MECHANICAL ACCEPTANCE TEST FOR MOTOR Date :
PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN
OWNER :M/s NAYARA ENERGY LTD.(formerly known as Essar Oil Limited)
PMC : M/s PRAGATI ENGINEERING MANAGEMENT SERVICES
CONTRACTOR : M/s SOPAN O & M COMPANY LTD.
Work Order No. & Date:6300002455 Dated 15.11.2019
1 MANUFACTURER’S DATA
2 GENERAL CHECKS :
2.1 MOTOR
Checking of foundation Size of Power and Control Cables
(same as given in schedule )
Installation of motor Weather
Cable glanding and termination
proofing
of
terminal
Weather proofing of terminal
Free hand rotation box
Starting Star/Delta/Soft
Connections Star/Delta
start/VFD
Remark :
Name
Signature
Date
o : SOP/NAYARA/PEMS/ELE/MOTOR/MECH-ACK
Report No.
NAYARA
TEST PERFORMA FOR HV / MV MOTOR
PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN
OWNER :M/s NAYARA ENERGY LTD.(formerly known as Essar Oil Limited)
PMC : M/s PRAGATI ENGINEERING MANAGEMENT SERVICES
CONTRACTOR : M/s SOPAN O & M COMPANY LTD.
Work Order No. & Date:6300002455 Dated 15.11.2019
AREA :
AREA CLASSIFICATION :
LOCATION :
1 :- IR TEST OF MOTOR
1
U-E, V W EARTHED
2
V-E, U W EARTHED
3
W-E, U V EARTHED
4 U- V
5 V- W
6 W- U
1 R-E, YB EARTHED
2 Y-E, RB EARTHED
3 B-E, RY EARTHED
4 R-Y
5 Y-B
6 B-R
Remark
SOPAN PEMS
Name
Signature
Date
DOC NO. SOP/NAYARA/PEMS/EE/MOTOR-TEST
R Date : Report No.
I, RAJASTHAN
EQUIPMENT TAG NO :
EQUIPMENT SR.NO.:
RATING :
TESTING DATE:
REMARK
REMARK
547249
11/8/2021
rtificate No. : KES/210216E/002
PEMS NAYARA
DOC NO. SOP/NAYARA/PEMS/EE/MOTOR/PRE-COMM
FIELD INSPECTION REPORT - MOTOR NO LOAD Date : Report No.
PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN
OWNER :M/s NAYARA ENERGY LTD.(formerly known as Essar Oil Limited)
PMC : M/s PRAGATI ENGINEERING MANAGEMENT SERVICES
CONTRACTOR : M/s SOPAN O & M COMPANY LTD.
Work Order No. & Date:6300002455 Dated 15.11.2019
a) DIRECTION OF ROTATION _ CLOCK WISE CCW (ANTI CLOCK WISE FROM NDE OF MOTOR)
( IF INCORRECT REVERSE
THE LEADS AND CORRECT TACHOMETER CALIBRATION DETAILS VIBRATION METER CALIBRATION DETAILS
TERMINAL COLOUR CODING Make : LT Sr. No. DTM-01 Make LUTRON Sr. No. S.8767
b) STARTING CURRENT (KICK) _ Validity upto : 13-01-2023 Test certificate No. HITC-M-01-22-426-01 Validity upto Test certificate No.
2/24/2023 CC223921000001988 P
Ambient Temp. :
12:15 7.75 64.51 7.83 62.8 7.35 63.3 414 415 415 1500 38.9 39.3 39 NORMAL 0.4 0.3 0.5
12:45 7.25 64.56 7.23 62.1 7.34 63.4 414 415 415 1499 52.3 42.01 41 NORMAL 0.6 0.5 0.5
13:15 7.43 64.35 7.45 62.3 7.62 63.3 414 415 415 1499 52.9 42.9 42 NORMAL 0.7 0.5 0.3
13:45 7.58 64.72 7.65 62.6 7.38 63.3 414 415 415 1499 53.1 43.2 43 NORMAL 0.9 0.5 0.2
14:15 7.24 64.75 7.37 62.9 7.69 63.3 414 415 415 1499 52.7 43.9 43 NORMAL 0.8 0.5 0.3
14:45 7.58 64.62 7.33 62.3 7.57 63.3 414 415 415 1499 50.3 44.2 44 NORMAL 0.7 0.5 0.3
15:15 7.82 64.26 7.22 62.5 7.41 63.3 414 415 415 1499 55.01 45.3 45 NORMAL 0.7 0.5 0.6
15:45 7.43 64.62 7.55 62.6 7.77 63.3 414 415 415 1499 56.5 47.1 47 NORMAL 0.7 0.5 0.9
Remarks :
Signature
Name
Date
PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN
OWNER :M/s NAYARA ENERGY LTD.(formerly known as Essar Oil Limited)
PMC : M/s PRAGATI ENGINEERING MANAGEMENT SERVICES
CONTRACTOR : M/s SOPAN O & M COMPANY LTD.
Work Order No. & Date:6300002455 Dated 15.11.2019
AREA :
AREA CLASSIFICATION :
RATING :
VOLATAGE:
RPM:
Ambient Temp. :
ON LOAD CURRENT
TIME
R Y B
Remarks :
Description SOPAN
Signature
Name
Date
FIELD INSPECTION REPORT - MOTOR ON LOAD
ASTHAN
EQUIPMENT SR.NO.:
EQUIPMENT TAG NO :
CONNECTION:
CURRENT:
MEATHOD OF STARTING :
TACHOMETER CALIBRATION DE
Make : LT
VOLTAGE AT TERMINAL
RPM
T TAG NO :
OF STARTING :
BEARING TEMP °C
BODY /Winding
NOISE LEVEL
TEMP °C
DE NDE
PEMS
DOC NO. SOP/NAYARA/PEMS/EE/MOTOR-COMM
Date : Report No.
VIBRATION (mm/sec.)
DE
EIL
APPROVED BY EIL
APPROVED BY
Horizontal Vertical Axial
NAYARA