TAMBAK LOROK COMBINED CYCLE
POWER PLANT BLOCK 3 PROJECT
WITH NET DEPENDABLE CAPACITY OF 600 – 850 MW.
SEMARANG – CENTRAL JAVA
Subject: Commissioning ITPL - Bypass Operation
Issue Purpose: Responsible Dept:
Issued for Construction PE-ACE
Originator:
TBL/31/E/153b---001/SP/021 0 0 / 11
Issue date: 2022-03-18
Revision History
Rev. Revision Issued by Checked by Released by Brief Description
Date
A 09-01-2020 N. MEKALA S. SUGUMARAN B. Baskaran
B 22-11-2021 S. SUGUMARAN S. SUGUMARAN B. Baskaran Customer comments
incorporated
Owner
Project:
TAMBAK LOROK COMBINED CYCLE
POWER PLANT BLOCK 3 PROJECT
WITH NET DEPENDABLE CAPACITY OF 600 – 850 MW.
SEMARANG – CENTRAL JAVA
Subject: Commissioning ITPL - Bypass Operation
Originator:
TBL/31/E/153b---001/SP/021 1/12
Issue date:
ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
Released
The first two pages of this document are only needed for the correct handling of this template file inside the PPDM.
To use it on site please take the word file (.docx) attached to this document (or inside PPDM tool).
Remove the first two pages by highlighting (selecting) the content starting from the title on the first page until the last
word of this second page and press the delete button. The current page 3 will then become the front page of the
relevant ITPL.
Before printing the file ensure the front page is correctly filled and that the GE Document Code (already prepared in
the footer) is adjusted with the three-digit project mnemonic and if needed the unit numbering and the last three-digit
continuous numbering (for more details about GE document code refer to GAS/00/E/02a----002/IS/013).
Ensure that all headers and footers on each page are complete and contain the correct page numbers, date and
document codes.
The attachment (if used) contains a list of all sub-item KKS’ belonging to the scope of this ITPL. For multi-unit plants
the list contains all KKS’ across all units. When issuing a unit specific ITPL the other units KKS’s shall be deleted from
the list.
ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
System Name: Commissioning ITPL - Plant Trip Tests
Name of the System / Item covered by this ITPL
Use this space for the contractual document designation if needed. Otherwise keep empty and delete this text.
The inspection and test plan does not release the subcontractor / manufacturer from his obligation to take all steps necessary to ensure that
the requirements stipulated in drawings and specifications are fulfilled for the product concerned.
GE POWER GE Document Code Rev. Date Lang. Sheet
Gas Power Systems TBL/31/E/153b---001/SP/021 0 en 3/11
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate
affiliates.
ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
TABLE OF CONTENTS:
SAFETY SYMBOLS ........................................................................................................................................................ 5
GENERAL ......................................................................................................................................................................... 6
PLANT CONDITIONS ...................................................................................................................................................... 7
COLD COMMISSIONING OF FUNCTION GROUP / SEQUENCER CONTROL ...................................................... 7
INITIAL START OF SYSTEM ......................................................................................................................................... 7
SUPERIOR SEQUENCER TEST ................................................................................................................................... 9
OPTIMIZATION AND FINAL TESTS ............................................................................................................................. 9
AFTER COMMISSIONING .............................................................................................................................................. 9
ATTACHMENT ............................................................................................................................................................... 11
The inspection and test plan does not release the subcontractor / manufacturer from his obligation to take all steps necessary to ensure that
the requirements stipulated in drawings and specifications are fulfilled for the product concerned.
GE POWER GE Document Code Rev. Date Lang. Sheet
Gas Power Systems TBL/31/E/153b---001/SP/021 0 en 4/11
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate
affiliates.
ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1. SAFETY SYMBOLS
The User must understand the following symbols used within this document:
DANGER
WARNING
Warning indicates a potentially hazardous situation that if not avoided,
could result in death or serious injury.
CAUTION
Note
Note indicates an important instruction or the best practices
It may also be used to alert against mechanical damage to the equipment
The inspection and test plan does not release the subcontractor / manufacturer from his obligation to take all steps necessary to ensure that
the requirements stipulated in drawings and specifications are fulfilled for the product concerned.
GE POWER GE Document Code Rev. Date Lang. Sheet
Gas Power Systems TBL/31/E/153b---001/SP/021 0 en 5/11
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate
affiliates.
ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1) Performed by B = GE or GE’s representative unit H = Hold point (observe notification period) Q = Q record to K
K = Customer or his representative
2) Acceptance by L = Erection Contractor M = Witness point (observe notification period) R = Internal Record
S = Official acceptance authority
3) Q – Record U = Material supplier, supplier ext. products and ext. processes Y = Internal test C = Record in Com. Record Set
System Name
Inspection and Test Plan Bypass Operation
Q Activities Step Completed
No. Description Procedure Record Remarks
1) 2) 3) Date / Signature
2. GENERAL
1.1 Make sure the general and project specific environmental aspects are known - - Y
and observed.
1.2 Make sure that all tests are carried out in accordance with the specified - - Y
regulations and requirements.
1.3 Make sure that the safety requirements are observed as mentioned in the TBL/00/P/CSR-------/CM/001 - B K*
project specific commissioning safety rules. If other regional requirements have
to be considered follow the more strict one.
1.4 Ensure that commissioning permit to work rules are known and followed. TBL/00/P/PTW--------/CM/001 - B K*
1.5 Check that system is turned over from erection to commissioning, that TBL/00/P/TP-- ------/CM/001 - B K*
“Notification of Change Certificate” (NOCC) is issued and that “Energisation
Clearence Protocol” (ECP) is filled out before first energisation.
1.6 Check system readiness and that preceding activities are completed and that - - B K*
relevant open items from turn over are closed.
1.8 Verify the completeness of the documentation as mentioned in the ITPL, collect - - B K*
all relevant drawings and documents at the latest revision.
1.9 Verify the needs of special tools. Make sure they are ordered / organised and - - B K*
verify if the calibration of entire test equipment is certified and valid.
1.10 Verify the needs of equipment original supplier or official authority. Ensure the - - Y
arrangement in time.
*Note: Activities marked with “K&M” in Q- Activities column 2 will be coordinated/informed during the daily site commissioning planning meeting only
The inspection and test plan does not release the subcontractor / manufacturer from his GE POWER GE Document Code Rev. Date Lang. Sheet
obligation to take all steps necessary to ensure that the requirements stipulated in TBL/31/E/153b---001/SP/021 0 en 6/11
drawings and specifications are fulfilled for the product concerned. Gas Power Systems
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.
ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1) Performed by B = GE or GE’s representative unit H = Hold point (observe notification period) Q = Q record to K
K = Customer or his representative
2) Acceptance by L = Erection Contractor M = Witness point (observe notification period) R = Internal Record
S = Official acceptance authority
3) Q – Record U = Material supplier, supplier ext. products and ext. processes Y = Internal test C = Record in Com. Record Set
System Name
Inspection and Test Plan Bypass Operation
Q Activities Step Completed
No. Description Procedure Record Remarks
1) 2) 3) Date / Signature
3. PLANT CONDITIONS
2.1 Commissioning of systems required for bypass operation completed - - B K* C
2.2 Gas turbine and Steam Turbine on turning gear - - B K*
2.3 Gas turbine and HRSG ready to start - - B K*
The inspection and test plan does not release the subcontractor / manufacturer from his GE POWER GE Document Code Rev. Date Lang. Sheet
obligation to take all steps necessary to ensure that the requirements stipulated in TBL/31/E/153b---001/SP/021 0 en 7/11
drawings and specifications are fulfilled for the product concerned. Gas Power Systems
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.
ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1) Performed by B = GE or GE’s representative unit H = Hold point (observe notification period) Q = Q record to K
K = Customer or his representative
2) Acceptance by L = Erection Contractor M = Witness point (observe notification period) R = Internal Record
S = Official acceptance authority
3) Q – Record U = Material supplier, supplier ext. products and ext. processes Y = Internal test C = Record in Com. Record Set
System Name
Inspection and Test Plan Bypass Operation
Q Activities Step Completed
No. Description Procedure Record Remarks
1) 2) 3) Date / Signature
4.5 Verify the Stabilization of gland steam pressure and temperature control - - B K* C
4.6 Monitor pressure in the Condenser and operation of vacuum pumps - - B K* C
4.7 Stabilize bypass pressure control - - B K* C
4.8 Test and adjust HRSG safety valves - Supplier test record B/ M* Q
U
*Note: Activities marked with “K&M” in Q- Activities column 2 will be coordinated/informed during the daily site commissioning planning meeting only
The inspection and test plan does not release the subcontractor / manufacturer from his GE POWER GE Document Code Rev. Date Lang. Sheet
obligation to take all steps necessary to ensure that the requirements stipulated in TBL/31/E/153b---001/SP/021 0 en 8/11
drawings and specifications are fulfilled for the product concerned. Gas Power Systems
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.
ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1) Performed by B = GE or GE’s representative unit H = Hold point (observe notification period) Q = Q record to K
K = Customer or his representative
2) Acceptance by L = Erection Contractor M = Witness point (observe notification period) R = Internal Record
S = Official acceptance authority
3) Q – Record U = Material supplier, supplier ext. products and ext. processes Y = Internal test C = Record in Com. Record Set
System Name
Inspection and Test Plan Bypass Operation
Q Activities Step Completed
No. Description Procedure Record Remarks
1) 2) 3) Date / Signature
8. AFTER COMMISSIONING
7.1 Check the completeness of Q.A. documentation - - B K*
7.2 Finalize red correx - - B K* C
The inspection and test plan does not release the subcontractor / manufacturer from his GE POWER GE Document Code Rev. Date Lang. Sheet
obligation to take all steps necessary to ensure that the requirements stipulated in TBL/31/E/153b---001/SP/021 0 en 9/11
drawings and specifications are fulfilled for the product concerned. Gas Power Systems
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.
ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1) Performed by B = GE or GE’s representative unit H = Hold point (observe notification period) Q = Q record to K
K = Customer or his representative
2) Acceptance by L = Erection Contractor M = Witness point (observe notification period) R = Internal Record
S = Official acceptance authority
3) Q – Record U = Material supplier, supplier ext. products and ext. processes Y = Internal test C = Record in Com. Record Set
System Name
Inspection and Test Plan Bypass Operation
Q Activities Step Completed
No. Description Procedure Record Remarks
1) 2) 3) Date / Signature
7.3 "Make sure this I & T plan as well as the test certificates and red correx - - B K*
belonging to it are signed by the commissioning manager.
Name: _______________________________
*Note: Activities marked with “K&M” in Q- Activities column 2 will be coordinated/informed during the daily site commissioning planning meeting only
The inspection and test plan does not release the subcontractor / manufacturer from his GE POWER GE Document Code Rev. Date Lang. Sheet
obligation to take all steps necessary to ensure that the requirements stipulated in TBL/31/E/153b---001/SP/021 0 en 10/11
drawings and specifications are fulfilled for the product concerned. Gas Power Systems
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.
ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
System Name
Inspection and Test Plan AutoField for: Item or System Name
KKS Function Designation Component Step Test certificate Checked Remarks