Owner CONTRACTOR

INSTALLATION OF AC UPS
PMC

Doc No .
PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT SOP/NAYARA/PEMS/EE/INSTL/IR-19A
VILLAGE SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN Rev.0.0

TAG No. Falcon 1k 2X15KVA TYPE & SIZE Three Phase ups

MANUFACTURER Fe Fuji Electric RATING 15KVA

REFERENCE DOCUMENTS: SOP-NAYA-PS-ELE-LTP-204

INSTALLATION CHECKS OF UPS CHARGER/ BATTERY Acceptable


1 Remarks
CHARGER/RECTIFIER (Yes / No / NA)

a Verification of name plates against data sheets yes

Equipment fixing and mountings are secure yes


b
External damage No
c
All connections are tight correct and cable markings are fitted yes
d
Connections with battery charger rectifier is correct Yes
e
Check equipment base frame are properly fixed Yes
f
g Check whether equipment is suitable for IP rating Yes

h Check gaskets and seals are not damaged Na

Acceptable
2 BATTERY SET Remarks
(Yes / No / NA)
a Batteries and racks installation Yes

Level of electrolyte in each cell Yes Maintenance Free


b
Leakage of electrolyte in cell if
NA
c any

Specific gravity NA
d
Number plates of cells and
Yes
e connection links
General cleaning & tightness of
Yes
f all cables connection

g Battery connection and Polarity Yes

Anticorrosive coating (Vaseline)


h Yes
provided on terminals

REMARKS :

SOPAN PEMS NAYARA

SIGN :

NAME :

DATE :
Owner CONTRACTOR

CHECK LIST FOR TESTING &


COMMISSIONING
OF AC/DC UPS
PMC

PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE Doc No . SOP/NAYARA/PEMS/EE/PRE-


SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN COMM/IR-19B Rev.0.0

TAG No. Falcon 1k 2X15KVA SYSTEM SR.NO P1202112211649

MANUFACTURER Fe Fuji Electric RATING 15KVA

INPUT 415V AC, 3Φn, Hz.50 BYPASS 240V AC, 1Φn, Hz.50

OUTPUT 240V AC, 1Φn, Hz.50 BATTERY 240 V DC

REFERENCE DOCUMENTS: SOP-NAYA-PS-ELE-LTP-204

1 BUSBAR TIGHTNESS

60 NM
Torque Value :

YES
Busbar Tightness checked with standard Torque Value for all joints

2 INSULATION RESISTANCE TEST TEST VOLTAGE 500V DC

Phase to Phase RY-505.46 MΩ,YB-524.345MΩ,BR-584.78MΩ

Phase to earth RE-574.68MΩ,YE-517.53MΩ,BE-567.74MΩ

Input Power supply cable, Battery


Positive to negative PN-175.75MΩ
cables

Positive to earth PE-185.76MΩ

Negative to earth NE-178.44MΩ

2.0 COMMISSIONING CHECKS

AC input voltage : RN-239 YN-239 BN-239

Rectifier DC output voltage : PN-270

Operating temperature in cabinet : 25°C

Battery voltage : 270 V DC

Abnormal noise if any : NO

Vendor report attached : YES

On completion of all cable glanding confirm spare entries are sealed : YES Sealed

UPS parellel operation and by pass operation sequences are tested satisfactorily Yes

Space heaters and lighting circuit to be tested : Yes

Switching from normal operation/battery operation/maintenance bypass test completed satisfactorily : Yes

REMARKS :

SOPAN PEMS NAYARA

SIGN :

NAME :

DATE :
Owner CONTRACTOR

CHECK LIST FOR TESTING &


COMMISSIONING
OF AC/DC UPS
PMC

PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE Doc No . SOP/NAYARA/PEMS/EE/P-06/IR-


SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN 02B Rev.0.0

TAG No. Falcon 1k 2X15KVA SERIAL NUMBER P1202112211649

MANUFACTURER Fe Fuji Electric RATING 15KVA

REFERENCE DOCUMENTS: SOP-NAYA-PS-ELE-LTP-204

1 BUSBAR TIGHTNESS

Torque Value :

Busbar Tightness checked with standard Torque Value for all joints

2 INSULATION RESISTANCE TEST TEST VOLTAGE

Phase to Phase

Phase to earth

Input Power supply cable, Battery


Positive to negative
cables

Positive to earth

Negative to earth

2.0 COMMISSIONING CHECKS

AC input voltage :

DC output voltage :

Operating temperature in cabinet :

Battery voltage :

Abnormal noise if any :

Vendor report attached :

On completion of all cable glanding confirm spare entries are sealed :

UPS parellel operation and by pass operation sequences are tested satisfactorily :

Space heaters and lighting circuit to be tested :

Switching from normal operation/battery operation/maintenance bypass test completed satisfactorily :

3.0 TEST READINGS OF CHARGE/DISCHARGE CYCLE OF BATTERY SET ( TO BE ATTACHED SEPERATELY)

MEASURING INSTRUMENT USED :


MAKE SL NO
TYPE/RATING: CALIBRATION DUE DATE:
CALIBRATION CERTIFICATE : CALIBRATION DUE DATE:

REMARKS :

SOPAN PEMS NAYARA

SIGN :

NAME :

DATE :
Owner CONTRACTOR

INSTALLATION OF AC UPS
PMC

Doc No .
PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT SOP/NAYARA/PEMS/EE/INSTL/IR-19A
VILLAGE SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN Rev.0.0

TAG No. Falcon 1k 2X40KVA TYPE & SIZE Three Phase ups

MANUFACTURER Fe Fuji Electric RATING 40KVA

REFERENCE DOCUMENTS: SOP-NAYA-PS-ELE-LTP-204

INSTALLATION CHECKS OF UPS CHARGER/ BATTERY Acceptable


1 Remarks
CHARGER/RECTIFIER (Yes / No / NA)

a Verification of name plates against data sheets yes

Equipment fixing and mountings are secure yes


b
External damage No
c
All connections are tight correct and cable markings are fitted yes
d
Connections with battery charger rectifier is correct Yes
e
Check equipment base frame are properly fixed Yes
f
g Check whether equipment is suitable for IP rating Yes

h Check gaskets and seals are not damaged Na

Acceptable
2 BATTERY SET Remarks
(Yes / No / NA)
a Batteries and racks installation Yes

Level of electrolyte in each cell Yes Maintenance Free


b
Leakage of electrolyte in cell if
NA
c any

Specific gravity NA
d
Number plates of cells and
Yes
e connection links
General cleaning & tightness of
Yes
f all cables connection

g Battery connection and Polarity Yes

Anticorrosive coating (Vaseline)


h Yes
provided on terminals

REMARKS :

SOPAN PEMS NAYARA

SIGN :

NAME :

DATE :
Owner CONTRACTOR

CHECK LIST FOR TESTING &


COMMISSIONING
OF AC/DC UPS
PMC

PROJECT : CONSTRUCTION OF RAIL FED DEPOT AT VILLAGE Doc No . SOP/NAYARA/PEMS/EE/PRE-


SWAIPURA/CHOTILA,DIST-PALI, RAJASTHAN COMM/IR-19B Rev.0.0

TAG No. Falcon 1k 2X40KVA SYSTEM SR.NO P1202112211647

MANUFACTURER Fe Fuji Electric SYSTEM RATING 40KVA

INPUT 415V AC, 3Φn, Hz.50 BYPASS 240V AC, 1Φn, Hz.50

OUTPUT 240V AC, 1Φn, Hz.50 BATTERY / Ah 377 V DC 130 Ah

REFERENCE DOCUMENTS: SOP-NAYA-PS-ELE-LTP-204

1 BUSBAR TIGHTNESS

60 NM
Torque Value :

YES
Busbar Tightness checked with standard Torque Value for all joints

2 INSULATION RESISTANCE TEST TEST VOLTAGE 500V DC

Phase to Phase RY-467.73 MΩ,YB-484.485MΩ,BR-484.95MΩ

Phase to earth RE-453.76MΩ,YE-495.76MΩ,BE-432.81MΩ

Input Power supply cable, Battery


Positive to negative PN-163.23MΩ
cables

Positive to earth PE-174.72MΩ

Negative to earth NE-149.84MΩ

2.0 COMMISSIONING CHECKS

AC input voltage : RN-239 YN-240 BN-240

Rectifier DC output voltage : PN-405

Operating temperature in cabinet : 25°C

Battery voltage and Ah : 377 V DC 130 Ah

Abnormal noise if any : NO

Vendor report attached : YES

On completion of all cable glanding confirm spare entries are sealed : YES Sealed

UPS parellel operation and by pass operation sequences are tested satisfactorily Yes

Space heaters and lighting circuit to be tested : Yes

Switching from normal operation/battery operation/maintenance bypass test completed satisfactorily : Yes

REMARKS :

SOPAN PEMS NAYARA

SIGN :

NAME :

DATE :
Plant Name Err:504
FORM No.
AC/DC UPS AND BATTERIES System No Err:504
B15 Subsystem No Err:504
TCM ID CODE : 3435-LZ-PQ-06-05001 POLYOLEFINS UNITS,PRODUCT HANDLING AND MARINE WORKS
BROUGE ID CODE : 06-SY-478-05001 BOROUGE 2 PROJECT,RUWAIS,UAE Report No 001

Rev Q3
TAG No.
Falcon 1k 2X15KVA TYPE & SIZE Three Phase ups

MANUFACTURER Fe Fuji Electric RATING 15KVA

REFERENCE DOCUMENTS:

TPI/
B15.1A INSTALLATION CHECKS OF UPS CHARGER/ BATTERY CHARGER/RECTIFIER TICB TCM
COMPANY

a Verification of name plates against data sheets Yes / No / NA

Equipment fixing and mountings are secure Yes / No / NA


b
External damage Yes / No / NA
c
All connections are tight correct and cable markings are
Yes / No / NA
d fitted

Connections with battery charger rectifier is correct Yes / No / NA


e
Check equipment base frame are properly fixed Yes / No / NA
f

g Check whether equipment is suitable for IP rating Yes / No / NA

Check gaskets and seals are not damaged Yes / No / NA


h
On completion of all cable glanding confirm spare entries
Yes / No / NA
i are sealed

Vendor report attached Yes / No / NA


j

Conductivity tests (Microhms)


Unit No Err:504

Phase R (L1) Err:504

Phase Y (L2) Err:504

Phase B (L3). Err:504

BUSBAR TIGHTNESS
Torque Value : Err:504
Busbar Tightness checked with standard Torque Value for Yes / No / NA
all joints

INSULATION RESISTANCE TEST


TEST VOLTAGE Err:504

a) Voltage between positive pole and earth "U1" (V) Err:504

b) Voltage between negative pole and earth "U2" (V) Err:504


MEASURING INSTRUMENT USED :
MAKE Err:504
TYPE/RATING: Err:504 SL NO Err:504

CALIBRATION Err:504 CALIBRATION DUE Err:504


CERTIFICATE : DATE:
REMARKS :
For charging and discharging test. Data for Batteries, Please refer vendor reports. Identified to ITP by Vender Scope.

TICB TCM TPI / COMPANY


.
NAME Err:504 Err:504 Err:504

SIGNATURE VVVVVV

DATE Err:504 Err:504 Err:504

Page 1 of 2
Plant Name Err:504
FORM No.
AC/DC UPS AND BATTERIES System No Err:504
B15 Subsystem No Err:504

TCM ID CODE : 3435-LZ-PQ-06-05001


POLYOLEFINS UNITS,PRODUCT HANDLING AND MARINE WORKS
BROUGE ID CODE : 06-
SY-478-05001 BOROUGE 2 PROJECT,RUWAIS,UAE Report No 001

Continued form Page 1 Rev Q3


ITEM Err:504
TYPE & SIZE
Err:504

MANUFACTURER RATING Err:504


Err:504

REFERENCE DOCUMENTS:

B15.1B INSTALLATION CHECKS OF A BATTERY TICB TCM TPI/ COMPANY

A Ventilation system satisfactory Yes/No/NA

B Presence of pole & mark & element numbering Yes/No/NA

C Termination corect tight Yes/No/NA

Area Classification correct (Ex / Gas Group /


D Yes/No
Temp Class)

E Labeling of Batteries done Yes/No/NA

REMARKS :

TICB TCM TPI / COMPANY


NAME Err:504 Err:504 Err:504

SIGNATURE

DATE Err:504 Err:504 Err:504


Page 2 of 2