Cat: 3
Besides the information discussed in the following, it is assumed that 2 = Approved with comments / reviewed as noted
subjects and the document itself are at least in accordance with the
Contract specification. Approval or comment will not relieve the Con- 3 = Not approved, rejected / returned for correction
tractor from fulfilling his contractual obligations. 4 = For information only
Com. Doc. Revi- Predec Owner’s / Owner’s Engineer’s Comments Contractor’s Response / Conclusion
ID: Rev. ewer essor [Abbreviations: KE=K-Electric Ltd. (Owner); TEG = Tractebel Engineering GmbH (Owner’s Action
Engineer); NES = NESPAK (Owner’s Engineer); RE2 = Renewable Resources Ltd. (To be submitted together with
(Owner’s Engineer)] the revised/completed docu-
ments)
1. 0 KE NIL Please mention reference drawing number for stairs finishing
details in notes
2. 0 KE NIL Sample of railing shall be approved on site.
3. 0 KE NIL Stair post embedded casing material shall be of GI
4. 0 KE NIL In section 2-2, mark waterproofing details
5. 0 KE NIL In section 1-1 GL is marked as 0.00 while in section 2-2 it is
marked as -0.500. HEI to rectify.
6. 0 KE NIL All metal plates shall be hot dip galvanized & protective coating
applied as per KE specifications.
7. 0 NE NIL The size of loading platform shall be finalised as per operational
requirments considering the maximum size of
equipment/component to be transported through it. HEI shall
check and confirm.
One behalf of the Owner On behalf of the Owner’s Engineer On behalf of the Contractor
Name:
Signature:
Date: