Revision History 
Rev.  Revision  Issued by  Checked by  Released by  Brief Description 
Date 

Description current Revision 

Owner

Owner’s Engineer:  Contractor:

Project:  
TAMBAK LOROK COMBINED CYCLE 
POWER PLANT BLOCK 3 PROJECT 
WITH NET DEPENDABLE CAPACITY OF 600 – 850 MW. 
SEMARANG – CENTRAL JAVA
Subject:  Commissioning ITPL - Steam Bypass System

Issue Purpose:  Responsible Dept:
PE-ACE
Originator: 

Originator Document no:  Document Status: Originator Rev:  0


1GP024029 Released
Project Document No.: Rev:  Sheet.:

TBL/31/E/153b---001/SP/008 0 0 / 15

Issue date:  2022-03-18

Information Class, if applicable, on pg. 1 et sqq


Space for Stamp: IP/OE
RETURN CODE

Revision History
Rev. Revision Issued by Checked by Released by Brief Description
Date
A 05-12-2019 N. MEKALA S. SUGUMARAN B. Baskaran
B 05-08-2021 P. Annegowda S. SUGUMARAN B. Baskaran Customer comments
incorporated

0 Description current Revision


FINAL ISSUE

Owner

Owner’s Engineer: Contractor:

Project:
TAMBAK LOROK COMBINED CYCLE
POWER PLANT BLOCK 3 PROJECT
WITH NET DEPENDABLE CAPACITY OF 600 – 850 MW.
SEMARANG – CENTRAL JAVA
Subject: Commissioning ITPL - Steam Bypass System

Issue Purpose: Responsible Dept.:

Originator:

Originator Document no: 1GP024029 Document Status: Originator Rev: 0


Released
Project Document No.: Rev: Sheet.:

TBL/31/E/153b---001/SP/008 1/12

Issue date:

© COPYRIGHT 2022 General Electric Company Non-Public


All rights reserved. The information herein is Proprietary and Technically Exclusive content that is solely owned by General Electric Company
and/or its affiliates. Thus, it is being provided with the explicit expectation of restricted and privileged use. All recipients of this information shall be
deemed to have agreed not to make duplications, reproductions of any nature by any means, modifications, disclosures, or use any portion of this
material; except as is expressly authorized in writing by the General Electric Company, and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
Released

This ITPL has to be issued for each unit separately.

The first two pages of this document are only needed for the correct handling of this template file inside the PPDM.

To use it on site please take the word file (.docx) attached to this document (or inside PPDM tool).
Remove the first two pages by highlighting (selecting) the content starting from the title on the first page until the last
word of this second page and press the delete button. The current page 3 will then become the front page of the
relevant ITPL.

Before printing the file ensure the front page is correctly filled and that the GE Document Code (already prepared in
the footer) is adjusted with the three-digit project mnemonic and if needed the unit numbering and the last three-digit
continuous numbering (for more details about GE document code refer to GAS/00/E/02a----002/IS/013).

Ensure that all headers and footers on each page are complete and contain the correct page numbers, date and
document codes.

The attachment (if used) contains a list of all sub-item KKS’ belonging to the scope of this ITPL. For multi-unit plants
the list contains all KKS’ across all units. When issuing a unit specific ITPL the other units KKS’s shall be deleted from
the list.

GE POWER Identification Number: Rev. Date Lang. Sheet


Gas Power Systems 1GP024029 0 2022-03-18 en 2/15
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate
affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
System Name: Steam Bypass System
Name of the System / Item covered by this ITPL

System KKS / Unit: LBF, MAN20, MAN40

Document Type: Commissioning Inspection & Test Plan


Commissioning ITPL

Projects and Customer’s Information:

TAMBAK LOROK COMBINED CYCLE


POWER PLANT BLOCK 3 PROJECT
WITH NET DEPENDABLE CAPACITY OF 600 – 850 MW.
SEMARANG – CENTRAL JAVA
Space for Stamping (Review and Validation status)

<This might comprise of:


Review and Validation information from GE, Customer, third party authorities ….
space for stamps …>

Contractual document designation:

Use this space for the contractual document designation if needed. Otherwise keep empty and delete this text.

The inspection and test plan does not release the subcontractor / manufacturer from his obligation to take all steps necessary to ensure that
the requirements stipulated in drawings and specifications are fulfilled for the product concerned.
GE POWER GE Document Code Rev. Date Lang. Sheet
Gas Power Systems TBL/31/E/153b---001/SP/008 0 en 3/15
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate
affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
TABLE OF CONTENTS:
SAFETY SYMBOLS ........................................................................................................................................................ 5
GENERAL ......................................................................................................................................................................... 6
PLANT CONDITIONS ...................................................................................................................................................... 7
PRECOMMISSIONING TEST FOR MEASURMENT CIRCUIT................................................................................... 7
PRECOMMISSIONING AND START-UP TESTS FOR APPARATUS (PIPE SYSTEMS, TANKS AND
HEAT EXCHANGERS) .................................................................................................................................................... 8
PRECOMMISSIONING AND START-UP TESTS FOR EQUIPMENT (AGGREGATES)......................................... 8
VISUAL INSPECTION ..................................................................................................................................................... 9
COLD COMMISSIONING OF FUNCTION GROUP / SEQUENCER CONTROL ...................................................... 9
PROTECTION TEST ........................................................................................................................................................ 9
INITIAL START OF SYSTEM ......................................................................................................................................... 9
OPTIMIZATION AND FINAL TESTS ............................................................................................................................. 9
AFTER COMMISSIONING ............................................................................................................................................ 10
ATTACHMENT ............................................................................................................................................................... 11

The inspection and test plan does not release the subcontractor / manufacturer from his obligation to take all steps necessary to ensure that
the requirements stipulated in drawings and specifications are fulfilled for the product concerned.
GE POWER GE Document Code Rev. Date Lang. Sheet
Gas Power Systems TBL/31/E/153b---001/SP/008 0 en 4/15
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate
affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
SAFETY SYMBOLS

The User must understand the following symbols used within this document:

DANGER

Danger indicates an imminently hazardous situation that if not avoided,


will result in death or serious injury. This signal word is to be limited to the most
extreme situations.

WARNING
Warning indicates a potentially hazardous situation that if not avoided,
could result in death or serious injury.

CAUTION

Caution indicates a potentially hazardous situation that if not avoided,


may result in minor or moderate injury.
It may also be used to alert against unsafe practices.

Note
Note indicates an important instruction or the best practices
It may also be used to alert against mechanical damage to the equipment

The inspection and test plan does not release the subcontractor / manufacturer from his obligation to take all steps necessary to ensure that
the requirements stipulated in drawings and specifications are fulfilled for the product concerned.
GE POWER GE Document Code Rev. Date Lang. Sheet
Gas Power Systems TBL/31/E/153b---001/SP/008 0 en 5/15
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate
affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1) Performed by B = GE or GE’s representative unit H = Hold point (observe notification period) Q = Q record to K
K = Customer or his representative
2) Acceptance by L = Erection Contractor M = Witness point (observe notification period) R = Internal Record
S = Official acceptance authority
3) Q – Record U = Material supplier, supplier ext. products and ext. processes Y = Internal test C = Record in Com. Record Set
System Name
Inspection and Test Plan Steam Bypass System
Q Activities Step Completed
No. Description Procedure Record Remarks
1) 2) 3) Date / Signature

1
GENERAL

1.1 Make sure the general and project specific environmental aspects are known - -
and observed. Y

1.2 Make sure that all tests are carried out in accordance with the specified - -
regulations and requirements. Y

1.3 Make sure that the safety requirements are observed as mentioned in the TBL/00/P/CSR-------/CM/001 -
project specific commissioning safety rules. If other regional requirements have B Y
to be considered follow the more strict one.
1.4 Ensure that commissioning permit to work rules are known and followed. TBL/00/P/PTW--------/CM/001 -
B K*

1.5 Check that system is turned over from erection to commissioning, that TBL/00/P/TP-- ------/CM/001 -
“Notification of Change Certificate” (NOCC) is issued and that “Energisation B Y
Clearence Protocol” (ECP) is filled out before first energisation.
1.6 Check system readiness and that preceding activities are completed and that - -
relevant open items from turn over are closed. B K*

1.7 Ensure handling of inspection & test documentation is followed. GAS/00/E/150B---001/TP/200 -


B Y

1.8 Verify the completeness of the documentation as mentioned in the ITPL, collect - -
all relevant drawings and documents at the latest revision. B K*

1.9 Verify the needs of special tools. Make sure they are ordered / organised and - -
verify if the calibration of entire test equipment is certified and valid. B Y

1.10 Verify the needs of equipment original supplier or official authority. Ensure the - -
arrangement in time. Y

*Note: Activities marked with “K&M” in Q- Activities column 2 will be coordinated/informed during the daily site commissioning planning meeting only

The inspection and test plan does not release the subcontractor / manufacturer from his GE POWER GE Document Code Rev. Date Lang. Sheet
obligation to take all steps necessary to ensure that the requirements stipulated in TBL/31/E/153b---001/SP/008 0 en 6/15
drawings and specifications are fulfilled for the product concerned. Gas Power Systems
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1) Performed by B = GE or GE’s representative unit H = Hold point (observe notification period) Q = Q record to K
K = Customer or his representative
2) Acceptance by L = Erection Contractor M = Witness point (observe notification period) R = Internal Record
S = Official acceptance authority
3) Q – Record U = Material supplier, supplier ext. products and ext. processes Y = Internal test C = Record in Com. Record Set
System Name
Inspection and Test Plan Steam Bypass System
Q Activities Step Completed
No. Description Procedure Record Remarks
1) 2) 3) Date / Signature

2
PLANT CONDITIONS
2.1 Low voltage power supply available - - Y
2.2 Control voltage available - - Y
2.3 Control system ready: - -
• The control cubicles are energized
• The measuring circuits are installed, connected and checked out (wiring check
resp. Loop check done)
B Y
• The control circuits and the signal processing is completed
• Control room equipment is ready (Hmi, alarm recorder, communication)
• Check of communication interface between field equipment / local control
system and DCS
2.4 Instrument air system operational - - B K*
2.5 Hydraulic control oil system operational - - B K*
2.6 Main condensate system operational - - B K*
2.7 Steam system depressurized and cold, turbine tripped - - B K*
2.8 Gt off / steam isolation valves closed - - B K*

3
PRECOMMISSIONING TEST FOR MEASURMENT CIRCUIT
3.1 Precommissioning tests for temperature transmitter GAS/00/E/153B---001/TP/203 GAS/00/E/153B---001/TQ/200 Signals listed in
B K* Q attachment
3.2 Precommissioning tests for pressure transmitter GAS/00/E/153B---001/TP/201 GAS/00/E/153B---001/TQ/200 Signals listed in
B K* Q attachment
3.3 Precommissioning tests for steam flow meter GAS/00/E/153B---001/TP/207 GAS/00/E/153B---001/TQ/214 Signals listed in
B K* Q attachment

3.4 Precommissioning tests for level switch GAS/00/E/153B---001/TP/202 GAS/00/E/153B---001/TQ/201 Signals listed in
B K* Q attachment
*Note: Activities marked with “K&M” in Q- Activities column 2 will be coordinated/informed during the daily site commissioning planning meeting only

The inspection and test plan does not release the subcontractor / manufacturer from his GE POWER GE Document Code Rev. Date Lang. Sheet
obligation to take all steps necessary to ensure that the requirements stipulated in TBL/31/E/153b---001/SP/008 0 en 7/15
drawings and specifications are fulfilled for the product concerned. Gas Power Systems
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1) Performed by B = GE or GE’s representative unit H = Hold point (observe notification period) Q = Q record to K
K = Customer or his representative
2) Acceptance by L = Erection Contractor M = Witness point (observe notification period) R = Internal Record
S = Official acceptance authority
3) Q – Record U = Material supplier, supplier ext. products and ext. processes Y = Internal test C = Record in Com. Record Set
System Name
Inspection and Test Plan Steam Bypass System
Q Activities Step Completed
No. Description Procedure Record Remarks
1) 2) 3) Date / Signature

4
PRECOMMISSIONING AND START-UP TESTS FOR
APPARATUS (PIPE SYSTEMS, TANKS AND HEAT
EXCHANGERS)
4.1 Visually inspect the piping system and verify: P&ID -
• Completeness according to P&ID TBL/31/E/LBF-----EN/FD/001
• Arrangement of the pipes: e.g. location, pipe slope, pipe diameter and TBL/31/E/MAN40---EN/FD/001
possibility to drain and vent the pipe line TBL/31/E/MAN20---EN/FD/001
• Hangers and supports operational: check the possibility to accommodate B Y
thermal expansion of the system
• Flow direction of installed devices (valves, flow meters, orifices)
• Thermal insulation or touch protection is sufficient for initial operation
• Access to all equipment used for operation
4.2 Verify earthing equipment is connected - -
B Y
4.3 Verify operation configuration of the system: - -
• Apparatus, devices and instrumentation (sampling probe on stack nozzle) are B Y
installed as required for initial start of system
4.4 Verify the correctness of orifices (by measuring the orifice hole diameter) - GAS/00/E/153B---001/TQ/206 Equipment listed in
B Y Q
attachment

5
PRECOMMISSIONING AND START-UP TESTS FOR
EQUIPMENT (AGGREGATES)
5.1 Precommissioning checks for hydraulic operated control valve. Check for proper GAS/00/E/153B---001/TP/214 GAS/00/E/153B---001/TQ/218 Equipment listed in
function, adjust the limit / torque switch (close/open) and verify correct indication B Y Q attachment

5.2 Precommissioning checks for hydraulic or pneumatic operated shut-off valve. GAS/00/E/153B---001/TP/212 GAS/00/E/153B---001/TQ/208 Equipment listed in
Check for proper function, adjust the limit / torque switch (close/open) and verify B Y Q attachment
correct indication
5.3 Precommissioning checks for motorized valve (incl motor space heater). Check GAS/00/E/153B---001/TP/216 GAS/00/E/153B---001/TQ/205 Equipment listed in
for proper function, adjust the limit / torque switch (close/open) and verify correct attachment
B Y Q
indication.

The inspection and test plan does not release the subcontractor / manufacturer from his GE POWER GE Document Code Rev. Date Lang. Sheet
obligation to take all steps necessary to ensure that the requirements stipulated in TBL/31/E/153b---001/SP/008 0 en 8/15
drawings and specifications are fulfilled for the product concerned. Gas Power Systems
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1) Performed by B = GE or GE’s representative unit H = Hold point (observe notification period) Q = Q record to K
K = Customer or his representative
2) Acceptance by L = Erection Contractor M = Witness point (observe notification period) R = Internal Record
S = Official acceptance authority
3) Q – Record U = Material supplier, supplier ext. products and ext. processes Y = Internal test C = Record in Com. Record Set
System Name
Inspection and Test Plan Steam Bypass System
Q Activities Step Completed
No. Description Procedure Record Remarks
1) 2) 3) Date / Signature

6
VISUAL INSPECTION
6.1 Inspect and verify all manually operated equipment (valve, local instruments - -
etc.) is lubricated, clean and functional B K*

7
COLD COMMISSIONING OF FUNCTION GROUP /
SEQUENCER CONTROL
7.1 Check implementation of functional requirements logic and control TBL/31/E/LBF-----EN/LO/001 - Mark discrepancies
TBL/31/E/MAN20---EN/LO/001 as red correx and
B K*
TBL/31/E/MAN40---EN/LO/001 inform mechanical
systems engineering

8
PROTECTION TEST
8.1 Check of steam bypass trip signals TBL/31/E/003b---001/DO/001 - B K*

9
INITIAL START OF SYSTEM
9.1 Exclusion zone during start up: - -
During initial start up activities, an appropriate exclusion zone with limited
access shall be foreseen. Special attention must be paid during the first start Y
ups of the system until the system has seen stable operating condition
9.2 Prepare system for cleaning (Validation blow) according procedure TBL/31/E/150b---001/CL/212 - B Y
9.3 Perform system cleaning according procedure TBL/31/E/150b---001/CL/212 GAS/00/E/153b---001/TQ/302 B K* Q
9.4 Check systems after cleaning. Verify all cleaning provisional’s are removed and TBL/31/E/150b---001/CL/212 -
B K*
systems are reinstated for start up and normal operation

10
OPTIMIZATION AND FINAL TESTS
10.1 Verify system behavior during plant nominal load operation TBL/31/E/LBF-----EN/DM/001 -
TBL/31/E/MAN20---EN/DM/001 B K*
TBL/31/E/MAN40---EN/DM/001

*Note: Activities marked with “K&M” in Q- Activities column 2 will be coordinated/informed during the daily site commissioning planning meeting only

The inspection and test plan does not release the subcontractor / manufacturer from his GE POWER GE Document Code Rev. Date Lang. Sheet
obligation to take all steps necessary to ensure that the requirements stipulated in TBL/31/E/153b---001/SP/008 0 en 9/15
drawings and specifications are fulfilled for the product concerned. Gas Power Systems
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
1) Performed by B = GE or GE’s representative unit H = Hold point (observe notification period) Q = Q record to K
K = Customer or his representative
2) Acceptance by L = Erection Contractor M = Witness point (observe notification period) R = Internal Record
S = Official acceptance authority
3) Q – Record U = Material supplier, supplier ext. products and ext. processes Y = Internal test C = Record in Com. Record Set
System Name
Inspection and Test Plan Steam Bypass System
Q Activities Step Completed
No. Description Procedure Record Remarks
1) 2) 3) Date / Signature

11
AFTER COMMISSIONING
11.1 Check the completeness of Q.A. documentation - - B Y
11.2 Finalize red correx - - B K* C
11.3 "Make sure this I & T plan as well as the test certificates and red correx - -
belonging to it are signed by the commissioning manager.

Name: _______________________________ B Y

Date: ____________ Sign.: _____________

*Note: Activities marked with “K&M” in Q- Activities column 2 will be coordinated/informed during the daily site commissioning planning meeting only

The inspection and test plan does not release the subcontractor / manufacturer from his GE POWER GE Document Code Rev. Date Lang. Sheet
obligation to take all steps necessary to ensure that the requirements stipulated in TBL/31/E/153b---001/SP/008 0 en 10/15
drawings and specifications are fulfilled for the product concerned. Gas Power Systems
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
System Name
Inspection and Test Plan AutoField for: Item or System Name
KKS Function Designation Component Step Test certificate Checked Remarks

ATTACHMENT

TEMPERATURE BEFORE HP BYPASS STEAM CONTROL


31LBA55CT001A TIS TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE BEFORE HP BYPASS STEAM CONTROL


31LBA55CT001B TIS TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE AFTER HP BYPASS STEAM CONTROL


31LBC15CT001A TICZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE AFTER HP BYPASS STEAM CONTROL


31LBC15CT001B TICZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE AFTER HP BYPASS STEAM CONTROL


31LBC15CT001C TICZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE AFTER IP BYPASS STEAM CONTROL


31MAN40CT001A TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200 P&ID:
VALVE
TBL/31/E/LBF-----EN/FD/001
TBL/31/E/MAN40---EN/FD/001
TEMPERATURE AFTER IP BYPASS STEAM CONTROL TBL/31/E/MAN20---EN/FD/001
31MAN40CT001B TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE AFTER IP BYPASS STEAM CONTROL


31MAN40CT001C TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE BEFORE IP BYPASS STEAM CONTROL


31MAN40CT005A TIS TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE BEFORE IP BYPASS STEAM CONTROL


31MAN40CT005B TIS TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE IP BYPASS STEAM CONTROL VALVE


31MAN40CT011A TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
CONDENSER INLET

TEMPERATURE IP BYPASS STEAM CONTROL VALVE


31MAN40CT011B TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
CONDENSER INLET

GE POWER GE Document Code Rev. Date Lang. Sheet


Gas Power Systems _ _ _/_ _/_/_ _ _ _ _ _ _COM/SP/_ _ _ en 11/15
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
System Name
Inspection and Test Plan AutoField for: Item or System Name
KKS Function Designation Component Step Test certificate Checked Remarks

TEMPERATURE IP BYPASS STEAM CONTROL VALVE


31MAN40CT011C TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
CONDENSER INLET

TEMPERATURE IP BYPASS STEAM CONTROL VALVE


31MAN40CT021A TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
CONDENSER INLET

TEMPERATURE IP BYPASS STEAM CONTROL VALVE


31MAN40CT021B TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
CONDENSER INLET

TEMPERATURE IP BYPASS STEAM CONTROL VALVE


31MAN40CT021C TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
CONDENSER INLET

TEMPERATURE DRAIN POT LP STEAM BEFORE BYPASS


31LBH20CT201 TISA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
SHUTOFF VALVE

TEMPERATURE AFTER LP BYPASS STEAM CONTROL


31MAN20CT001A TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE
P&ID:
TEMPERATURE AFTER LP BYPASS STEAM CONTROL TBL/31/E/LBF-----EN/FD/001
31MAN20CT001B TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE TBL/31/E/MAN40---EN/FD/001
TBL/31/E/MAN20---EN/FD/001
TEMPERATURE AFTER LP BYPASS STEAM CONTROL
31MAN20CT001C TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE BEFORE LP BYPASS STEAM CONTROL


31MAN20CT005A TISA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE BEFORE LP BYPASS STEAM CONTROL


31MAN20CT005B TISA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
VALVE

TEMPERATURE LP BYPASS STEAM CONTROL VALVE


31MAN20CT011A TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
CONDENSER INLET

TEMPERATURE LP BYPASS STEAM CONTROL VALVE


31MAN20CT011B TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
CONDENSER INLET

TEMPERATURE LP BYPASS STEAM CONTROL VALVE


31MAN20CT011C TISZA TRANSMITTER 3.1 GAS/00/E/153B---001/TQ/200
CONDENSER INLET

GE POWER GE Document Code Rev. Date Lang. Sheet


Gas Power Systems _ _ _/_ _/_/_ _ _ _ _ _ _COM/SP/_ _ _ en 12/15
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
System Name
Inspection and Test Plan AutoField for: Item or System Name
KKS Function Designation Component Step Test certificate Checked Remarks

31MAN40CP001A PIS PRESSURE AFTER IP BYPASS STEAM CONTROL VALVE TRANSMITTER 3.2 GAS/00/E/153B---001/TQ/200

31MAN40CP001B PIS PRESSURE AFTER IP BYPASS STEAM CONTROL VALVE TRANSMITTER 3.2 GAS/00/E/153B---001/TQ/200

31MAN20CP001A PIS PRESSURE AFTER LP BYPASS STEAM CONTROL VALVE TRANSMITTER 3.2 GAS/00/E/153B---001/TQ/200

31MAN20CP001B PIS PRESSURE AFTER LP BYPASS STEAM CONTROL VALVE TRANSMITTER 3.2 GAS/00/E/153B---001/TQ/200

31LBF51CF001A FIC FLOW WATER INJECTION HP BYPASS TRANSMITTER 3.3 GAS/00/E/153B---001/TQ/200

31LBF51CF001B FIC FLOW WATER INJECTION HP BYPASS TRANSMITTER 3.3 GAS/00/E/153B---001/TQ/200


P&ID:
TBL/31/E/LBF-----EN/FD/001
31MAN41CF001A FIC FLOW WATER INJECTION IP BYPASS TRANSMITTER 3.3 GAS/00/E/153B---001/TQ/200
TBL/31/E/MAN40---EN/FD/001
TBL/31/E/MAN20---EN/FD/001
31MAN41CF001B FIC FLOW WATER INJECTION IP BYPASS TRANSMITTER 3.3 GAS/00/E/153B---001/TQ/200

31MAN21CF001A FIC FLOW WATER INJECTION LP BYPASS TRANSMITTER 3.3 GAS/00/E/153B---001/TQ/200

31MAN21CF001B FIC FLOW WATER INJECTION LP BYPASS TRANSMITTER 3.3 GAS/00/E/153B---001/TQ/200

31MAN20CL201 LSA LEVEL DRAIN LP BYPASS STEAM CONTROL VALVE SWITCH 3.4 GAS/00/E/153B---001/TQ/201

ORIFICE DRAIN HP STEAM BEFORE BYPASS CONTROL


31LBA55BP201 ORIFICE 4.4 GAS/00/E/153B---001/TQ/206
VALVE

31LBH40BP201 ORIFICE DRAIN IP BYPASS STEAM SHUTOFF VALVE ORIFICE 4.4 GAS/00/E/153B---001/TQ/206

GE POWER GE Document Code Rev. Date Lang. Sheet


Gas Power Systems _ _ _/_ _/_/_ _ _ _ _ _ _COM/SP/_ _ _ en 13/15
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
System Name
Inspection and Test Plan AutoField for: Item or System Name
KKS Function Designation Component Step Test certificate Checked Remarks

31MAN40BP201 ORIFICE DRAIN IP BYPASS STEAM CONTROL VALVE ORIFICE 4.4 GAS/00/E/153B---001/TQ/206

ORIFICE DRAIN LP STEAM BEFORE BYPASS SHUTOFF


31LBH20BP201 ORIFICE 4.4 GAS/00/E/153B---001/TQ/206
VALVE

31MAN20BP201 ORIFICE DRAIN LP BYPASS STEAM CONTROL VALVE ORIFICE 4.4 GAS/00/E/153B---001/TQ/206

31MAN20BP211 ORIFICE DRAIN LP BYPASS STEAM CONTROL VALVE ORIFICE 4.4 GAS/00/E/153B---001/TQ/206

HYDRAULIC
31LBF50AA001 HP BYPASS STEAM CONTROL VALVE CONTROL 5.1 GAS/00/E/153B---001/TQ/218
VALVE
HYDRAULIC
31LBF51AA002 HP BYPASS WATER INJECTION CONTROL VALVE CONTROL 5.1 GAS/00/E/153B---001/TQ/218
VALVE
P&ID:
HYDRAULIC
TBL/31/E/LBF-----EN/FD/001
31MAN40AA002 IP BYPASS STEAM CONTROL VALVE CONTROL 5.1 GAS/00/E/153B---001/TQ/218
TBL/31/E/MAN40---EN/FD/001
VALVE
TBL/31/E/MAN20---EN/FD/001
HYDRAULIC
31MAN41AA001 IP BYPASS WATER INJECTION CONTROL VALVE CONTROL 5.1 GAS/00/E/153B---001/TQ/218
VALVE
HYDRAULIC
31MAN20AA002 LP BYPASS STEAM CONTROL VALVE CONTROL 5.1 GAS/00/E/153B---001/TQ/218
VALVE
HYDRAULIC
31MAN21AA001 LP BYPASS WATER INJECTION CONTROL VALVE CONTROL 5.1 GAS/00/E/153B---001/TQ/218
VALVE
HYDRAULIC
31LBF51AA001 HP BYPASS WATER INJECTION SHUTOFF VALVE SHUTOFF 5.2 GAS/00/E/153B---001/TQ/208
VALVE
HYDRAULIC
31MAN40AA001 IP BYPASS STEAM SHUTOFF VALVE SHUTOFF 5.2 GAS/00/E/153B---001/TQ/208
VALVE
HYDRAULIC
31MAN41AA002 IP BYPASS WATER INJECTION SHUTOFF VALVE SHUTOFF 5.2 GAS/00/E/153B---001/TQ/208
VALVE

GE POWER GE Document Code Rev. Date Lang. Sheet


Gas Power Systems _ _ _/_ _/_/_ _ _ _ _ _ _COM/SP/_ _ _ en 14/15
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22
System Name
Inspection and Test Plan AutoField for: Item or System Name
KKS Function Designation Component Step Test certificate Checked Remarks

HYDRAULIC
31MAN20AA001 LP BYPASS STEAM SHUTOFF VALVE SHUTOFF 5.2 GAS/00/E/153B---001/TQ/208
VALVE
HYDRAULIC
31MAN21AA002 LP BYPASS WATER INJECTION SHUTOFF VALVE SHUTOFF 5.2 GAS/00/E/153B---001/TQ/208
VALVE
DRAIN VALVE HP STEAM BEFORE BYPASS CONTROL
31LBA55AA201 MOV 5.3 GAS/00/E/153B---001/TQ/205
VALVE

DRAIN VALVE HP STEAM BEFORE BYPASS CONTROL


1LBA55AA202 MOV 5.3 GAS/00/E/153B---001/TQ/205 P&ID:
VALVE
TBL/31/E/LBF-----EN/FD/001
TBL/31/E/MAN40---EN/FD/001
31LBH40AA201 DRAIN VALVE IP BYPASS STEAM SHUTOFF VALVE MOV 5.3 GAS/00/E/153B---001/TQ/205 TBL/31/E/MAN20---EN/FD/001

31LBH40AA202 DRAIN VALVE IP BYPASS STEAM SHUTOFF VALVE MOV 5.3 GAS/00/E/153B---001/TQ/205

31MAN20AA202 DRAIN VALVE LP BYPASS STEAM CONTROL VALVE MOV 5.3 GAS/00/E/153B---001/TQ/205

DRAIN VALVE LP STEAM BEFORE BYPASS SHUTOFF


31LBH20AA202 MOV 5.3 GAS/00/E/153B---001/TQ/205
VALVE

GE POWER GE Document Code Rev. Date Lang. Sheet


Gas Power Systems _ _ _/_ _/_/_ _ _ _ _ _ _COM/SP/_ _ _ en 15/15
© COPYRIGHT 2022 General Electric Company Non-Public
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

ReleasedforConstruction-setbyS.SUGUMARANon21-Mar-22