, connections under pressure, and in maintenance purposes.
EF welding usually does not require visual control after welding. W elding parameters can be
systematically applied to next welding process. Once conditions are defined, welding process is
done in automatic machines.
Generally, electrofusion welding machines have barcode readers, and the barcodes contains
welding parameters to report automatically to the machine. Most welding machines also allows
the operator to put the data in manually. Therefore a basic education is sufficient for electrofusion.
Advantages of EF welding:
• Pipe interior diameter does not shrink.
• Welding machines & equipment have low cost, easy to use, light.
• High welding speed.
• No pressure loss is considered at welding point.

Page:92
Electrofusion welding capabilities

While joining PE pipes with electrofusion welding method, PE made materials, such as
couplers, tapping saddles, reducers with resistant wire inside, are used. When electric current is
applied on resistance wire of the electrofusion fittings, heat spreads on a large area and melts the
material. Winding number and resistance values of wires are set in according to required energy
for melting the material.

Welding principles are similar apart from electrofusion fittings type or diameter. Required heat
for electrofusion welding, is obtained by joule effect of metallic resistance wires.

Figure 7: Welding area during operation

During electrofusion welding, the resistance inside electrofusion fittings is kept connected to
the energy for a certain of time specified by manufacturer. This resistance heats up the surfaces,
it touches and increase up to melting temperature. Temperature arises between 130°C - 250°C
during welding.

Page:93
EF Welding Steps
Pipe should be cut clean and smoothly from the welding ends, must be and perpendicular to its
own axis. If the pipe is not cut precisely, this results in contact between heating coils and the pipe,
which causes uncontrolled flow of melted material due to overheating.

Smooth and clean cut pipes are placed into electrofusion fittings up to the stops (middle of the
fittings) and pipe is marked. Scratch the pipe with a marker from marked area to the end.

Clean the pipe fittings' surface and scrape the oxidation with a scraper. Following, the internal
edge must be cleaned of fillings and the edges rounded off by a scraper.

Page:94
Pipes may have ovality if stored inconveniently. Ovality should not exceed 1,5% of the external
diameter of the pipe. When ovality exceeds this ratio fixing apparatus should be used.

Pieces to be welded must have clean surface, have no dirt, oil e.g. Electrofusion surfaces be
welded (coupler's interior, pipe and fittings' outer surfaces) must be cleaned by means of proper
fluids (industrial alcohol, acetone) and by soft, non-fuzzy papers. After the surfaces of pipe and
fittings are cleaned, they must not be touched.

Then the couplers is placed on the pipe and pushed until the leaning limit of couplers (marked
on the pipe).While joining, pipe and couplers must be parallel.

Page:95
Electrofusion welding ends are fixed after aligned with the pipe, and ends faced upwards.
Welding machine sockets are placed at the weld ends and prepared for welding.

After the ready signal is received from the machine, welding process is started having the
barcode indicated to the machine or having welding parameters manually entered. Generally the
welding machine indicates the welding time and voltage on monitor. After the welding process
ended, indicators move out.

Page:96
WELDING ERRORS AND REASONS

During welding pieces expose to inconvenient weather conditions


Bad weather condition during welding is an important effect on quality in electrofusion welding
as well as in the other welding methods. Above all, it caused to new faults by effecting operators
who cannot perform properly under such conditions. Welding under normal environment, such as
normal temperatures, free of dust, moisture and contaminations, will have direct effect on the
welding quality.

Unreleased pressurized air or gas flow in pipe, regional gas accumulations


Especially for maintenance applications pressurized air or gas will have various effects on
welding before or after. When a damaged pipe is cut and repaired with a EF coupler pressurized
pipe must be squeezed at both sides in order to prevent gas and water loses and endangering
the working site. It is important that no water or gas is left at the welding zone otherwise welding
might not be proper.

Low or high environment temperature


Air temperature (should be between 0°C and +35°C) at the welding site is an important issue and
direct effect on the welding quality. W hile deciding welding time in welding parameters,
environmental temperature is taken into consideration, and pipe and/or fittings temperatures are
considered to be close to the outer temperature values. If there is big difference welding might not
be correct.

Pause at welding operations


For some reasons, such as technical failures, energy cut off, electrofusion welding may stop at
half way before welding is complete. In this case, the welding pieces must be left to cool down
completely then the procedure could be started as it is a new welding. If the welding carried on
before the welding zone is cool quality problems are likely to occur.

Mechanical forces on welding area


One of the important issue at welding is to protect the pipe and fitting against any mechanical
loads during welding and cooling. If pipes are coiled, a positioning apparatus should be used at
welding.

Insufficient cleaning of the welding zone


Cleaning has direct effect on the quality of welding at both electrofusion and butt welding
techniques. Before welding oxidation layer on the pipe and fitting should be scraped out and then
wiped with convenient solvents. Cleaned zones should not be touched with bare hands.
Insufficient cleaning will end with welding failure.

Bends and ovality in pipes


PE pipes may have ovality and/or bends because of manufacture, storage and/or from various
operations on pipe. These pipes must be straightened before welding by means of using suitable
clamps and/or apparatus otherwise welding will result failure because of mismatch.

Page:97
Low voltage or choosing wrong welding time

To have a proper welding quality, correct pressure, heat and voltage must be obtained at welding
zone by using appropriate machinery. If required current (it is generally between 18 and 39 Volts
at electrofusion welding) and the other welding parameters, which are determined at laboratory
conditions, are not reached it is not possible to have a quality welding. If heating / welding time is
too long flow or burnt is inevitable, contrary when the time is too short the material is not yet
mature for welding. Both result in failure.

Using butt welding pipes on electrofusion welding method

PE pipes are produced based on outer diameter and classified in two groups: A (sensitive
tolerance) and B (medium tolerance). For electrofusion welding A group pipes are preferred, B
group is usually for butt welding. Butt welding pipes are not sensitive at outer diameter and may
create problems when used together with electrofusion fittings.

Mismatching of pipe and EF fittings, gap between pipes in EF fittings

PE pipes must be prepared for electrofusion welding according to the fittings to be used. When
pipe ends are not pushed in properly failure at welding is likely to occur. In this case melt material
will flow inside the pipe and/or close ci,rcuit may happen.

Pipe and electrofusion fitting made of different resins

During welding material between electrofusion fittings internal surface and pipes outer surface
must melt. Different resins will give different melting characteristics, therefore welding quality may
decrease when two different resin based pipe and fittings are used.

Problems arising from electrofusion fittings

Although manufacturers apply various quality checks at production the end user may receive
faulty electrofusion fittings. Ovality is the most common failure and using such fittings may result
with low quality welding and/or failure as one experience at using pipes with unacceptable ovality.

Incorrect insert in electrofusion fittings

Preparation is the most critical phase of electrofusion welding. Pipe ends must be marked before
scraping and cleaning so that pipe must be inserted in the fittings at desired length. Short insert
will result flow in the pipe and/or short circuit, contrary long insert will push the other part out by
giving the other part insufficient welding zone. In this case, from outside the welding operation is
considered fine but in reality it fails.

Page:98
Page:99
Page:100
Page:101
Page:102
Page:103
Page:104
Page:105
Page:106
Page:107
Page:108
Material Safety Data Sheet

Contractor and Supplier

Page:109
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

SECTION 1: Identification of the Substance/Mixture and of the Company/Undertaking

1.1 Product identifier


Trade name: SCGTM HDPE
Product type: High Density Polyethylene Compound (Black)
This SDS applies to all grades of HDPE Compound (Black) manufactured by Thai Polyethylene Co., Ltd.
1.2 Relevant identified uses of the substance or mixture and uses advised against
Application of the substance / the preparation: Raw material for different industrial uses
1.3 Details of the supplier of the safety data sheet

Manufacturer/Supplier: Further information obtainable from:


Thai Polyethylene Co., Ltd. Quality Assurance Department or Environmental Health and Safety
10 I-1 Road, Map Ta Phut Industrial Department
Estate, Muang, Rayong 21150 Thailand 10 I-1 road, Map Ta Phut Industrial Estate, Muang, Rayong 21150
Tel: +66 3868 3393-7 Thailand
Fax: +66 3868 3398 Tel: +66 3868 3393-7 ext. 2407 or 2459
www.scgchemicals.com or
Technical Service and Development Department
1 Siam Cement Road, Bangsue, Bangkok 10800 Thailand
Tel: +66 2586 1111 Fax: +66 2586 3676

1.4 Emergency telephone number:


Environmental Health and Safety Department
Tel: +66 3868 3138

SECTION 2: Hazards identification

2.1 Classification of the substance or mixture


• Classification according to Globally Harmonized System (GHS):
The substance is not classified as hazardous according to GHS.
• Classification according to Regulation (EC) No 1272/2008 (CLP):
The substance is not classified as hazardous according to the CLP regulation.
• Classification according to Directive 67/548/EEC or Directive 1999/45/EC:
The substance is not classified as hazardous according to Directive 67/548/EEC or Directive 1999/45/EC.

Thai Polyethylene Co., Ltd. P a g e |1


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:110
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

2.2 Label elements


• Labelling according to GHS: None
• Labelling according to Regulation (EC) No 1272/2008:None
• Hazard pictograms: None
• Signal word: None
• Hazard statements: None
• Precautionary statements :
Prevention: Not Applicable
Response: Not Applicable
Storage: Not Applicable
Disposal: Not Applicable
• Additional information:
Pellets on the floor may cause a serious slipping hazard.
Skin or eye contact with hot polymer can cause thermal burns.
Processing the polymer at high temperatures may form vapors that irritate the eyes and respiratory
tract.

2.3 Other hazards

• Results of PBT and vPvB assessment


- PBT: Not determined
- vPvB: Not determined

SECTION 3: Composition/information on ingredients

3.1 Chemical characterization: Mixture


Chemical Name CAS No. EC No. Concentration (wt%)
Ethylene-1-butene copolymer 25087-34-7 - > 96%

Additives - - < 4%

Thai Polyethylene Co., Ltd. P a g e |2


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:111
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

SECTION 4: First Aid Measures

4.1 Description of first aid measures:


• General information:
Take affected persons out of danger area and lay down.
• After inhalation:
Move person to fresh air; if symptoms persist, consult a doctor.
• After skin contact:
Wash exposed area with soap and water. Seek medical attention if symptoms develop or persist. If
molten polymer comes in contact with the skin, cool rapidly with cold water or running water. Do not
pull solidified polymer off the skin. Seek medical attention immediately.
• After eye contact:
In case of dust contact with eyes, flush thoroughly with running water for 5-15 minutes. Remove contact
lenses, if worn. Seek medical attention if irritating persists. For thermal eye burns, immediately flush
eyes with running water for 5-15 minutes. Do not remove contact lenses, if worn. Seek medical attention
immediately, preferably an ophthalmologist.
• After swallowing:
Rinse out mouth with water and gargle with plenty of water. If swallowed, consult a doctor. May cause
gastrointestinal blockage. Do not give laxative. Do not induce vomiting unless directed to do so by
medical personnel.
4.2 Most important symptoms and effects, both acute and delayed:
Skin and eye burns from molten product. Skin and eye irritation from product dusts. Irritated respiratory
tract from dust inhalation.
4.3 Indication of any immediate medical attention and special treatment needed:
Treat symptomatically and supportively.

Thai Polyethylene Co., Ltd. P a g e |3


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:112
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

SECTION 5: Firefighting Measures

5.1 Extinguishing media:


• Suitable extinguishing agents:
CO2, powder or water spray. Fight larger fires with water spray.
Use fire extinguishing methods suitable to surrounding conditions.
• Unsuitable extinguishing agents:
Do not use water jet
5.2 Special hazards arising from the substance or mixture:
• Hazard combustion products:
Carbon dioxide (CO2), Carbon monoxide (CO), other organic vapors and soot.
5.3 Advice for firefighters:
• Protective equipment:
Fire-fighters should wear appropriate protective equipment (includes fire-fighting helmet, coat, trousers,
boots and gloves) and positive pressure self-contained breathing apparatus (SCBA).
• Fire Fighting Procedure:
Keep people away. Isolate fire and deny unnecessary entry. Soak thoroughly with water to cool and
prevent re-ignition. If material is molten, do not apply direct water stream. Use fine water spray or foam.
Cool surroundings with water to localize fire zone.
• Additional information:
Collect contaminated fire fighting water separately. It must not enter the sewage system. Cool
endangered receptacles with water spray.

SECTION 6: Accidental Release Measures

6.1 Personal precautions, protective equipment and emergency procedures:


• For non-emergency personnel:
Material creates a slipping hazard on hard surfaces. Clean up spills from walking surfaces immediately.
Eliminate sources of ignition. Avoid formation of dust.
• For emergency responders:
Wear appropriate respirator when ventilation is inadequate. Put on appropriate personal protective
equipment.

Thai Polyethylene Co., Ltd. P a g e |4


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:113
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

6.2 Environmental precautions:


• Avoid dispersal and contact with soil, waterways, sewers and groundwater.
6.3 Methods and material for containment and cleaning up:
• For containment: place in a designated and labeled waste container.
• For cleaning up: sweep or shovel into suitable containers. Do not allow water contaminated with pellets
or powder to enter any waterway, sewer or drain.
• Other information: Dispose of contaminated material at an authorized site. Notify authorities if product
enters sewers or public waters.
6.4 Reference to other sections:
• See Section 7 for information on safe handling.
• See Section 8 for information on personal protection equipment.
• See Section 13 for disposal information.

SECTION 7: Handling and Storage

7.1 Precautions for safe handling:

• Protective Measures:
Put on appropriate personal protective equipment (see Section 8). Avoid contacting molten material
with eyes, skin and clothing. Avoid breathing dust and process fumes. Ensure good ventilation at the
workplace. Prevent dust accumulation. Pneumatic conveying of powder and pellets and other
mechanical handling operations can generate large static electrical charges. Dust can be ignited by
static electrical discharge. To avoid fire or explosion, dissipate static electricity during transfer by
grounding and bonding containers and equipment before transferring material. Worker should handle
the container with appropriate apparatus such as forklift and handlift. If worker feel stiff, should take a
rest sufficiently.
• Advice on general occupational hygiene:
Eating, drinking and smoking should be prohibited in areas where this material is handled, stored and
processed.
Always wash hands after handling the product.

Thai Polyethylene Co., Ltd. P a g e |5


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:114
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

7.2 Conditions for safe storage, including any incompatibilities:

• Technical measures and storage conditions:


Electrically bond and ground equipment to reduce the potential for dust explosions. Store in dry, cool,
dust-free and well-ventilated area at temperature below 50ºC. Protect from heat, direct sunlight and
rain.
• Packaging materials:
Store only in the original container. Keep container tightly closed and sealed until ready for use.
Containers that have been opened must be carefully resealed and kept upright to prevent leakage. Do
not store in unlabeled containers. Use
appropriate containment to avoid environmental contamination.
• Materials to avoid:
Store away from incompatible substances, flammable substances and oxidizing agents.
• Further information about storage conditions:
Use an appropriate handling and storage method as described in Manufacturer’s “Handling and storage
guide” Manual. (Please visit this website www.scgchemicals.com)

7.3 Specific end uses:

No further relevant information available.

8SECTION 8: Exposure Controls/Personal Protection

8.1 Control parameters:


• Occupational Exposure Limits Not established
8.2 Exposure controls:
8.2.1 Appropriate engineering controls: Provide readily accessible eye wash stations and safety
showers. Ensure adequate ventilation. If user operations
generate dust, fumes, gas, vapor or mist, use process
enclosures, local exhaust ventilation or other engineering
controls to keep worker exposure to airborne
contaminants below any recommended or statutory limits.

Thai Polyethylene Co., Ltd. P a g e |6


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:115
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

8.2.2 Personal protective equipment:


• Eye/Face protection Use safety glasses with side shields. If this material is
heated and there is potential for dust, wear chemical
goggles.
• Skin protection
- Hand protection Skin contact should be minimized. Use gloves to protect
from mechanical injury. Chemical protective gloves should
not be needed when handling this material. Use insulated
gloves when handling the hot or molten material.

- Body protection At ambient temperatures use of clean and protective


clothing is good industrial practice. If the material is
heated or molten, wear thermally insulated, heat-resistant
gloves that are able to withstand the temperature of the
molten product. If this material is heated, wear insulated
clothing to prevent skin contact if engineering controls or
work practices are not adequate.

• Respiratory protection A properly fitted air purifying respirator or air supply


respirator should be worn if a risk assessment indicates
that respiratory protection is necessary. Respirator
selection must be based upon known or measured levels of
exposure.
8.2.3 Environmental exposure control: Emissions from ventilation or work process equipment
should be checked to ensure they comply with the
requirements of environmental protection legislation. In
some cases, fume scrubbers, filters or engineering
modifications to the process equipment will be necessary
to reduce emissions to acceptable levels.

Thai Polyethylene Co., Ltd. P a g e |7


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:116
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

SECTION 9: Physical and chemical properties

9.1 Information on basic physical and chemical properties:


• Appearance: Pellets
• Physical state: Solid
• Color: Black
• Odor: Light
• Odor threshold: No data available
• pH: Not applicable
• Melting point: 125-135 °C
• Boiling point Not applicable
• Flash point: No data available
• Evaporation rate: Not applicable
• Flammability (solid, gas): No
• Upper/lower explosion limits: Not applicable
• Vapor pressure: Not applicable
• Vapor density Not applicable
• Relative density: No data available
• Density at 23°C 0.90-0.97 g/cm3
• Solubility in water: Insoluble.
• Partition coefficient, n-octane/water: No data available
• Auto-ignition temperature: No data available
• Decomposed temperature: No data available
• Viscosity, kinematic: Not applicable
• Viscosity, dynamic: No data available
• Explosive properties: No
• Oxidizing properties: No
9.2 Other information: No further relevant information available.

Thai Polyethylene Co., Ltd. P a g e |8


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:117
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

SECTION 10: Stability and Reactivity

10.1 Reactivity:
No dangerous reaction known under conditions of normal use.
10.2 Chemical stability:
The product is stable at normal handling and storage conditions.
10.3 Possibility of hazardous reactions:
Polymerization will not occur. Dust may form explosive mixture in air.
10.4 Conditions to avoid:
Avoid prolonged storage at elevated temperature. Exposure to elevated temperatures can cause product
to decompose (Temperature should less than 300°C). See Technical Datasheet for suitable processing
condition.
Avoid dust formation.
Avoid the build-up of electrostatic charge.
10.5 Incompatible materials:
Avoid contact with strong oxidizing agents.
10.6 Hazardous decomposition products:
Burning can produce carbon monoxide and/or carbon dioxide and other harmful products. The
decomposition products are low molecular weight oligomers, hydrocarbons and hydrocarbon oxidation
product (aldehydes, alcohols, organic acids) depending on temperature and air availability.

SECTION 11: Toxicological Information

Information on toxicological effects:


• Acute toxicity:
LD50 oral, rat Not determined.
• Skin corrosion/irritation: Non-irritating to skin. Mechanical injury only. Molten
polymer may cause serious thermal burns.
• Eye damage/irritation: Dust may cause eye irritation upon repetitive or prolonged
exposure. Molten polymer may cause serious thermal
burns. Vapors released during thermal processing may
cause eye irritation experienced as mild discomfort and
redness.

Thai Polyethylene Co., Ltd. P a g e |9


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:118
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

• Sensitization to the respiratory tract: No effects are expected for ingestion of small amounts.
May cause choking if swallowed.
• Skin sensitization: No relevant data found.
• Germ cell mutagenicity: No relevant data found.
• Carcinogenicity: No relevant data found.
• Reproductive toxicity: No relevant data found.
• Additional toxicological information: When used and handled according to specifications, the
product does not have any harmful effects to our
experience and the information provided to us.

SECTION 12: Ecological Information

12.1 Toxicity:
• Aquatic toxicity: Not expected to be acutely toxic, but material in pellet
form may mechanically cause adverse effects if ingested
by waterfowl or aquatic life.
12.2 Persistence and degradability: Not easily biodegradable
12.3 Bioaccumulative potential: This material is not expected to bioaccumulation because
of the relatively high molecular weight (MW greater than
1000).
12.4 Mobility in soil: This material is expected to remain in the soil and float on
the water surface
12.5 Results of PBT and vPvB assessment:
• PBT: Not determined
• vPvB: Not determined
12.6 Other adverse effects: Avoid release to the environment.

Thai Polyethylene Co., Ltd. P a g e | 10


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:119
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

SECTION 13: Disposal Considerations

13.1 Waste treatment methods:

• Waste disposal: Do not dump into any sewers, on the ground, or into any
body of water. All disposal practices must be in compliance
with official or local regulations. Regulations may vary in
different locations. Waste characterizations and
compliance with applicable regulations are the
responsibility solely of the waste generator.
• Packaging disposal: Do not reuse container. Disposal must be in compliance
with official or local regulations. The packaging only use
for industrial purpose.
• Waste treatment option: Recycle if possible
• Other disposal recommendations: Disposal must be made according to official or local
regulations.

SECTION 14: Transport information

14.1 UN-Number:
• ADR, IMDG, IATA Not regulated
14.2 UN proper shipping name:
• ADR, IMDG, IATA Not regulated
14.3 Transport hazard class(es):
• ADR, IMDG, IATA
• Class Not regulated
14.4 Packing group:
• ADR, IMDG, IATA Not regulated
14.5 Environmental hazards:
• Marine pollutant: No
14.6 Special precautions for user: Not applicable.

Thai Polyethylene Co., Ltd. P a g e | 11


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:120
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

14.7 Transport in bulk: Not applicable.


(according to Annex II of MARPOL73/78 and the IBC Code)
• Transport/Additional information: Not dangerous according to the above specifications.
• UN "Model Regulation": -

SECTION 15: Regulatory information

15.1 Chemical inventories More information on Declaration of Compliance (DoC)


15.2 Chemical safety assessment: A Chemical Safety Assessment has not been carried out.

SECTION 16: Other information

Recommended Uses and Restrictions


This product is a raw material for industrial conversion. We recommended you to use this product under
description in this document only.

Issued by
Thai Polyethylene Co., Ltd (QA & QC Department)
10 I-1 road, Map Ta Phut Industrial Estate, Muang, Rayong 21150 Thailand
Tel: +66 38 683393-7 ext. 2407
Fax: +66 38 683398

Disclaimer:
• It is customer’s responsibilities to inspect and test the product for suitability of the customer’s own use and purpose.
The customer is responsible for appropriate, safe, legal use, processing and handling of the product.
• To the best of our knowledge, the information contained herein is accurate and reliable as of the date of
publication. We however do not assume any liability whatsoever for the accuracy and completeness of the
information contained herein.
• We make no warranties which extend beyond the description herein. Nothing herein shall constitute any implied
warranty of merchantability or fitness for a particular purpose.
• No liability can be accepted in respect of the use of the product in conjunction with other materials. The information
contained herein relates exclusively to the product when it is not used in conjunction with any third party’s materials.

Thai Polyethylene Co., Ltd. P a g e | 12


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:121
Product Name
SAFETY DATA SHEET
SCGTM HDPE
Product Type

HDPE Compound (Black)

Revision: 01.01.2019 (Valid for 3 years from the lasts version) Version No: 7

Abbreviations and acronyms:


• ADR: Accord européen sur le transport des marchandises dangereuses par Route (European Agreement concerning
the International Carriage of Dangerous Goods by Road)
• IMDG: International Maritime Code for Dangerous Goods
• IATA: International Air Transport Association
• GHS: Globally Harmonized System of Classification and Labelling of Chemicals
• EINECS: European Inventory of Existing Commercial Chemical Substances
• CAS: Chemical Abstracts Service (division of the American Chemical Society)

Thai Polyethylene Co., Ltd. P a g e | 13


10 I-1 Road, Map Ta Phut Industrial Estate, Muang, Rayong, 21150 Thailand
www.scgchemicals.com
Tel. +66 3868 3393-7 Fax +66 3868 3398

Page:122
Warranty Certificate

Page:123
Page:124
Test Certificate / Report

Page:125
Sample MTC

Page:126
Page:127
Page:128
Previous Approval

Page:129
Page:130
Page:131
Page:132
Page:133
Page:134
Page:135
Page:136
Page:137
Page:138
Page:139
Page:140
Page:141
Page:142
Page:143
Page:144
Page:145
Page:146
Page:147
Page:148
Page:149
Page:150
Page:151
Page:152
Material Submittal Forms

Page:153
N/A

Page:154
Material Compliance Statement (As per QCS 2014)

Page:155
Page:156
Page:157
Page:158
Doha Regional Plastic Solutions
Head Office
Zone 81, St. No. 03, Building No. 282,
New Industrial Area
P.O. Box: 40613, Doha, Qatar
Tel. No: +974 4436 6244
Fax No: +974 4436 6277
E-mail: info@drps.com.qa
www.drps.com.qa

You might also like