You are on page 1of 1

FORMAT: E16

PERFORMA-MEASUREMENT OF IR VALUE & CONTINUITY CHECK OF CONTROL CABLES

Project : KPCAP Report No. :EE/ITP/06


Client : BPCL Date :06/05/2013
Contractor : SOPAN PROJECT Job no. : A218
Name of work: Composite Work IP:3 Malarna work order No.:

S.NO CABLE SIZE IR(M


OHM)
TAG VALUE