LARSEN & TOUBRO (OMAN) LLC

PROJECT: CONSTRUCTION OF 132/33kV GRID STATION AND ASSOCIATED TRANSMISSION


SYSTEM IN MISFAH AREA (TENDER 175 / 2009)

CHECKLIST FOR WALL / FLOORING TILE

Area/ Bldg : Report No.:

Date :

Location : Drawing No :

Sl.No. Description Observed results Remarks

1 Surface cleaned, dry ,free from oil, grease, other foreign materials Yes No N.A

2 Check tiles / skirtings with approved sample proportion Yes No N.A

3 Check for tile layout and expansion joint location if any Yes No N.A

4 Check for Consistency of joint alignment & joint size. Yes No N.A

5 Line , level checked before starting of tiles laying Yes No N.A

6 Check alignment for skirting to be to true line . Yes No N.A

7 Any un evevness, air voids found Yes No N.A

8 Check for polishing work Yes No N.A

10 Clearance for MEP Works / subsequent activities Yes No N.A

11 Proper protection provided to avoid damage to tilings Yes No N.A

12 Care has to be taken to avoid damage of Battery room tiles during Yes No N.A
Acid filling

L&T (OMAN) LLC ENERGOPROJEKT ENTEL LLC

MISFAH-SF-C18