Besides the information discussed in the following, it is assumed that 2 = Approved with comments / reviewed as noted
subjects and the document itself are at least in accordance with the
Contract specification. Approval or comment will not relieve the 3 = Not approved, rejected / returned for correction
Contractor from fulfilling his contractual obligations. 4 = For information only
Com. Doc. Revi- Predec Owner’s / Owner’s Engineer’s Comments Contractor’s Response / Conclusion
ID: Rev. ewer essor [Abbreviations: KE=K-Electric Ltd. (Owner); TEG = Tractebel Engineering GmbH (Owner’s Action
Engineer); NES = NESPAK (Owner’s Engineer); RE2 = Renewable Resources Ltd. (To be submitted together with
(Owner’s Engineer)] the revised/completed
documents)
1. 0 KE NIL Fence details around gantry area is missing. HEI to mark fence in RFP didn’t have this
drawing along with related distances from gantry. require , please check
龙门区域周围的围栏详细信息丢失。 HEI 在图纸中标记围栏以及
距龙门架的相关距离。
2. 0 KE NIL HEI to provide reference of electrical drawings for the subject Noted
drawing & also incorporate the same in drawing notes.
HEI 为主题图纸提供电气图纸参考,并将其纳入图纸注释中。
3. 0 KE NIL All metal parts shall be hot dip galvanized & finish with protective Noted, please check
coating as per KE specifications. E113S-LAN-T0303-01
所有金属部件均应按 KE 规范进行热浸镀锌和表面处理,并涂上防 note 6.3
护涂层。
4. 0 NES NIL Please refer to our comments on design calculation E113S-LAN- Noted
T0303-CS-01.
5. 0 NES NIL The details including height, conductor attachment points etc. Noted and
shall all be finalised as per related approved electrical drawings. incorporated
包括高度,导体连接点等在内的所有细节均应根据相关批准的电气
图纸完成。
Page 1 of 3
900 MW BQPS-III Combined Cycle & Associated Projects, Pakistan
Com. Doc. Revi- Predec Owner’s / Owner’s Engineer’s Comments Contractor’s Response / Conclusion
ID: Rev. ewer essor [Abbreviations: KE=K-Electric Ltd. (Owner); TEG = Tractebel Engineering GmbH (Owner’s Action
Engineer); NES = NESPAK (Owner’s Engineer); RE2 = Renewable Resources Ltd. (To be submitted together with
(Owner’s Engineer)] the revised/completed
documents)
HEI are advised to submit and attain the approval of all related
Electrical Drawings & loadings from KE/OE prior to finalisation of
the structural design.
建议 HEI 在完成结构设计之前,先从 KE / OE 提交并获得所有相关
电气图和载荷的批准。
6. 0 NES NIL HEI shall check and ensure that all the design loading parameters Noted and
for Gantry Towers including Sag, conductor tension, Short circuit incorporated
loading, temperature, wind etc. are being finalised as per
approved Electrical Data.
Com. Doc. Revi- Predec Owner’s / Owner’s Engineer’s Comments Contractor’s Response / Conclusion
ID: Rev. ewer essor [Abbreviations: KE=K-Electric Ltd. (Owner); TEG = Tractebel Engineering GmbH (Owner’s Action
Engineer); NES = NESPAK (Owner’s Engineer); RE2 = Renewable Resources Ltd. (To be submitted together with
(Owner’s Engineer)] the revised/completed
documents)
行相应的审查。
10. 1 KE 3 Noted, closed
11. 1 NES 4 Please refer to our comments on design calculation E113S-LAN- Noted
T0303-CS-01.
12. 1 NES 5 HEI confirmation to comply with Engineer’s comment is noted. Noted,HEI design as
per E113S-LAN-D0302
13. 1 NES 6 HEI confirmation to comply with Engineer’s comment is noted. Noted,HEI design as
per E113S-LAN-D0302
14. 1 NES 7 Noted.
15. 2 NES 11 Please refer to our comments on design calculation E113S-LAN-
T0303-CS-01.