1. Method Statement
Procedure:
1. Description of Work
This Method Statement and Risk Assessment establishes the working steps and sequences during the
Chemical Cleaning of Fuel Gas Pipeline at UEN, H phase 4.
The purpose of method statement is to provide a detailed description of the methodology (cleaning and
removing of rust, stains and other contamination from natural gas pipeline (carbon steel pipes), to improve
the appearance of welding/work piece and restores the materials natural corrosion resistance which has been
compromised as a result of the welding process).
The chemical cleaning will be done by Monophase Circulation method which is a single fill method in three
loops.
Scope
The areas
• UEN at phase 4 - Aweer power station H Phase project
Relevant Reference and Document:
Method statement & Risk Assessment for Chemical Cleaning of Fuel gas line at
UEN by Mono-phase Circulation method 3761800008-E-08-M-E-65750_A
Procedure (Piping).
• General Layout.
• HSE Plan.
• Inspection and Test Plan (ITP) / Field Quality Plan (FQP). 376180008-U-OO-M-Q-60008-E
• VOL II – GO5.1 - Mechanical Equipment and Piping.
• VOL V – AO5_Specimen Project Procedure Manual.
• VOL II - G05.6 - Inspection and Testing
• VOL II - G05.5 - Corrosion Protection and Painting
• Hydraulic Testing Procedure for Balance of Plant - BOP -3761800008-U-31-M-P-65762
• DEWA SP-06 Health and Safety Procedures
• Dubai Municipality Code of Construction Safety Practice.
• HSE Technical Guidelines from Dubai Municipality.
2. CHEMICAL USED
DEGREASING PHASE:
2.1
TERGITOL™ NP-10 Surfactant / TERGITOL™ NP-6 Surfactant.
Dosing Percentage: 0.05%.
ACID PHASE:
2.2
Acid Inhibitor { EC-ArmoHib-CI-31}
Dosing Percentage: 0, 1%
Citric Acid
Dosing Percentage: 3% (w/w).
Ammonium Biflouride
Dosing Percentage: 0.5 - 1% (w/w).
PASSIVATION PHASE:
2.3
Liquid Ammonia
Dosing Percentage: Until pH in the range of 8.2 to 9.5
Sodium Nitrite
Dosing Percentage: 0.3% (w/w).
3. PREPARATIONS
The UEN internal piping testing packages are splitted into 7Nos of loops in each unit
3.1.
61/62/63 as shown in attachment no.1.
The loop No. 1,2,3,4,7 is installed with temporary support anchored to the ground to detach
3.2 the spool from its original position on skid , same arrangement shall be used. And loop
no.5 & 6 will be dismantled and chemical cleaned on ground.
Page 4 of 249
Method statement & Risk Assessment for Chemical Cleaning of Fuel gas line at
UEN by Mono-phase Circulation method 3761800008-E-08-M-E-65750_A
The loop No. 1,2,3,4,7 will be placed at same elevation on the support and locked with
3.3
temporary welded support to avoid movement of spool during chemical cleaning
Using the ISO Metric Drawing are refered to Identify the systems to be cleaned. The loops are
3.4
marked in general layout – Attachment No.1.
3.5 Line walk-down with E/E to identify the system to be cleaned and each loop
3.6 All the Fabrication / welding work & Hydro testing should be done prior to chemical cleaning.
All the required Isolation of equipment’s such as instruments like flow transmitter, sensors etc.
3.7
& All NRV to be removed and that shall identify during the line walk.
3.8 Temporary spools, adaptors etc. will be fabricated and installed prior to cleaning.
3.9 Organize electric supply for cleaning equipment – 380V-63/32A & 220V-16A and diesel required
Prepare the Area where equipment to be kept. Layout attached showing the proposed location to be
3.10
used during the cleaning process for each loop. Attachment No.1.
Equipment list including circulation pumps, waste tanks with capacity of each, lab equipment…etc.
3.11
deployed to the working location, photos of Equipment are attached as per Attachment no 01
Mobilization of equipment’s to work location after getting all the required permits from E/E as
3.12
applicable
3.13 Offloading the materials and equipment’s should be done by Trained and certified Riggers.
All lifting equipment’s used for the activity are inspected and certified and color coded by approved
3.14
TPI.
3.15 Only trained/inducted employees will work on the project with in-house training certificate
Barrication to be applied on the working area including adequate number of signage’s identifying
3.16
the process and the nature of the work.
3.17 Wherever required PTW shall be applied for the activity.
The required amount of water will be arranged and Pumped directly to chemical mixing tank and
3.18
then to line.
3.19 110% Tray to be placed down side of the diesel tanks.
3.20 Adequate number of fire extinguisher to be placed in area (Foam, Water & CO2 types).
The work area shall be adequately illuminated using appropriate lighting arrangement during the
3.21
night shift.
3.22 Appropriate fall protection shall be used while working at height and life line/proper.
3.23 Chemical cleaning shall be done with Operation Pressure : 3-4 Bars
4. CONDITION OF PIPELINES BEFORE CHEMICAL CLEANING
4.1. All pipelines should be hydro tested and certified before the start of the cleaning.
5.4. No other works can be carried out in the exclusion area of chemical cleaning during the treatment.
The project activities shall comply with the requirements of Project HSE Plan and the applicable
5.5.
HSE requirements of contractor and company.
5.6. Only authorized person to be allowed at the same area during treatment.
5.7. First aid equipment, special for this job, will be on site during the whole operation.
Page 5 of 249
Method statement & Risk Assessment for Chemical Cleaning of Fuel gas line at
UEN by Mono-phase Circulation method 3761800008-E-08-M-E-65750_A
5.8. All safety precautions are in force at all times both during the cleaning process,
5.9. All local medical centers should be informed and equipped to give medical aid in case of accidents.
5.10. E/E and ESC PTW system to be followed.
Before starting the activity and during the activity regular checks to be made to prevent any HSE
issue and concerns. The area activity will be barricaded to prevent other workforce entering and
5.11. coming in contact / receiving chemicals from the activities. Check list to be implemented by the
supervisor to check, prevent and mitigate any HSE issue. Barricade to be maintained and monitored
during the activity.
5.12. MSDS shall be available at site for all chemicals employed.
Waste water disposal to be done through a third party licensed waste management company and to
5.13.
be treated under local laws and regulation.
All the necessary precautions shall be taken to avoid burns/harm from chemicals while performing
5.14.
the cleaning works.
All Mandatory PPE identified shall be worn (Safety Helmet, safety shoes, coverall, eye protection,
5.15.
appropriate hand gloves for the task) – Attachment No.02
Any additional PPE’s (Aprons, Face masks, respirators, fall arrestors etc.) shall be worn when
5.16.
required. (Attachment No.: 02).
110 % Capacity tray to be placed under diesel tanks only.
All the chemicals tanks are supplied with a level indicator & made from a compatible materials to
5.17. hold this kind of chemicals (Referred to tank data sheet attachments No. 02) Tanks data sheet is
attached) & all waste storage tanks will be provided with level meter and to be kept outside of the
existing plant.
5.18. During operation, vents should always be kept open.
5.19. LOTO procedure to be applied if required.
5.20. Hard Barrication to be applied around the Auxiliary Boiler during the operation.
5.21 Safety shower & Eye wash to be maintained in the vicinity.
6. Chemical Cleaning Method
6.1. looping Plan
6.1.1 The chemical cleaning will be performed as per the loop shown in (Attachment No.: 01)
Filter skid will be connected to the system during all the cleaning stages including the
6.1.3
pressure test, Flushing, and the chemical cleaning stages.
6.2. Filling
6.2.1 Fill the system with potable water from the water tanker to a 20 m3 mixing tank and
filling the system through the temporary circulation pump.
6.2.2 During filling all the vents are kept open until water has reached the vents.
6.2.3 All return lines are kept closed until all vent lines have given water
6.3. Pressure Test
Prior to the actual cleaning the system is filled with water and a leak test of the
6.3.1
temporary lines.
6.3.2 Pressure testing is used to find leaks in the (temporary) cleaning system. Leaks typically
occur at valves, joints or connections in the system.
Page 6 of 249
Method statement & Risk Assessment for Chemical Cleaning of Fuel gas line at
UEN by Mono-phase Circulation method 3761800008-E-08-M-E-65750_A
The test pressure during a pressure test is normally set to 150 % of the pump shut off
pressure. The operating pressure of the pump during the chemical cleaning is max. 3-
6.3.3 4 bar. The pressure is gradually increased to reach 150% of pump shut off pressure &
the system will be controlled from the main header and out-let valves (As per
Circulation Flow Diagram).
The pressure test to be conducted for all the temporary setup (piping & Hoses) during
6.3.4
the pressure testing.
6.3.5 The Pressure test of the system is performed after the lines are filled and vented to
remove the air.
The Test Shall be 2 hours
6.3.6 Temporary arrangement circuit, will be kept open during the cleaning procedure, by
connecting all the inlet, outlet, and vent points to the mixing tank, considering the
mixing tank is an open tank
6.3.7 A walk down of the system and pumping skid shall be performed.
6.3.8 All temporary lines and all temporary valves shall be checked for leakages, during the
pressure test.
6.3.9 When leakages have been found, shall be repaired after the pressure test. The section(s)
where the leak occurred shall be tested again after the repair.
6.3.10 At the conclusion of the test, the system is carefully depressurized by controlled
releasing of water to the mixing tank or to the effluent storage.
The pump is set to a lower (operating pressure) or will be shutdown.
6.3.11 Refer to attachment 3 - Inspection and test plan (ITP) / Section 2.
6.4. Flushing
Once the leak test and the system was depressurized install the filtration unit starting with a 20
6.4.1 micron filter in the return hose to the chemical mixing / circulation tank to collect the debris and
other foreign particles.
Periodically check the filter in return line for any debris/foreign particles (Every 1 hour filter bags
6.4.2 to be checked).
Some amount of discoloration on filter is acceptable. If required use 10 micron filter also.
6.4.3 Once filter is clean and inspected, Same solution can be used for next step No.: 6.5
The Maximum Flushing Velocity is 2.00 m/s during the flushing only.
6.4.4 - Refer to Pumps data sheet – Attachment No.: 02.5
All debris shall be removed from the system during the flushing.
Flushing Parameters
Temperature :Ambient
Turbidity : visually clear
6.4.5
Time: Every 30 Min.
Solution Samples for testing will be collected from the sampling valve on the return line only.
Filter : Some amount of discoloration is acceptable
Time : Every 1 Hour
6.4.6 Refer to attachment 3 - Inspection and test plan (ITP) / Section 3.
6.5. Degreasing Phase
6.5.1
The One sample piece to be placed in the return/outlet temporary line, and just before mixing tank
A d On the same solution of Step 6.4.3 the concentration of 0.05% of the Degreasing agent
6.5.2
TERGITOL NP-10 Surfactant / TERGITOL NP-6 Surfactant is dosed.
Page 7 of 249
Method statement & Risk Assessment for Chemical Cleaning of Fuel gas line at
UEN by Mono-phase Circulation method 3761800008-E-08-M-E-65750_A
6.5.4 After the degreasing phase the saturation of the solution is checked with a MN test strip.
Same solution can be used for next step.
6.5.5 Sampling location will be from the sampling valve on the return line only.
Every 30 minutes a sample is taken and the concentration of iron and acid to be measured.
6.6.9
Solution Samples for analytical testing will be collected from the sampling valve on the return line
only.
If the iron concentration is stabilized for two subsequent samples with a margin of +/-5%, the
6.6.10
cleaning is finished, but at least 4-6 hours of acid cleaning is done to ensure the cleanliness & all
the analysis value to be graphed.
6.6.11 Solution Samples for analytical testing will be collected from the sampling valve on the return line
only.
6.6.12 After finalizing the acid phase, the solution partially drained if the Iron concentration more than 15
g/l and partially refilled with water to reach a concentration less than 15 g/l Fe.
6.6.13 After finalizing the acid phase, the solution is NOT drained and passivation phase will continue if
the Iron concentration less than 15 g/l.
6.6.14
Acid Phase Parameters
Temperature : 45-55 °C
Page 8 of 249
Method statement & Risk Assessment for Chemical Cleaning of Fuel gas line at
UEN by Mono-phase Circulation method 3761800008-E-08-M-E-65750_A
Acid Concentration : 3% and this will reduce with time. (Every 30 Min.)
6.8 Draining
After the passivation phase lines will be drained from the lowest point under Dry Air pressure to
6.8.1 Corodex waste tank for neutralization and disposal and the draining will be done from the
temporary drain fixed to the temporary spool as showed in the flow diagram & Vent Point can be
utilized as a purging point during the Dry Air blowing.
6.8.2
All drain lines to be connected to Corodex waste collection tanks.
6.8.3
Operation of 24 Hrs. will be applied during chemical cleaning & Draining.
6.8.4
Final Inspection Parameters:
pH (neutralization) : 8.2 – 9.5
Method statement & Risk Assessment for Chemical Cleaning of Fuel gas line at
UEN by Mono-phase Circulation method 3761800008-E-08-M-E-65750_A
Pipe to be blown with compressed oil free dry air to remove any remains of water & Until Dew
Point of -5 C°.
Portable DEW Point meter will be used during the inspection to check the out coming air.
6.9.1
Data Sheet is Attached.
System will be checked at lowest point for any remaining water.
Air Compressor and Dryer data sheet are attached –Attachment No.: 02
Temp humidity meter data sheet attached - Attachment No.: 02
7. QA/QC Requirements :
As per Project Specification
Chemical cleaning inspection and test plan (ITP). Refer to attachment 3.
Third party lab analysis report to be collected prior to waste disposal for DM approval.
A third party contractor approved by Dubai municipality is engaged for collection through tankers and
disposal of the waste following the local rules and regulation.
√ Yes No
Page 10 of 249
Method statement & Risk Assessment for Chemical Cleaning of Fuel gas line at
UEN by Mono-phase Circulation method 3761800008-E-08-M-E-65750_A
Material Safety Data Sheet available (To be attached with MSRA) Yes √ No
Any special handling procedures available (To be attached with MSRA) Yes √ No
Electricity Yes √ No
Lighting Yes √ No For night shift, specifically.
Water Yes √ No
Other Yes √ No Compressed Air
10. Resources:
10.1. Equipment:
Method statement & Risk Assessment for Chemical Cleaning of Fuel gas line at
UEN by Mono-phase Circulation method 3761800008-E-08-M-E-65750_A
Method statement & Risk Assessment for Chemical Cleaning of Fuel gas line at
UEN by Mono-phase Circulation method 3761800008-E-08-M-E-65750_A
12. Applicant responsibility
The Applicant is responsible to ensure that all of the conditions as stated in this MS/RA are implemented
and that the full content of the MS/RA is transferred to and clearly understood by all personnel involved
via a signed tool-box-talk prior to the commencement of the work. A copy of the MS/RA must be
available at the work area at all times for reference and review.
Applicant
Subcontractor
Frederic Shaji
HSE Manager 02.05.2021
Name Signature Date
EPC Contractor
QC Engineer
Name Signature Date
Field Engineer
Name Signature Date
HSE Manager
Name Signature Date
Page 13 of 249
Attachment (A)
Chemical Cleaning Phases Table
Page 16 of 294
Page 14 of 249
Dose
Medium Inspection/Sample
Chemical Cleaning Phases Medium Steps Agent Percentag PH Value Temperature Duration Test Methodology Acceptance Criteria Draining Required
Velocity Collection Intervals
e
Deminarlized or
Phase-01 Water Filling - N/A N/A - Ambient N/A 2 Days N/A N/A N/A No
Potable Water
Deminarlized or
Phase-02 Pressure Testing - N/A N/A Ambient N/A 2 Days Visual Test For Leaks After Two Hours Not Leak Detected No
Potable Water
A- Visually A- Turbidity is Visually clear
Deminarlized or A-Every 30 minutes
Phase-03 Flushing - N/A N/A - Ambient 2.00 m/s 4 Days B- 20 micron filter to be B- Some amout of discoloration is No
Potable Water B- Every 1 hour
installed on the return hose acceptable
Iron Concentration to be
Deminarlized or Marchery Nagel Test Strip For stabilized for 2 measurements
Phsae - 05 Acid Cleaning Step-02 Citric acid 3% - 45- 55 °C 1.2 m/s 1 day Every 30 minutes No
Potable Water Iron (with a maximum of 15g/l). and a
margin of +/-5%
Step-03 Ammonium Bi-fluoride 0.5-1% - HACH DR 900 Every 30 minutes Acid Percentage 3%
Step-04 2.0 – 3.0 PH PAPER Every 30 Minutes PH Value 2.0 - 3.0
Step-01 Liquied Ammonia 8.2 - 9.5 PH PAPER Every 30 minutes PH Value 8.2 - 9.5
Deminarlized or After Passivation
Phsae - 06 Passivation 40- 50 °C 1.2 m/s 1 day
Potable Water Step-02 Sodium Nitrite 0.3% - MN TEST STRIPS FOR NITRITE Every 30 minutes Residual Nitrite > 1500 ppm Completion
Phsae - 07 Draining N/A - N/A N/A N/A N/A N/A 2 Days N/A N/A N/A N/A
Phsae - 08 Air Blowing Nitrogen or Dry Air - N/A N/A N/A N/A N/A 3 Days Dew Point Portable Meter N/A Dew Point of -5 C° N/A
Page 17 of 294
Page 15 of 249
Attachment No.01
Page 18 of 294
Page 16 of 249
Page 17 of 249
Temporary Arrangement
40 Meters
12.6 M 12.6 M 8M
2.6 M
2.6 M
2.5 M
Waste Tank Waste Tank Waste Tank
10 meters
12.6 M 12.6 M 8M
2.5 M
2.6 M
2.6 M
20 Meters
6.2 M
2.6 M
6.2 M
Hoses & Hard Piping Storage Area
2.6 M
Page 23 of 294
Page 18 of 249
Temporary Arrangement
40 Meters
6M
6M 2.5 M
2M 2.6 M
8M
2.6 M
Mixing Tank
2M
2M
2.6 M
Waste Tank
10 meters
Pump 1 Pump 2 6M
2M
2M
2.6 M
2M 2M
Tools Container
Hoses & Fittings Storage Area
Page 24 of 294
Page 19 of 249
Page 25 of 294
Page 20 of 249
FILTER SKID
Page 26 of 294
Page 21 of 249
Page 27 of 294
Page 22 of 249
MIXING TANK – 20 m3
Page 28 of 294
Page 23 of 249
Page 29 of 294
Page 24 of 249
ATTACHMENT NO.01.1
Photograph of Internal
Cleaning of pipes
Page 68 of 294
Page 25 of 249
Page 69 of 294
Page 26 of 249
Page 70 of 294
Page 27 of 249
Page 71 of 294
Page 28 of 249
Page 72 of 294
Page 29 of 249
Page 73 of 294
Page 30 of 249
ATTACHMENT NO.02
Page 74 of 294
Page 31 of 249
Page 75 of 294
Page 32 of 249
Page 76 of 294
Page 33 of 249
Page 77 of 294
Page 34 of 249
Page 78 of 294
Page 35 of 249
Page 79 of 294
Page 36 of 249
Page i Page
Release Date: 80 of 294 2019
11 November Version 2
Page 37 of 249
Page ii Page
Release Date: 81 of 294 2019
11 November Version 2
Page 38 of 249
Page 1 Page
Release Date: 82 of 294 2019
11 November Version 2
Page 39 of 249
Page 2 Page
Release Date: 83 of 294 2019
11 November Version 2
Page 40 of 249
Page 3 Page
Release Date: 84 of 294 2019
11 November Version 2
Page 41 of 249
□
□
□
□
o
o
o
o
o
□
□
□
□
□
□
Page 4 Page
Release Date: 85 of 294 2019
11 November Version 2
Page 42 of 249
Page 5 Page
Release Date: 86 of 294 2019
11 November Version 2
Page 43 of 249
Page 6 Page
Release Date: 87 of 294 2019
11 November Version 2
Page 44 of 249
Page 7 Page
Release Date: 88 of 294 2019
11 November Version 2
Page 45 of 249
Page 8 Page
Release Date: 89 of 294 2019
11 November Version 2
Page 46 of 249
Page 9 Page
Release Date: 90 of 294 2019
11 November Version 2
Page 47 of 249
Page 10 Page
Release Date: 91 of 294 2019
11 November Version 2
Page 48 of 249
Page 11 Page
Release Date: 92 of 294 2019
11 November Version 2
Page 49 of 249
Page 12 Page
Release Date: 93 of 294 2019
11 November Version 2
Page 50 of 249
Page 13 Page
Release Date: 94 of 294 2019
11 November Version 2
Page 51 of 249
Page 14 Page
Release Date: 95 of 294 2019
11 November Version 2
Page 52 of 249
Page 15 Page
Release Date: 96 of 294 2019
11 November Version 2
Page 53 of 249
Page 97 of 294
Page 54 of 249
Page 98 of 294
Page 55 of 249
ATTACHMENT NO.02.1
Page 99 of 294
Page 56 of 249
Al Aweer Power Station ‘H’
Emergency Response Plan Page 1 of 10
Subject For Chemical Cleaning of Fuel Gas Lines
Contents
1. Emergency Response Plan ......................................................................................................2
1.1 Purpose ..............................................................................................................................2
1.2 Designated Positions and Responsibilities ..........................................................................2
1.3 Emergency Response Action Leader (on-site) ....................................................................2
1.4 Emergency Response Priorities ..........................................................................................2
1.5 Action Required...................................................................................................................3
1.6 Have the Following Information Available for the Contact Person........................................3
1.7 Contact Person to Provide the Following Information ..........................................................3
1.8 Corodex Emergency Contact Numbers: ..............................................................................4
1.9 Reporting of Incidents .........................................................................................................4
2. Spill Response Plan..................................................................................................................4
2.1 Classification of Spill ...........................................................................................................4
2.1.1 Minor Spill.....................................................................................................................4
2.1.2 Major Spill.....................................................................................................................4
2.2 Measures taken by Corodex for containing spill...................................................................4
- Chemical transfer pumps will be kept on drip trays. .............................................................4
- Chemical cleaning tanks will be provided with drip trays ......................................................4
- Diesel tanks will be kept in 110 % containment....................................................................4
- Spill kits will be kept near chemical cleaning setup area and waste storage area.................4
- all waste tanks provided will have level gauge .....................................................................4
2.3 In Case of Spillage: .............................................................................................................5
2.3 Chemical Spill Team ...........................................................................................................5
Team Leader ........................................................................................................................5
3. Medical Facilities On-Site .........................................................................................................5
4. Security .................................................................................................................................5
1.1 Purpose
The Emergency Response Plan has three basic functions:
▪ To Protect People
▪ To Protect the Environment
▪ To Protect Property
The aim and the objective is to provide guidelines for effectively controlling and managing
emergencies through a coordinated emergency response plan using CMS personnel, who form
the emergency response team. This is in line with the CMS Environmental Procedures Manual.
1.6 Have the Following Information Available for the Contact Person
1. Nature of the incident – oil/chemical spill? Vehicle accident? Medical emergency? Snake
bite?
2. Name / mode of transport.
3. Products/chemicals involved - names of UN numbers from the MSD Sheets.
4. Location and details of incident.
5. Extent of personal injuries, if any. Include patient’s name, location, time of incident, age,
medical condition, and passport number, contact phone number, fax number (if available)
chemical products, ifany.
6. Caller names, location, telephone number, and fax number (if available.) Caller to stand by
phone for call back.
7. Contacted person will notify the Key Personnel listed in the Emergency Response
Procedure.
Once the decision is taken to medevac personnel they have the authority to make the medical
decisions required to commence medevac procedures. Non-qualified personnel are not permitted
to make medical decisions.
- Spill kits will be kept near chemical cleaning setup area and waste storage area.
- all waste tanks provided will have level gauge.
1. In case of chemical spillage, immediately shut off the system if the leak is due to circulation
of fluid.
2. First priority should be trying to arrest the leak.
3. Simultaneously a team should make use of spill kit and chemical absorbent granules to
absorb fluid which leaked.
4. Then we will collect all the things (cotton rag, sand or soil, etc.) that were contaminated by
the chemical spill and dispose it accordingly with our licensed waste disposal contractor as
per UAE law.
CMS team who will be the in-charge and respond in case of chemical spill incident.
Team Leader:
Fadi Ismail
Shakir Iqbal
Members:
Mustafa
Fouad
Mammoud
Fami
Pramod
Omar
4. Security
Prior to mobilization, CMS Personnel shall be briefed on the present global and local security
situation and advised of any present security level, which may be in force or could be put in force
at the time of operations commencing.
If Personnel are in country and a security level is enforced, it is the responsibility of the Project
Manager to ensure that information is available on a daily basis and to update personnel as and
when it changes. The CMS Project Manager shall liaise with other specialized staff to ensure the
information provided to the field staff is timely and accurate.
It is very important for everyone to understand that it is CMS policy not to compromise the
security and safety of its employees. And that employees, too, have a responsibility to
themselves, to their families and to the company to be constantly vigilant, to be aware of the
security level if any and to be fully versed in the actions that are required for implementation
should the need arise.
Following perssonel,s are well trained for chemical cleaning and pickling passivation activities they are
competent for chemical handling and perform the chemical cleaning activity in a safe and professional manner.
Mikko Toivonen
Following perssonel,s are well trained for chemical spillage clean up and further prevention in a
safe and professional manner.
Mikko Toivonen
Following perssonel,s are well trained for chemical cleaning and pickling passivation activities they are
competent for chemical handling and perform the chemical cleaning activity in a safe and professional manner.
Mikko Toivonen
Following perssonel,s are well trained for chemical spillage clean up and further prevention in a
safe and professional manner.
Mikko Toivonen
ATTACHMENT NO.02.2
MSDS
web: http://www.nfil.in
mailto: bulkfluoride@nfil.in
NAVIN FLUORINE INTERNATIONAL LTD 2nd Floor, Suntek Centre,
37/40, Subhash Road, Vile Parle
(East), Mumbai-400057. India.
PRODUCT SPECIFICATION
Title: AMMONIUM BIFLUORIDE Document No. : NFIL/QC/SPEC/FP/051/00
(NH4HF2) Effective Date : 05/11/2008
Structural Formula :
Sr.
TEST SPECIFICATION
No.
Product Specification:
1 Appearance/ Description White Hygroscopic flakes
Moisture
2 0.30% Max.
NH4HF2
3 98.50% Min.
• Customer should discuss with business unit at bulkfluoride@nfil.in for the other
requirements than specified.
• Analytical Method No. NFIL/QC/WI/FP/051.
Ammonium bifluoride
1. CHEMICAL IDENTITY
Chemical name Ammonium bifluoride
Synonym Ammonium hydrogen difluoride
Chemical Formula H5F2N
2. COMPOSITION / INFORMATION ON INGREDIENTS
Ingredients Name CAS No.: 1341-49-7
EC No: 215-676-4
3. PHYSICAL / CHEMICAL DATA
Boiling Point 239.50C@760 mmHg Vapour Pressure 1 hPa @ 20 0 C
Melting Point 125 deg C Solubility in water 630 G/L water (20°C)
Vapour Density Not available Appearance white solid
Specific Gravity 1.50
pH 3.5 @ 5% solution Odour Slightly pungent
Physical State Solid Other
4. FIRE / EXPLOSION HAZARD DATA
Flammability Non Flammable Flash Point Not applicable.
Auto ignition temperature Not applicable LEL Not available
Explosion sensitivity to impact UEL Not available
Explosion sensitivity to static electricity
Hazardous Combustion products
Hazardous Polymerization Will not occur
Pyrophoric material Corrosive
Organic Peroxide Oxidizer
Explosive material Other
5. STABILITY & REACTIVITY DATA
Chemical Stability Stable under normal temperatures and pressures. Deliquescent
(tending to absorb atmospheric water vapor and become liquid)
Incompatibility Acids, bases
Conditions to avoid Dust generation, moisture, temperatures above 300°C
Hazardous reaction / Hydrogen fluoride gas, ammonia and/or derivatives
decomposition products.
6. HEALTH HAZARD DATA
Effects of exposure / symptoms Eye: Causes eye burns. May cause chemical conjunctivitis and
corneal damage.
Skin: Contact with liquid causes severe burns and ulceration.
May penetrate the skin and cause severe tissue and bone
destruction. May cause skin rash (in milder cases), and cold and
clammy skin with cyanosis or pale color.
Ingestion: Harmful if swallowed. May cause severe and
permanent damage to the digestive tract. May cause kidney
moisture.
Hazard Label
MAHARASHTRA, INDIA
3. HAZARDS IDENTIFICATION
Skin contact: Blistering may occur. Progressive ulceration will occur if treatment is not immediate.
Eye contact: Corneal burns may occur. May cause permanent damage.
Ingestion: Corrosive burns may appear around the lips. Blood may be vomited. There may be bleeding
Inhalation: There may be shortness of breath with a burning sensation in the throat. Exposure may cause
coughing or wheezing.
Skin contact: Remove all contaminated clothes and footwear immediately unless stuck to skin. Drench the
affected skin with running water for 10 minutes or longer if substance is still on skin. Transfer to
Eye contact: Bathe the eye with running water for 15 minutes. Transfer to hospital for specialist examination.
Ingestion: Wash out mouth with water. Do not induce vomiting. Give 1 cup of water to drink every 10
minutes. If unconscious, check for breathing and apply artificial respiration if necessary. If
unconscious and breathing is OK, place in the recovery position. Transfer to hospital as soon
as possible.
Inhalation: Remove casualty from exposure ensuring one's own safety whilst doing so. If unconscious and
breathing is OK, place in the recovery position. If conscious, ensure the casualty sits or lies
down. If breathing becomes bubbly, have the casualty sit and provide oxygen if available.
5. FIRE-FIGHTING MEASURES
Extinguishing media: Suitable extinguishing media for the surrounding fire should be used. Use water spray to
cool
containers.
Protection of fire-fighters: Wear self-contained breathing apparatus. Wear protective clothing to prevent contact
with skin
and eyes.
Personal precautions: Notify the police and fire brigade immediately. If outside keep bystanders upwind and
away from
danger point. Mark out the contaminated area with signs and prevent access to unauthorised
personnel. Do not attempt to take action without suitable protective clothing - see section 8 of
Environmental precautions: Do not discharge into drains or rivers. Contain the spillage using bunding.
Clean-up procedures: Clean-up should be dealt with only by qualified personnel familiar with the specific
substance.
Absorb into dry earth or sand. Transfer to a closable, labelled salvage container for disposal by
an appropriate method.
Handling requirements: Avoid direct contact with the substance. Ensure there is sufficient ventilation of the area.
Do
not handle in a confined space. Avoid the formation or spread of mists in the air.
Storage conditions: Store in cool, well ventilated area. Keep container tightly closed.
Eye protection: Tightly fitting safety goggles. Ensure eye bath is to hand.
State: Liquid
Colour: Colourless
Boiling point/range°C: 68
Autoflammability°C: >500
pH: >10
Routes of exposure: Refer to section 4 of SDS for routes of exposure and corresponding symptoms.
NB: The user's attention is drawn to the possible existence of regional or national regulations
regarding disposal.
ADR / RID
IMDG / IMO
IATA / ICAO
Labelling: 8
S26: In case of contact with eyes, rinse immediately with plenty of water and seek medical advice.
S28: After contact with skin, wash immediately with plenty of water.
S29/56: Do not empty into drains, dispose of this material and its container at hazardous or
S36/37/39: Wear suitable protective clothing, gloves and eye / face protection.
S45: In case of accident or if you feel unwell, seek medical advice immediately (show the label where possible).
S60: This material and its container must be disposed of as hazardous waste.
S61: Avoid release to the environment. Refer to special instructions / safety data sheets.
Note: The regulatory information given above only indicates the principal regulations specifically
applicable to the product described in the safety data sheet. The user's attention is drawn to
the possible existence of additional provisions which complete these regulations. Refer to all
Legal disclaimer: The above information is believed to be correct but does not purport to be all inclusive and shall
be used only as a guide. This company shall not be held liable for any damage resulting from
EC-ArmoHib-CI-31
1. Identification of Product and Company
3. Hazards Identification
4. First-aid Measures
Ingestion: Do Not induce vomiting unless directed to do so by medical personnel. Never give anything
by mouth to an unconscious person. If large quantity of this material are swallowed, call a
physician immediately. Loosen tight clothing such as tie, collar, belt or waist board.
Inhalation: If inhaled, remove to fresh air. If not breathing, give artificial respiration/ If breathing is
difficult, give oxygen. Get medical attention.
Skin contact: In case of contact, immediately flush skin with plenty of water for at least 30 minutes while
removing contaminated clothing and shoes, Cold water may be used. Wash clothing before
reuse. Thoroughly clean shoes before re use. Get medical attention.
Eye Contact: In case of contact with eyes, rinse with plenty of water. Cold water may be used Get
medical attention immediately. Remove contact lenses. Protect unharmed eye. Keep eye
wide open while rinsing.
General Advice: Immediate medical attention is required, Move out of dangerous area.
5. Fire-fighting Measures
MSDS EC-ArmoHib-CI-31
MSDS EC-ArmoHib-CI-31
Contaminated packaging: Recommendation: Handle contaminated packages in the same way as the substance
ADR: Not dangerous goods
IATA: Not dangerous goods
IMDG Not dangerous goods
RID Not dangerous goods
Not classified as dangerous in the meaning of transport regulations.
Important notice: This data sheet is a supplement to the technical instructions but does not replace them. The data are given in good faith based on information derived from our knowledge of the product at the
date of issue of this document. Each user is responsible to determine that the product is suitable for the user's intended application and that such usage complies with applicable legislative and administrative rules
and guidelines. This data sheet may contain dotted lines (....), which may indicate the missing of phrases in the computerized database.
1.2 Relevant identified uses of the substance or mixture and uses advised against
Identified use(s) Used as a sour agent, buffering agent and antioxidant in the food industry; a
correctant in pharmaceutical industry; used in detergents, buffering and
chelating, sizing and as a sequestrant.
Uses advised against No uses advised against
1.3 Details of the supplier of the Safety Data Sheet
Company Identification Weifang Ensign Industry Co., Ltd.
No. 1567, Changsheng Street, Changle, Weifang, 262400, Shandong Province, China
Telephone 0086-536-6298198
6298125
Fax No 0086-536-6234587
Contact name Wei
Xiaoming
Liu Yi
Email sales@ensignworld.com
Irritant
Risk Phrases R36. Irritating to eye
Safety Phrases S26. Avoid contact with eyes. In case of contact with eyes, rinse immediately with
plenty of water and seek medical advice
2.3 Other hazards Not known
2.4 Additional Information Not known
7.2 Conditions for safe storage, including Keep locked up or in an area accessible only to qualified staff
any incompatibilities
Storage Store in tightly closed original container in a dry, cool and well ventilated
place. Keep in original container.
Incompatible materials Strong oxidising substances, strong alkalis.
Skin protection (Hand protection/ Other) Avoid contact with skin, eyes and clothing. Wash hands before breaks and at
the end of workday. Protective gloves must satisfy the specifications of EU
Directive 89/686/EEC and EN 374
Respiratory protection Provide adequate ventilation. Wear respirator where dust level exceeds 10
mg/m3.
Information contained in this publication or as otherwise supplied to users is believed to be accurate and is given in good faith, but it is for
the users to satisfy themselves of the suitability of the product for their own particular purpose. Weifang Ensign Industry Co., Ltd. gives no
warranty as to the fitness of the product for any particular purpose and any implied warranty or condition (statutory or otherwise) is
excluded except to the extent that exclusion is prevented by law. Weifang Ensign Industry Co., Ltd. accepts no liability for loss or damage
(other than that arising from death or personal injury caused by defective product, if proved), resulting from reliance on this information.
Freedom under Patents, Copyright and Designs cannot be assumed.
1.2. Relevant identified uses of the substance or mixture and uses advised against
Relevant identified uses of the substance or mixture
Industry sector : Mineral Oil
Type of use : Corrosion inhibitor for the petroleum industry
Exposure scenarios: see section 15.2.
Symbols/Indications of danger
Harmful
R phrases
22 Harmful if swallowed.
52/53 Harmful to aquatic organisms, may cause long-term adverse effects in the
aquatic environment.
S phrases
26 In case of contact with eyes, rinse immediately with plenty of water and
seek medical advice.
28.2 After contact with skin, wash immediately with water and soap.
36/37/39 Wear suitable protective clothing, gloves and eye/face protection.
Hazardous ingredients
Ethanediol
Concentration : 45 %
CAS number : 107-21-1
EC number: 203-473-3
Index Number 603-027-00-1
REACH - Registration 01-2119456816-28, 01-2119456816-28-0000, 01-2119456816-
number according to 28-0003, 01-2119456816-28-XXXX
article 20(3):
Classification hazard substance EC
Xn Harmful R 22
GHS classification EC
Specific target organ Category 2 H373
toxicity - Repeated
exposure
Acute toxicity Category 4 H302
1-(Benzyl)quinolinium chloride
Concentration : 35 - 40 %
CAS number : 15619-48-4
EC number: 239-695-2
Classification hazard substance EC
Xn Harmful R 22
R 52/53
GHS classification EC
Acute toxicity Category 4 H302
Chronic aquatic toxicity Category 3 H412
The text of the R-phrases is shown in section 16.
The text of the H-phrases is shown in section 16.
4.2. Most important symptoms and effects, both acute and delayed
Symptoms
No symptoms known currently.
Hazards
No hazards known at this time.
4.3. Indication of any immediate medical attention and special treatment needed
Treatment
Treat symptomatically.
DNEL/DMEL values
DNEL/DMEL values are not available.
PNEC values
PNEC values are not available.
14.7. Transport in bulk according to Annex II of MARPOL73/78 and the IBC Code (International
Bulk Chemicals Code)
No transport as bulk according IBC - Code.
15.1. Safety, health and environmental regulations/legislation specific for the substance or
mixture
Other regulations
Apart from the data/regulations specified in this chapter, no further information is available
concerning safety, health and environmental protection.
Legend
ADN European Agreement concerning the International Carriage of Dangerous
Goods by Inland Waterways
ADR European Agreement concerning the International Carriage of Dangerous
Goods by Road
AOX Adsorbable organic bound halogens
CAS Chemical Abstracts Service
DMEL Derived Minimal Effect Level (genotoxic substances)
DNEL Derived No Effect Level
EC50 Half maximal effective concentration
GHS Globally Harmonized System
IATA International Air Transport Association
IMDG International Maritime Dangerous Goods
LC50 Lethal Concentration 50%
LD50 Lethal Dose 50%
MARPOL International Convention for the Prevention of Pollution From Ships
NOAEC No Observed Adverse Effect Concentration
NOAEL No Observed Adverse Effect Level
Decimal notation: "thousands" places are identified with a dot (for example, "2.000 mg/kg"
means "two thousand mg/kg"). Decimal places are identified with a comma (for example,
"1,35 g/cm3" means "one point three five g/cm3").
This information corresponds to the present state of our knowledge and is intended as a
general description of our products and their possible applications. Clariant makes no
warranties, express or implied, as to the information's accuracy, adequacy, sufficiency or
freedom from defect and assumes no liability in connection with any use of this information.
Any user of this product is responsible for determining the suitability of Clariant's products
for its particular application. Nothing included in this information waives any of Clariant's
General Terms and Conditions of Sale, which control unless it agrees otherwise in writing.
Any existing intellectual/industrial property rights must be observed. Due to possible
changes in our products and applicable national and international regulations and laws, the
status of our products could change. Material Safety Data Sheets providing safety
precautions, that should be observed when handling or storing Clariant products, are
available upon request and are provided in compliance with applicable law. You should
obtain and review the applicable Material Safety Data Sheet information before handling
any of these products. For additional information, please contact Clariant.
1. Product Identification
Synonyms: Nitrous acid, sodium salt
CAS No.: 7632-00-0
Molecular Weight: 69.00
Chemical Formula: NaNO2
Product Codes:
J.T. Baker: 3780, 3782
Mallinckrodt: 7824
2. Composition/Information on Ingredients
3. Hazards Identification
Emergency Overview
--------------------------
DANGER! STRONG OXIDIZER. CONTACT WITH OTHER MATERIAL MAY CAUSE FIRE.
HEAT, SHOCK, OR CONTACT WITH OTHER MATERIAL MAY CAUSE FIRE OR
EXPLOSIVE DECOMPOSITION. HARMFUL IF SWALLOWED, INHALED OR ABSORBED
THROUGH SKIN. CAUSES IRRITATION TO SKIN, EYES AND RESPIRATORY TRACT.
GLOVES
Storage Color Code: Yellow (Reactive)
---------------------------------------------------------------------
Inhalation:
Toxic. Causes irritation to the respiratory tract and systemic poisoning with symptoms paralleling
ingestion.
Ingestion:
Toxic. Can irritate the mouth, esophagus, stomach, etc. Excessive amounts effect the blood and blood
vessels. Signs and symptoms of nitrite poisoning include intense cyanosis, nausea, dizziness, vomiting,
collapse, spasms of abdominal pain, rapid heart beat, irregular breathing, coma, convulsions, and death
due to circulatory collapse. Estimated lethal dose 1 to 2 grams.
Skin Contact:
Causes irritation, redness and pain. May be absorbed through the skin causing systemic poisoning;
symptoms may parallel ingestion.
Eye Contact:
Causes irritation, redness, and pain.
Chronic Exposure:
Repeated exposure through any route may cause symptoms similar to acute toxicity.
Aggravation of Pre-existing Conditions:
No information found.
Fire:
Not combustible, but substance is a strong oxidizer and its heat of reaction with reducing agents or
combustibles may cause ignition. Increases the flammability of any combustible material.
Explosion:
Contact with oxidizable substances may cause extremely violent combustion. May explode when heated
to 537C (1000F) or on severe impact or on contact with cyanides, ammonium salts, cellulose, lithium,
potassium plus ammonia, and sodium thiosulfate.
Fire Extinguishing Media:
Water or water spray in early stages of fire. Foam may also be used, but avoid the use of multi-purpose
dry chemical fire extinguishers where contact with sodium nitrite may occur. Water streams may scatter
molten material.
Special Information:
In the event of a fire, wear full protective clothing and NIOSH-approved self-contained breathing
apparatus with full facepiece operated in the pressure demand or other positive pressure mode.
Decomposition of sodium nitrite may leave a caustic residue.
Local exhaust ventilation is generally preferred because it can control the emissions of the contaminant at
its source, preventing dispersion of it into the general work area. Please refer to the ACGIH document,
Industrial Ventilation, A Manual of Recommended Practices, most recent edition, for details.
Personal Respirators (NIOSH Approved):
For conditions of use where exposure to dust or mist is apparent and engineering controls are not feasible,
a particulate respirator (NIOSH type N95 or better filters) may be worn. If oil particles (e.g. lubricants,
cutting fluids, glycerine, etc.) are present, use a NIOSH type R or P filter. For emergencies or instances
where the exposure levels are not known, use a full-face positive-pressure, air-supplied respirator.
WARNING: Air-purifying respirators do not protect workers in oxygen-deficient atmospheres.
Skin Protection:
Wear impervious protective clothing, including boots, gloves, lab coat, apron or coveralls, as appropriate,
to prevent skin contact.
Eye Protection:
Use chemical safety goggles and/or full face shield where dusting or splashing of solutions is possible.
Maintain eye wash fountain and quick-drench facilities in work area.
Oral rat LD50: 180 mg/kg; inhalation rat LC50: 5500 ug/m3; irritation: eye rabbit: 500 mg/24H mild.
Investigated as a tumorigen, mutagen, reproductive effector.
------\Cancer Lists\------------------------------------------------
---NTP Carcinogen---
Ingredient Known Anticipated IARC Category
------------------------------------ ----- -----------
Sodium Nitrite (7632-00-0) No No None
ATTACHMENT NO.02.3
COSHH
Health Hazard
Hazard Type
Route of Exposure
x X X X
Inhalation Skin Eyes Ingestion Other (State)
Workplace Exposure Limits (WELs) please indicate n/a where not applicable Not Applicable
Long-term exposure level (8hrTWA): N/A Short-term exposure level (15 mins): N/A
Control Measures: (for example extraction, ventilation, training, supervision). Include special measures for vulnerable groups, such as disabled people and pregnant workers. Take
account of those substances that are produced from activities undertaken by another employer’s employees.
1. Training and awareness for handling of Chemicals to the working Crew.
2. Communicated the MSDS to the working Crew.
3. Storage: Handle container with care, keep in a tightly closed container, stored in a cool, dry, ventilated area. Protect against physical damage and
moisture. Isolate from any source of heat or ignition. Avoid storage on wood floors. Separate from incompatibles, combustibles, organic or other
readily oxidizable materials. Containers of this material may be hazardous when empty since they retain product residues (dust, solids); observe all
warnings and precautions listed for the product.
4. Wear suitable Personnel Protective Equipment’s. Use chemical safety goggles and/or full face shield where dusting or splashing of solutions is
possible. Maintain eye wash fountain and quick-drench facilities in work area, Wear impervious protective clothing, including boots, gloves, lab
coat, apron or coveralls, as appropriate, to prevent skin contact
5. For emergencies or instances where the exposure levels are not known, use a full-face positive-pressure, air-supplied respirator. WARNING: Air-
purifying respirators do not protect workers in oxygen-deficient atmospheres
6. Take the Hygiene measures like Wash hands before breaks and after work, Use barrier skin cream, Remove soiled or soaked clothing immediately
and clean thoroughly before using again.
7. Take the environmental exposure controls like. Do not allow to enter drains or waterways.
8. It cannot be saved for recovery or recycling should be handled as hazardous waste and sent to a approved waste facility.
9. Accidental Release Measures: Remove all sources of ignition. Ventilate area of leak or spill. Wear appropriate personal protective equipment, Clean up
spills in a manner that does not disperse dust into the air. Use non-sparking tools and equipment. Reduce airborne dust and prevent scattering by
moistening with water. Pick up spill for recovery or disposal and place in a closed container.
X X
Respirator Goggles
X X
Gloves Overalls
X
Footwear Other
X Health Hazard
Hazard Type
Route of Exposure
x X X X
Inhalation Skin Eyes Ingestion Other (State)
Workplace Exposure Limits (WELs) please indicate n/a where not applicable Not Applicable
Long-term exposure level (8hrTWA): N/A Short-term exposure level (15 mins): N/A
X X
Respirator Goggles
X X
Gloves Overalls
(Use tightly fitted chemical safety goggles, In the
X X case of vapor formation use a respirator with an
approved filter, For prolonged or repeated contact
Footwear Other use protective gloves. Use protective suit
according to the amount and concentration of the
dangerous substance at the work place etc.,)
First Aid Measures
1. Skin contact: In case of contact, immediately flush skin with plenty of water for at least 30 minutes while removing contaminated clothing and
shoes, Cold water may be used. Wash clothing before reuse. Thoroughly clean shoes before re use. Get medical attention.
2. Eye contact: In case of contact with eyes, rinse with plenty of water. Cold water may be used Get medical attention immediately. Remove
contact lenses. Protect unharmed eye. Keep eye wide open while rinsing.
3. Ingestion: Do Not induce vomiting unless directed to do so by medical personnel. Never give anything by mouth to an unconscious person. If
large quantity of this material are swallowed, call a physician immediately. Loosen tight clothing such as tie, collar, belt or waist board.
4. Inhalation: If inhaled, remove to fresh air. If not breathing, give artificial respiration/ If breathing is difficult, give oxygen. Get medical attention.
Storage
1. Storage in accordence with local regulation for flamable liquids.
2. Store container tightly closed in a cool dry & well ventilated area away from incompatible substances. Keep away from heat, sparks, and flame.
Keep away from sources of ignition. Keep container closed when not in use.
Disposal of Substances & Contaminated Containers
Health Hazard
Hazard Type
Route of Exposure
x X X X
Inhalation Skin Eyes Ingestion Other (State)
Workplace Exposure Limits (WELs) please indicate n/a where not applicable Not Applicable
Long-term exposure level (8hrTWA): N/A Short-term exposure level (15 mins): N/A
X X
Respirator Goggles
X X
Gloves Overalls
X
Footwear Other
First Aid Measures
1. Skin contact: In case of contact, wash off immediately with soap and water.
2. Eye contact: In case of contact with eyes, Rinse thoroughly with plenty of water and seek medical advice.
3. Ingestion: Never give anything by mouth to an unconscious person. Consult a physician immediatly.
4. Inhalation: If inhaled, remove to fresh air and seek medical aid.
Storage
1. Storage in accordence with local regulation for flamable liquids.
2. Handle container with care, keep container tightly closed in a cool, well-ventilated place.
Disposal of Substances & Contaminated Containers
Health Hazard
Hazard Type
Route of Exposure
x X X X
Inhalation Skin Eyes Ingestion Other (State)
Workplace Exposure Limits (WELs) please indicate n/a where not applicable Not Applicable
Long-term exposure level (8hrTWA): N/A Short-term exposure level (15 mins): N/A
X X
Respirator Goggles
X X
Gloves Overalls
X
Footwear Other
First Aid Measures
1. Skin contact: In case of contact, Wash off immediately with plenty of water for at least 15 minutes. If irritation persists, call a physician.
2. Eye contact: In case of contact with eyes, Rinse thoroughly with plenty of water for at least 15 minutes and consult a physician.
3. Ingestion: Do NOT induce vomiting. Drink 1 or 2 glasses of water. Never give anything by mouth to an unconscious person. Consult a physician.
4. Inhalation: If inhaled, Move to fresh air.
Storage
1. Storage in accordence with local regulation for flamable liquids.
2. Keep locked up or in an area accessible only to qualified staff, Store in tightly closed original container in a dry, cool and well-ventilated place.
Keep in original container.
Disposal of Substances & Contaminated Containers
X Health Hazard
Hazard Type
X x
Route of Exposure
x X X X
Inhalation Skin Eyes Ingestion Other (State)
Workplace Exposure Limits (WELs) please indicate n/a where not applicable Not Applicable
Long-term exposure level (8hrTWA): N/A Short-term exposure level (15 mins): N/A
X X
Respirator Goggles
X X
Gloves Overalls
X
Footwear Other
First Aid Measures
1. Inhalation: Get medical aid immediately.Remove from exposure and move to fresh air immediately. If not breathing, give artificial respiration. If
breathing is difficult, give oxygen. Do NOT use mouth-to-mouth resuscitation. If breathing has ceased apply artificial respiration using oxygen and
a suitable mechanical device such as a bag and a mask.
2. Skin contact: Get medical aid immediately.Immediately flush skin with plenty of water for at least 15 minutes while removing contaminated
clothing and shoes. Wash clothing before reuse. Destroy contaminated shoes.
3. Eye contact: Get medical aid immediately. Do NOT allow victim to rub eyes or keep eyes closed. Extensive irrigation with water is required (at
least 30 minutes)
4. Ingestion: Do not induce vomiting. If victim is conscious and alert, give 2-4 cupfuls of milk or water. Never give anything by mouth to an
unconscious person. Get medical aid immediately
Storage
1. Storage in accordence with local regulation for flamable liquids.
Page 3 of 4 SP15: Procedure for Control of Substances Hazardous to Health
Page 173 of 294
Page 130 of 249
Annexure 1: COSHH Risk Assessment Sheet REV:01
2. Keep container closed when not in use and store in a cool, dry, well ventilated area away from incompatible substances. Stay protected from
moisture and keep away from acids and corrosives area.
Disposal of Substances & Contaminated Containers
X Health Hazard
Hazard Type
Route of Exposure
x X X X
Inhalation Skin Eyes Ingestion Other (State)
Workplace Exposure Limits (WELs) please indicate n/a where not applicable Not Applicable
Long-term exposure level (8hrTWA): N/A Short-term exposure level (15 mins): N/A
X X
Respirator Goggles
X X
Gloves Overalls
(Self-contained breathing apparatus must be
X X available in case of emergency. Impermeable
gloves. Tightly fitting safety goggles. Ensure eye
Footwear Other bath is to hand, Impermeable protective clothing
etc.,)
First Aid Measures
1. Skin contact: Get medical aid immediately.Remove all contaminated clothes and footwear immediately unless stuck to skin. Drench the affected
skin with running water for 10 minutes or longer if substance is still on skin. Transfer to hospital if there are burns or symptoms of poisoning.
2. Eye contact: Bath the eye with running water for 15 minutes. Transfer to hospital for specialist examination.
3. Ingestion: Wash out mouth with water. Do not induce vomiting. Give 1 cup of water to drink every 10 minutes. If unconscious, check for breathing
and apply artificial respiration if necessary. If unconscious and breathing is OK, place in the recovery position. Transfer to hospital as soon as
possible.
4. Inhalation: Remove casualty from exposure ensuring one's own safety whilst doing so. If unconscious and breathing is Ok, Place in the recovery
position. If conscious, ensure the casualty sits or lies down. If breathing becomes bubbly, have the casualty sit and provide oxygen if available.
Transfer to hospital as soon as possible.
Storage
1. Storage in accordence with local regulation for flamable liquids.
2. Keep container closed when not in use and store in a cool, dry, well ventilated area away from incompatible substances. Stay protected from
moisture and keep away from acids and corrosives area.
Disposal of Substances & Contaminated Containers
ATTACHMENT NO.02.4
PPE Information
Specifications
Accessories Yes
Brand 3M™
Cartridge or Filter Type Gas and Vapor
Clip-on Welding Shield Yes
3M™ Full Facepieces FF-400, 3M™ Half Facepiece Reusable Respirators
Compatible Respirator 6000 Series, 3M™ Half Facepiece Reusable Respirators 7000 Series
Compatible with 3M™
PAPR Systems Yes
Compatible with 3M™
Supplied Air System Yes
Compatible with
Welding Shield Yes
Connection Type Bayonet
Cool Flow™ Exhalation
Valve Yes
Drop-down Feature Yes
Enhanced Comfort Yes
Enhanced Durability Yes
Eye Protection Yes
Features Low Profile
For Use With Reusable Respirators
Ammonia, Chlorine, Chlorine Dioxide, Formaldehyde, Hydrogen Chloride,
Gas & Vapor Protection Hydrogen Fluoride, Hydrogen Sulfide, Methylamine, Organic Vapor, Sulfur
Type Dioxide
Multigases: organic vapor, chlorine, chloridric acid, chlorine dioxide,
sulphur dioxide, hydrogen sulphide (only for escape),
Hazard Type ammonia/methylamine, formaldehyde and hydrogen fluoride
Maintenance Free No
Market Aerospace, Maritime, Defense, Homeland Security
National Stock Number 4240014557259, 4240015856633, 4240014557370
Nuisance Odor Relief (<
OSHA PEL) N/A
Overall Height (Imperial) 3.4 in, 3.4 in
Overall Length
(Imperial) 4.2 in
Particulate Protection Acid Gas, Ammonia, Formaldehyde, Methylamine, Organic Vapor
Ammonia, Chlorine, Chlorine Dioxide, Formaldehyde, Hydrogen Chloride,
Hydrogen Fluoride, Hydrogen Sulfide, Methylamine, Organic Vapors, Sulfur
Protection Focus Dioxide
Purpose Cartridges & Filters
Assembly and Mechanical, Batch-Charging, Chemical Clean-up, Chemical
Transfer, Cleaning, Composite Finishing, Final Finish, Handling, Hazardous
Waste Handling, Laboratories, Maintenance, Manufacturing, Paint
Recommended Preparation, Painting, Parts Cleaning, Petrochemical, Pharmaceuticals,
Application Pouring Molten Metal, Remediation, Seal Coatings, Welding
Facility Sanitation, Food Processing, Food Safety, General Manufacturing,
Recommended Industry Mining, Oil & Gas, Transportation
Segment Personal Safety
Silicone Faceseal Yes
Six-point Head Harness Yes
Spare Parts Yes
Speaking Diaphragm Yes
Standards/Approvals Ammonia, Chlorine, Chlorine Dioxide, Formaldehyde, Hydrogen Chloride,
Details
NIOSH approved for protection against certain organic vapors, acid gases,
ammonia, methylamine and formaldehyde
Swept-back design allows an enhanced field of view and comfort
Bayonet compatibility allows use with many 3M half and full facepiece
designs
Wide range of applications reduces inventory needs
Simple installation and usage requirements reduces training requirements
NIOSH approved against certain organic vapors, acid gases, ammonia,
methylamine or formaldehyde. Use with 3M™ Half and Full Face pieces 6000,
7000 and FF-400 Series with bayonet filter holders.
The 3M™ Multi Gas & Vapor Cartridge 6006 helps provide gas and vapor
protection in a variety of environments. The cartridge may be used for gas and
vapor concentrations up to 10 times the Permissible Exposure Limit (PEL) with
half face pieces or 50 times PEL with quantitatively fit tested full face pieces.
Recommended applications for the cartridge include assembly, batch-charging,
chemical clean-up, chemical transfer, cleaning, hazardous waste handling,
painting, pouring molten metal. Inventory needs and training requirements for
safety equipment are reduced because this respirator cartridge selection works
for many different applications. Industries in which this cartridge is commonly
used include chemicals, mining, oil and gas, and primary metals.
This multi gas and vapor cartridge works with 3M™ Half and Full Face pieces
6000, 7000 and FF-400 Series with bayonet holders. The cartridge is NIOSH
(National Institute for Occupational Safety and Health) approved for
environments containing certain organic vapors, chlorine, hydrogen chloride,
chlorine dioxide, sulfur dioxide, hydrogen sulfide, ammonia, methylamine,
formaldehyde or hydrogen fluoride. The cartridge has been assigned the color
code “olive” in the NIOSH system.
Breathing gases and vapors can pose a risk to your health. NIOSH, a Federal
government regulatory agency, has tested and approved the 3M™ Organic Vapor
Cartridge 6006 to help reduce exposure to certain gases and vapors
C. RUBBER SHOES
Mandatory PPE’S
2- Safety Helmet
4- Safety Goggles
5- Hand Gloves
ATTACHMENT NO.02.5
ATTACHMENT NO.02.6
Boiler Information
INDEX
1
Page 196 of 294
Page 153 of 249
TECHNICAL CHARACTERISTICS
1 TECHNICAL CHARACTERISTICS
1.1 GENERAL
The ASB series steam boilers are type semi-fixed, horizontal smoke-tube type, complete with accessories.
The boilers are suitable for operation with pressurised burners for gas, fuel oil or heavy oil.
Safety, reliability, high efficiency and high quality saturated steam are the characteristics of our boilers.
Please consult the instructions with attention.
2
This high-pressure steam (12-15 kgf/cm ) generator uses a combustion chamber with three-gas-passes, wet
floor-externally-fired boiler. For operation at up to 3000 kg/h of steam generated there is partial exoneration
(in Europe) in the employment of specialist boiler operators. Local requirements as to personnel qualification
MUST be taken into account for the country where the unit is installed.
1.2 CHARACTERISTICS
st nd
Working pressure switches for operation (controlling the 1 and 2 burner flame).
Locking pressure switches (stops the burner on reaching the maximum steam pressure; the boiler is
manually reset from the control panel).
Automatic level regulator (2 probes connected to an electronic conductivity relay maintain the water
level between the set levels).
Water level limits (2 probes connected to two independent electronic conductivity relays stop the burner
if the water level falls below the safe minimum; reset is manual on the control panel).
2
Page 197 of 294
Page 154 of 249
TECHNICAL CHARACTERISTICS
Fig. 1
LEGEND 12 Barrel drain 24 Feed water pumps
1 Switchboard 13 Burner plate 25 Salinity check
2 Control pressure switches 14 Steam take-off 26 Chill
3 Locking pressure switch 15 Non return valve 27 Level gauges drain
4 Pressure gauge 16 Inspection door
5 Level gauges 17 Safety valves N1 Steam take-off fitting
6 Pump stop probes 18 Feed water N2 Feed water fitting
7 Pump start probes 19 Suction pumps filters N3 Safety valve drain fittings
8 1st safety level probe 20 Smokestack connection N4 Boiler drain fitting
9 2nd safety level probe 21 Flame inspection hole N5 Safety valves fittings
10 Front plates 22 Boiler drain
11 Probes holder barrel 23 Pneumatic drain valve
NOTE: drawing and legend refer to highest option models. Therefore, all accessories mentioned in
the legend might me not equipped with standard models; please refer to the provided
accessory drawing.
Length Width Net Height Height with accessories Chimney Dia Dry weight
Model
mm mm mm Mm mm Kg
3
Page 198 of 294
Page 155 of 249
ACCESSORIES
2 ACCESSORIES
ASB steam boilers are fitted with a series of accessories that can be subdivided as follows:
• Safety accessories (safety valves, water level limits, safety pressure switches).
• Observation accessories (level gauges, pressure gauge, flame inspection).
• Control accessories (level ad pressure switches).
• Feed water accessories: centrifugal pump, stop valves.
• Manual operation accessories (stop valves, purge valve).
In the following description the accessories are subdivided as to the physical parameter they control
(pressure and level).
2.1 PRESSURE
Fig. 2
4
Page 199 of 294
Page 156 of 249
ACCESSORIES
a) Turn the knob (1) until the scale indicator (2) reaches the pressure at which the burner shall restart.
b) Remove the cover of the pressure switch and position the drum (3) at the value selected for the pressure
differential (stopping the burner) as to the diagram Fig. 4.
Example:
* Type of pressure switch: RT 5
* Scale indicator 9 bar
* Drum indicator: 4 corresponding to 2,1 bar
* Burner start: 9 bar
* Burner stop: 11,1 bar
Fig. 3 Fig. 4
This switch is set at a higher pressure than the maximum of the control pressure switch, but always lower
than the opening pressure of the safety valves.
The safety pressure switch acts in the case of a fault to the control pressure switch and stops the burner
permanently. Restarting the burner can only occur after the steam pressure has fallen and after a manual
reset on the switchboard.
This pressure switch is adjusted in a similar manner to that of the control pressure switch, with the only
precaution that the drum indicator is set to 1 so that the differential is effectively nil.
5
Page 200 of 294
Page 157 of 249
ACCESSORIES
These valves have the function of discharging steam when the maximum design pressure of the boiler is
reached.
The valves used on boilers are of the type Spring (Fig. 5).
The boiler operator must pay much attention to the safety valves and
carry out careful and diligent maintenance. The safety valve is the
most important and sensitive accessory on the boiler and represents
the best guarantee that the internal pressure of the boiler does not
exceed the design pressure.
As during normal operation of a boiler, the safety valve never acts, it
is good practice to check that the valve is free, i.e. that the
valve plug is not stuck to the seat, by acting on the side lever until
the valve starts to discharge steam.
WARNING
The safety valve installed on steam boilers must have the discharge
piped to outside the boiler room. Particular care must be taken in
designing the discharge line; we show some here.
• The discharge line should e of diameter at least equal to that of
the discharge flange on the safety valve.
• Only wide radius curves must be used in the discharge line.
• The entire discharge line must be built to avoid the formation of
condensation locks. There must be therefore adequate slopes to
ensure complete drainage.
Particular care must be taken if the valve seat and plug are to be
ground; if this operation becomes necessary due to leaks, use
abrasives based on silicon carbide or oil based carborundum. Carry
out the first grinding operation using fine grain abrasive, finishing
with a very fine grain abrasive.
Fig. 5
2.2 LEVEL
The level indicator consists of a pair of valves connected to a sight glass box containing a prismatic glass.
This device is connected to the boiler both above and below the normal water level, while the lower part is
fitted with a purge valve so that any sludge can be removed, to keep the glass clean. Using these valves, the
efficiency of the level control system can be verified periodically by carrying out the following operations:
• Open for a few seconds and then close the purge valve. If the water disappears from the sight glass and
then appears again with ample level oscillation, then it can be considered that the level operates correctly. If
on the other hand the water returns slowly or stops at a level differing form the preceding level, then on of
the communications may be obstructed. To make sure which of the two is obstructed, and to attempt a
purge, close the steam valve leaving the water valve open, then open the purge valve. This valve must
release water taking with it any sludge formed in the pipes. Then close the water valve and open the steam
valve: steam should be released from the purge valve. Closing the purge valve and leaving the two water
and steam valves open, the water should return to the initial level. If this does not occur, the communication
pipes between the level and the boiler must be cleaned.
6
Page 201 of 294
Page 158 of 249
ACCESSORIES
The physical principle employed to detect and control the water level is based on the electrical conductivity of
the water. The control device consists of a part sited in the control panel (electronic relays) and of probes of
differing lengths immersed in the barrel and boiler shell.
Operation of the system provides for:
Automatic pump start and stop: Two probes inserted in the barrel, of which the longer starts, and the
shorter stops the pump, connected to a single control relay in the control panel.
Burner stop at low water level: two probes, inserted in the boiler and connected to two distinct control
relays in the control panel, stop the burner permanently if the water level drops below the admissible level.
Barrel probes:
6 Pump stop
7 Pump start
Boiler probe:
nd
8 2 safety burner stop and
alarm on.
st
9 1 safety burner stop and
alarm on.
Fig. 6
An electric centrifugal pump supplies the water. The inlet side of the pump must never be under suction
pressure, but always under positive pressure due to the difference in height between the pump itself and the
feed water tank. While a pump can operate under suction head from a cold water tank (up to 5-6 m), if the
water is hot the pump cannot operate and indeed needs the water to be delivered under a certain pressure.
The height of the feed water tank varies with the temperature, as shown in the following table:
WARNING
Avoid the use of feed water at temperatures lower than 60 Celsius, being rich in Oxygen and
therefore such as to cause corrosion.
To avoid pump cavitation problems, the feed water temperature should not be higher than 90
Celsius.
7
Page 202 of 294
Page 159 of 249
INSTALLATION
3 INSTALLATION
3.1 SITING
Our steam boilers are supplied as units and do not need any foundation work. A flat even floor only is
needed, that can be raised by 5-10 cm.
3.2 WATER CONNECTIONS
The steam boilers once positioned are connected to the system as follows (Fig. 7):
Water
From the condensate collection tank (10) (if existing; otherwise from the treated water tank) to the suction
side of the feed water pump (9).
Steam
From the main steam take-off valve (3) to the user services (distributor or others), from the safety valve
outlets (6) to outside the boiler room in a safe position.
Drains
From the level indicator drains (16) and the boiler drain (17) to the drainage network.
Fuel
Connection to the burner foreseen for fuel oil or natural gas.
8
Page 203 of 294
Page 160 of 249
INSTALLATION
The boilers are provided with a switchboard (protection level IP 55) completely assembled to the various
boiler accessories.
Before connecting the switchboard, make sure that the electric system has been correctly installed, checking
in particular the efficiency of the earthing system.
Wiring diagram
Refer to the diagram supplied with the specific switchboard.
3.4 SMOKESTACK
The connection from the boiler to the base of the smokestack must slope upwards in the direction of the gas
flow, with a slope that should be at least 10%. The path should be as short and as possible and the bends
and connections designed as to the rules used in the design of air ducts.
For lengths of up to 2 metres, the same diameter as the boiler flue gas outlet can be used (see the technical
specification table). For more tortuous paths, the diameter must be suitable increased.
The smokestack must in any case be dimensioned as to applicable regulations. It is advisable to pay great
attention to the inside diameter, insulation, gas tightness, ease of cleaning and to the fitting required for
taking flue gas samples for combustion analysis.
3.5 BURNER
The suitable burner shall be a two-stage burner or a modulating burner; this avoids large pressure
variations consequent on sudden stream demands.
Further, and above all with natural gas, every burner start-up is preceded by a long period of preventilation of
the combustion chamber, with consequent loss of heat to the smokestack.
Verify that the spaces between the burner sleeve and the plug are suitable filled with flame-resistant ceramic
insulation.
9
Page 204 of 294
Page 161 of 249
BOILER OPERATION
4 BOILER OPERATION
4.1 FIRST START-UP
1 2
Fig. 8
Start the boiler as follows:
1) Switch on the control panel by turning the main switch.
2) Check that the drive shaft of the feed water pump is free to turn. By starting the pump manually for an
instant, check that the shaft turns in the correct direction.
3) Set the pump switch to AUT and verify that burner cannot start before the attainment of the minimum level;
4) Check that the pump stops when the maximum level is reached by observing the level indicators and
checking the positions of the indicator valves.
5) Press and keep pressed the safety water level reset button for at least 10 seconds, the conductivity relay
being of the delayed type.
6) Open the boiler drain and check on the level indicator at what level the pump-start probe acts.
7) Set the pump switch to “0” leaving the drain open and check the actuation level of the safety probes with
respect to the minimum level reference plate.
8) Close the drain and set the pump switch to AUT
9) Switch on the burner and bring the boiler up to pressure adjusting the operation pressure.
WARNING: On boilers with a man-way and head-way, during the first start-up it is important to tighten progressively the
nuts on the man-way cover as the pressure increase. Otherwise a hazardous situation is created due to steam leaks
that quickly deteriorate the gasket creating a dangerous situation for the boiler room personnel.
10
Page 205 of 294
Page 162 of 249
MAINTENANCE
5 MAINTENANCE
5.1 ORDINARY
Periodically purge the level gauges, probe holder if fitted and the boiler, to avoid the accumulation of
sludge.
Check the efficiency of the control and regulation instruments, examining carefully the electrical parts
(connections included) and the mechanical parts (pressure switches); it is advisable to replace every year
the ceramic probe-holders.
Carry out burner maintenance (as to the specific instructions);
Check the tightness of flange bolts and the state of the gaskets;
Check the conditions of the boiler door internal covering after loosening the anti vibration bolts on the
hinges, in order to allow door opening;
Clean the flue-gas tube bundle;
Carry out correct maintenance to the pump (bearings, mechanical seal);
Check for wear to the discharge valves; these tend to wear more quickly, due to the abrasive effect of the
sludge during blow-down;
5.2 PERIODIC
From time to time (every 6 hours of use) the thermal plant must be inspected by qualified personnel to check
the efficiency of all safety accessories:
The system can be reset if no anomalies have been encountered: power off the panel for approx. 20
seconds, power on the main switch and press the reset buttons.
11
Page 206 of 294
Page 163 of 249
MAINTENANCE
12
Page 207 of 294
Page 164 of 249
MAINTENANCE
5.3 SCHEDULED
All boilers must be periodically stopped for careful inspection and maintenance: the time interval between
stops is established by experience, by the operating conditions, by the quality of the feed water and by the
type of fuel used.
Before entering the boiler shell for inspection or for cleaning, check carefully that there is no possibility of
entry of water or steam via the pipework to which the boiler is connected. Every valve must be locked and if
necessary isolated by removing a piece of pipework or by inserting a blind flange.
The parts under pressure must be carefully examined internally to identify any encrustation, corrosion and
other potential sources of danger linked to the feed water.
All deposits must be removed mechanically or chemically and the effective thickness of the structures
must be verified using suitable instruments to determine that they are equal to or greater than the
design values. All pustules or other types of corrosion must be scraped and cleaned with a steel wire brush
to white metal. Leaks between fire tubes and tube plates must be carefully examined: any welding must be
done in all cases observing legal obligations, without forgetting that a steam boiler is a pressure vessel with
danger of explosion and subject to control by competent authorities.
During inspection also verify all the accessories, with priority to safety valves, level probes and pressure
switches.
13
Page 208 of 294
Page 165 of 249
WATER CHARACTERISTICS
6 WATER CHARACTERISTICS
All the values listed as follow are taken by tables 5.1 and 5.2, figure 5.1 and 5.2 contained in the EN 12953-
10 (rules related to quality features of feeding and working of boiler water).
For steam generators there are some regulations that require limit values for water characteristics.
However, limits should be adopted for all generators as stated by qualified companies that recommend the
type of treatment to be carried out basing on careful analysis of the available water. Many faults and
sometimes serious accidents are caused by the use of water with non-conforming features.
Chart. 1.1
Alkalinity Silicate
0,5 mmol/l 80 mg/l
5 mmol/l 105 mg/l
10 mmol/l 135 mg/l
15 mmol/l 160 mg/l
Note 2. These values are to be accepted when a thermal deaerator is installed. If not so, it is good practice to heat the
water in the tank at least to 80°C (refer to Chapt. 2.7 – Feed water) to reduce the content of dissolved gasses (O2 e
CO2). Be sure to use chemical conditioners to deoxygenate feed water and to reduce CO2 corrosion.
14
Page 209 of 294
Page 166 of 249
WATER CHARACTERISTICS
Chart. 2
Characteristics Unit of measurement Pressure 20 bar
Aspect Clear, limpid, no foam, suspended solids
Direct conductivity at 25 °C S/cm < 6000
pH at 25 °C ------ from 10,5 to 12
Total alkalinity mmol/l from 1 to 15
Silica (SiO2 ) mg/l See chart 1.1
Phosphates (PO4 ) mg/l from 10 to 30
Organic concentration ------ Note 1
The frequency of analysis is determined evidently as a function of the use of the boiler and of the quality of
the water used; it is advisable in any case to check the pH, the total hardness and the alkalinity of the feed
and boiler waters at least every two days. Once a month, especially under conditions of variable operation, it
is advisable to subject meaningful samples of the boiler and feed waters to complete analysis.
It is also advisable to inspect the return condensate for traces of any highly contaminating oily substances
(reduction of evaporation from the water surface in the boiler caused by a layer of oil).
15
Page 210 of 294
Page 167 of 249
TROUBLESHOOTING
7 TROUBLESHOOTING
16
Page 211 of 294
Page 168 of 249
8.1 GENERAL
The water level limits consists in: n. 2 level rods, n. 2 probes, electrical cables, n. 2 electronic relays. The
device prevents the lowering of the level of water in the steam generators and the consequent overheating of
the membrature.
The principle of survey and control of the level is based on water conductivity. In order to guarantee
the correct operation of the device, following conditions must be fulfilled:
17
Page 212 of 294
Page 169 of 249
Boiler probes:
6 Pump stop
7 Pump starting
8 1st burner cut-out safety device and alarm ON.
9 2nd burner cut-out safety device and alarm ON
18
Page 213 of 294
Page 170 of 249
8.6 MAINTENANCE
8.6.1 Ordinary
Bleed periodically (level indicators, probe-holder barrel if any, boiler) to avoid mud deposits.
Check the efficiency of the regulation and control instruments by inspecting carefully the electrical (also
connections); it is also recommended that the probe-holder ceramic plugs are replaced every year
Safety valve
The system can be reset if no anomalies have been encountered: power off the panel for approx. 20 seconds, power on the
main switch and press the reset buttons.
19
Page 214 of 294
Page 171 of 249
20
Page 215 of 294
Page 172 of 249
To replace the water level limits or parts of it, follow strictly the instructions below:
1. Ensure that the new ceramic plug is intact
2. Check the length of the rod
3. Ensure that the rod is coaxial to the plug axis
4. Inspect the electrical system and, in particular, ensure that the resistance of the electric circuit linking the
ceramic plug to the electrical panel is intact (resistance must be over 10 MOhm)
5. Ensure that the automatic level control consisting of the two ceramic plugs and their conductivity-relays,
work well
8.7 TROUBLESHOOTING
21
Page 216 of 294
Page 173 of 249
Alitaliya Industries.
Sharjah – United Arab Emiraets
Tel: +971 6 533 5880
Fax + 971 6 533 4880
mail@alitaliya.com www.alitaliya.com
LIVELLOSTATO DI SICUREZZA
WATER LEVEL LIMITS Boiler serial number
Model GP1
Serial number
Water conductivity
> 250 S/cm
PS max 20 bar
TS max 210°C
Fluid Acqua / Water
Date
Boiler final test date
Volt / Freq. / Pot. - Power 24 VAC / 50-60 Hz / 3 VA
Approval
22
Page 217 of 294
Page 174 of 249
The data reported are indicative only and are not binding. Our company reserves the right to introduce alterations at any time, as it
deems fit and proper for the development of the product.
ATTACHMENT NO.02.7
Environmental
Release/Spill
Yes
Is It
Controllable?
NO
Control Spill with
Raised Alarm
Spill Kits or Shut Off
Manual or Electrical
valves
Report to
Evacuate the Area &
Elsewedy
Report to Assembly
Project Director/
Point
HSE Manager
Declare Emergency
NO YES
Call
Call Emergency response
Team Is External Help Civil defense-997
required?
ATTACHMENT NO.03
LEGEND
CLIENT: EM HIDROMONTAZA
W:Witness
WORK DESCRIPTION: CHEMICAL CLEANING OF FUEL GAS PIPELINE
H: Hold Point
SUBCONTRACTOR: CORODEX RI:RANDOM INSPECTION
DOC REF.: CMS/EMH/ITP/00 S: SURVIELANCE
ACCEPTED RANGE
SR.# DESCRIPTION CONTROLLI QUALITY TEST CORODEX EMH ESI DEWA
NG CHARACTERSTICS TO FREQUENC VALUE CODE/STAN
DOCUMENT BE VERIFIED Y DARD
Visual
appearance of Chemical Visual Check With Once Check Chemical
CS pipe internal Cleaning Torch In Accessible Whether There Cleaning W H W W
Procedure Area Of Pipes Is Debris Or Procedure
1 surface (before
chemical Foreign
cleaning) Material Inside
The Pipes. The
internal rust &
welding flakes.
Borescope
inspection on
the accessible
areas limited
to 40 meter
length.
The test
pressure
during a W W RI RI
The temporary The test pressure
piping, Hoses are Once pressure during test is
tested first (the a pressure test normally
pumping skid, is normally set set to 150
both headers and to 150 % of the % of the
the effluent line pump shut off pump shut
are included in the pressure. off
testing). pressure.
Chemical
Leak Test Cleaning
2 Procedure Visually check Once No leaks Chemical H W W W
temporary Joints for should be Cleaning
leaks found on Procedure
Temporary
Joints
W RI RI S
MN Test 1 HOUR Use MN Paper Chemical
to Check Oil Cleaning
Content In Procedure
Water. No
color changes
on the MN
Paper will be
accepted.
4 Degreasing, Chemical W RI RI S
Cleaning
Procedure Temperature Once 50 C to 60C. Chemical
Cleaning
Procedure
Neutralization
6 &Passivation
Chemical
Cleaning
Procedure
Visual Check W W W W
with Torch in
Accessible
Area of Pipes.
Chemical Slight
Cleaning Visual Appearance Final Discoloration
Procedure On The Weld
7 Final Inspection Joint Is
Acceptable Chemical
Cleaning
Procedure
Borescope W W W W
inspection on
the accessible
areas limited
to 40 meter
length.
Visual Check W W W W
with Torch &
Bore scope in
Accessible
Area of Pipes.
Slight
Discoloration
On The Weld
Joint Is
Acceptable
Visual Check W W W W
for the sample
piece which
kept in the
mixing tank
W W W W
SILVER GRAY
FINISH
COLOR
Client:
Contractor: Sub-Contractor: Job no.:
Site:
Job: Date:
1. Leak Test:
Date Time Pressure (Bar) Remarks
2. Degreasing Phase
Oil.
Temp
Date Time M-N pH Remarks
C
test paper
3. Acid Phase
IronTot. Acid WOOL Temp
Date Time pH Remarks
as Fe+2 Concentration Test C
4. Passivation Phase
Temp
Date Time Nitrite Conc. (PPM) pH Remarks
C
ATTACHMENT NO.04
1. Introduction:
HRSG 22 has been chemically cleaned as per the approved procedure. The chemical cleaning
procedure was meant for the removal of debris, oil/grease, rust, and mill scales. The chemical cleaning
procedure consisted of the below steps:
Total of 7 sample pieces were given by client and placed in LP drum, IP drum, HP drum and our
chemicals mixing tank. Photos for the weight and conditions of the sample pieces were taken at the
presence of the client representative and kept for record.
1.4 Pre-flush
We filled the system with fresh water to remove all loose debris, dust, and any physical contamination in
the system. Flushing continued until all waters come from the system got clear and reached the
turbidity/TDS as per the procedure.
1.5 Degreasing
Introduced degreasing agent to remove all oil/grease from the system. Water heated to temperature 55
C. Quantity of 270 Liters of degreasing agent was added to the HRSG-22 for the degreasing.
Degreasing phase continued until no oil/grease was found while testing by oil/grease test strips.
1.7 Passivation,
Passivation was done by adding ammonia of quantity 16,600 liters to the existing solution until pH
adjusted to 9.0-9.5 in all sections vents, drains, and sampling points. Recirculation continued until we
ensured the pH is stable and consistent in the whole HRSG 22, then added 0.3 % sodium Nitrite and
continued recirculation until Nitrite stabilized.
After visual inspection passed, we flushed the system the ammoniated DM water from top side to
remove any residues. We flushed with the pH at 9 to 9.5.
2. Analytical Results:
Chemical cleaning was done as per the procedure, and during each phase, the required
testing/analyses were performed and recorded accordingly, all analyses are shown below in this
report (appendix-1)
3. Inspection:
3.1 Visual Inspection:
After completion of all chemical cleaning activities, steam drums were opened in 20.0918 at 04:30
am, kept open for ventilation and inspected visually by IES representative, then official inspection
done by the representatives of the concerned parties of the job (TIEJUN and SHINAS) in 20.09.18 at
10:30 pm and the visual inspection accepted by all concerned parties.
Please refer to the attached documents for the photos of Visual Inspection before and after the Chemical
Cleaning.
All sample pieces were checked visually by inspection attendees and they found all samples were
satisfactory to their standard. Samples then weighed, and weight recorded and found satisfactory as
well.
Please refer to the attached documents for the photos of weights of the sample pieces before and after
the Chemical Cleaning.
Appendix – 1:
1- Degreasing phase:
2- Acid phase:
Time Steel
Iron Citric
Date Hr Wool pH Temperature Remarks
Time ppm Acid %
count test
16.09 14:00 0 0 0 62 Steam boiler re-run
16.09 19:00 5 0 0 63 Adding acid inhibitor
16.09 21:00 7 0 0 ok 3.1 64 start dosing 3% of citric acid
17.09 24::00 10 400 3.5 ok 3 64 Test acid inhibitor
17.09 01:00 11 510 3.46 ok 3 64 Recirculation continues
17.09 02:00 12 600 3.43 ok 3.2 63 Dosing 3% of citric acid is complete
17.09 03:00 13 790 3.35 ok 3.7 64 Dosing of Ammonia
17.09 05:00 15 960 3.3 ok 3.5 65 Monitoring and testing
17.09 07:00 17 1240 3.26 ok 3.3 64 Monitoring and testing
17.09 09:00 19 1516 2.9 ok 3.4 64 Monitoring and testing
17.09 11:00 21 2010 2.85 ok 3.43 63 Monitoring and testing
17.09 13:00 23 2350 2.8 ok 3.4 64 Monitoring and testing
17.09 14:00 24 2600 3.1 ok 3.3 64 Monitoring and testing
17.09 15:00 25 2980 3.08 ok 3.45 63 Monitoring and testing
17.09 17:00 27 3300 2.29 ok 3.4 62 Monitoring and testing
17.09 19:00 29 3500 2.6 ok 3.4 61 Iron stabilizes
17.09 21:00 31 3540 2.52 ok 3.3 60 Iron Stabilizes
3- Passivation Phase:
10
CMS/JL-04/HRSG/018
CMS/JL-3/HRSG/018
CMS/JL-3/HRSG/018
CMS/JL-3/HRSG/018
ATTACHMENT NO.05
RISK ASSESSMENT
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
Likelihood
Likelihood
Final Risk
requirements
Severity
Severity
Number
Number
Person(s) with mechanism from with mechanism from
Risk
HAZARDS Hazard Effect To be
at risk hierarchy of control for each hierarchy of control for each
complied
identified hazard identified hazard
(Yes/No)
Task No.: 01-: Transportation of Materials Using Heavy Vehicles/ Equipment’s & & Mobilization.
• Failure of Personnel Workers/ Yes 1. Ensured all relevant valid 1 10 5 50 1) Maintain Safe Distance (at 1 10 1 10
Heavy injury / People Supervisors DM COSP DEWA PTW, DEWA LC and least 2mtr) from the
vehicles/In being run over Chapter -20 ESC permit are obtained moving vehicles &
adequate or crushed & prior to mobilization of Pedestrian access shall
strapping/ while As applicable Personnel, Plant & be separated.
Incompetent movement of Equipment. 2) Do not leave the vehicle
drivers/ heavy vehicles 2. Ensured all Employees unattended in running
operators/ may cause attend the ESC Site Safety condition.
Over fatality. Induction & mandatory 3) Shall Maintain SWL.
Speeding/ Property Internal training prior
Unknown damage mobilization.
location/ 3. Ensured Valid DEWA &
Unsecured ESC Entry Pass for all
load. material, personnel and
Vehicles & equipment’s as
per the DEWA & ESC
Security Procedure.
4. Only authorized and
competent operator/driver
has been deployed on site.
The driver and operator
Page 226 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
have valid UAE driving
license and heavy
equipment operator
physically fit & Required
Valid Third party for Heavy
equipment operator
5. Ensure the Availability of
material Shipment location
map.
6. Ensured the material stored
in proper location & free of
obstruction for access.
7. Ensured the transport
vehicles have adequate
capacity and Ensured loads
are Strapping Properly
before the transportation.
8. Ensured reverse alarm
functioning for all type of
vehicles. Ensure there is no
overtake and not use cell
phone while driving &
operations.
9. Follow the Site Speed Limit
& Ensured the Banksman/
escort vehicle while
movement of heavy
vehicles & equipment’s.
Dewa Security or Dewa
Escort pass holder only can
perform the Escort.
Page 227 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
10. Welfare facilities (Rest
shelter A/C, drinking water
station & ablution unit etc.)
has been in place.
11. Ensured proper and
Adequate PPE.
Task No.: 02 Un loading of Materials using Crane/ Forklift and other Lifting Gears.
*Failure of Personnel Workers, Yes 1. Ensured all relevant valid 2 10 5 100 1. Specific pre task TBT & 2 10 1 20
lifting Injury, Fatality/ operators DM COSP DEWA PTW, LC and ESC PTW. STARRT shall be conducted &
equipment/lifti Property and Chapter-21&22 2. Ensured approved lifting plan communicate the MSRA to the
ng tackles, Damage supervisors & available for 10 ton and above & work crew. Provision of MSRA
Crane As applicable communicated the approved copy in field.
collapse, lift lifting plan to work crew (Crane
jack failure, & Forklift operators, riggers, 2. Provision of trained &
unsafe Banksman’s, rigging supervisor competent banksman.
slinging and & helpers) through specific TBT.
rigging, 3. Shall undertake pre-entry 3. Provision of amber light and
Communicatio inspection of all Heavy Reverse alarm functioning for all
n Failure, No equipment’s by EMH EHS & crane, Forklift and all Heavy
lifting Plan ESC EHS & Shall affix the equipment’s and vehicles.
sticker by ESC EHS. Forklift operator shall wear face
4. Ensured All Crane, Fork lift & shield during chemical
Heavy Equipment have valid offloading.
UAE registration card & Valid
DAC approved third party 4. Do not leave the crane,
certification. Forklift or equipment in running
5. Ensured the crane operator & conditions.
Forklift Operator have valid UAE
driving license & competent 5.Comply with the DEWA
emergency procedure and ESC
Page 228 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
certified by DM approved third emergency response plan and
party institution. display DEWA emergency
6. Ensured crane, Forklift and contact numbers and control
heavy equipment operator room, Security numbers & ESC
physically fit. emergency numbers.
7. Ensured the competent
Rigger & Rigging Supervisor 6. Provision of visible safety &
have valid DM approved third restriction signage’s and safety
party certification is allowed to barriers to avoid un authorized
giving Signals to the Crane, entry.
Forklift and Other heavy
equipment’s.
8. Ensured all lifting tackles
inspected and tested by DAC
approved third party inspection
& DEWA monthly color code
system has been followed.
9. Ensured all crane, Forklift
lifting equipment clearly marked
with its SWL (safe working load)
and identification number.
10. Ensured fabricated and
Damaged lifting accessories not
used.
11. Ensured Using double Tag
line used for lifting.
12. Ensured the Load Secured
with forklift while Shift the
Materials and followed Site
speed limit.
Page 229 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
13. Ensured safe rigging
practices & not undertake any
short cut.
14.Ensured the area and access
for Crane, Forklift & all
equipment & checked that the
soil is of sufficient load bearing
capacity to undertake crane &
Forklift work.
15. Ensured not allowed People
to stand underneath a
suspended load.
16.Use of adequate PPE in
place.
Task No.03: Manual Handling
*Unskilled & Backache, Workers Yes 1.Mechanical aids (hydraulic 1 5 5 25 1.Provide Internal manual 1 5 1 5
untrained workers/ HAV, Slipped DM COSP trolley) has been used to lift handling training to the work
Unavailability of disc, Knee, Chapter-7.4.1 materials. crew.
ankle and & 2.Safe manual handling
mechanical
Shoulder, As applicable techniques have been adopted. 2.Conduct the pre task TBT and
devices/ Due to Personal 3. Sufficient space and safe communicated MSRA , COSHH
Ergonomical Injury, access prior to lift has been & MSDS to work crew.
Hazards, Lack of Inhalation, ensured.
knowledge about irritation Fire, 4.Ensured Never exceed 3. Ladders only to be used as
chemical, Exposure Eye damage. allowable load limit. means of access. No tools to be
to Chemical Dermatological .5. Ensured all Chemicals is carried up through ladder.
Mucous handled by a competent &
aerosols /acid /
membrane trained person with a sound 4.Comply with the DEWA
Spillage Infection & knowledge of the health hazards emergency procedure and ESC
respiratory associated with such chemicals. emergency response plan and
Problems for 6. Ensured all personnel has display DEWA emergency
Page 230 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
people with been completed the adequate contact numbers and control
allergies, Hazardous Substances in- room, Security numbers & ESC
chemical house training from ESC. emergency numbers.
splash 7. Ensured all chemical MSDS
and COSHH Risk Assessment
available in Chemical storage
area and Site location and it has
been maintained regularly.
8.Ensured employees handling
chemicals must wash their
hands and face after finishing
works.
9. Ensured Adequate PPE
(Chemical Resistant Gloves,
Half face mask & Face shield
and Rubber Boot, etc) provided
as per MSDS.
10. All Works has been
performed under the close
supervision.
Task No.04: Pre fabrication & Hot works (cutting, grinding & welding)
*Defective portable Fire, burn, Foreman/ Yes 1. Specific Hot work from DEWA 1 10 5 50 1.Conducting the pre task TBT 1 10 1 10
power tools inhalation, Supervisor/ DM COSP ESC PTW required and DEWA and communicated MSRA.
(welding machine, electrocution Engineer & Chapter- LC has been Issued.
may cause Workers 14,15&16 2.Hot works area is shielded 2.Ensure Civil Defense Certified
grinder etc.) /
fatality, & with fire retardant tarpaulin & fire fire watchman is available at hot
Unskilled workers, suffocation blanket to control the sparks and work area and need to check hot
As applicable
multiple power Ensured all combustible work area before the scope and
connections. material eliminated from hot need to stand by for 30 minutes
work locations, after the hot area.
3.Earthing is provided to close
Page 231 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
the welding area and welding 3.Unauthorized person’s entry
machine is grounded. restricted. Incompatible works
4.Ensured Suitable Fire not be allowed near the hot work
extinguisher has been provided. area.
5. Ensured Cylinder gauge and
regulator free from damage. 4. Follow DEWA and ESC
6. Ensured the proper cylinder emergency response plan and
key has been used and display DEWA & ESC
Fabricated or home-made emergency Team contact
cylinder key is not allowed to numbers and Security numbers.
use.
7. Non-returnable valves and 5. Provision of close supervision
Flashback arrestor are installed and Safety coverage.
in cutting set to gas cylinders
on each hose. 6. Provision of proper barrication
8. Ensure the hoses are free and adequate safety signage in
from any crack or damage. place.
9. Ensured crimping type hose
has been used in cutting set
and jubilee clamp is not allowed
to use in Cutting Set.
10. Cylinders are being kept
upright & tied off / kept in
trolleys and cylinder cap in
place and operational gap has
been provided (if it is required
only).
11. All welding machine &
Temporary generator is
inspected and color coded
12. Compliance of proper &
Page 232 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
adequate PPE.
Task No.: 05- Scaffolding and Work at height activities.
*Personnel fall & Serious Workers Yes 1. Ensured DEWA PTW, LC & 2 10 5 100 1.Conducting specific TBT to 2 10 1 20
falling object. injuries/ and DM COSP ESC PTW has been obtained communicate the MSRA to the
/Untrained Fatality Supervisors Chapter-8 prior to start work & Ensured work force before task. Ensure
scaffolders & Safe work platform provided the MSRA copy available in field.
As applicable with edge protection for
(scaffolds) and all work at 2. All personnel shall attend the
heights activities. ESC work at height training.
2.Ensured Double lanyard, full
body safety harness with shock 3. Working at height rescue
absorber has been used & team available on site &
100% tie off required above Coordinate with ESC ERT team
1.8mtr working at height to perform during high angle
activities. rescue from height and under
3.Ensured the soil stability and suspension trauma & mock drill
provided base plate for to be conducted.
scaffolding structures. 4. Provision of Adequate
4.Ensured Only competent warning signs.
scaffolders (certified by DM
approved third party institution) 5.Provision of First aider
perform for scaffolding erection available on site.
and Dismantling and
modification work. 6.Provision of tool Container to
5.Ensured all scaffolding avoid falling object while un
components suitable quality and bolting activity.
being in good condition and free
from corrosion or other defect. 7. All raising and lowering of
6. Ensured Adequate number of material to be carried out in a
ties and bracings has been controlled manner i.e. Hand to
provided to the scaffold. hand, by rope & pulley, fitting
Page 233 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
7. Ensured Scaffolds must have bag.
base plate even when setting on
a concrete floor. 8. Work at height activity shall
8. Ensured ladders Secured not be carried out during
with use of ladder clamp and its adverse weather condition like
only used for accessing heavy rain or wind.
location at height.
9.Ensured 3-point contact has 9.Provision of Close
been maintained. Supervision and Safety
10.Ensured competent Coverage.
supervisors-controlled Working
at Height works.
11.Ensured all Scaffolds are
inspected by scaffolding
inspector (certified by DM
approved third party institution)
prior to use.
12.Ensured No personnel
allowed to work directly below
the scaffold erection activities.
Area is barricaded and
eliminated unauthorized
personnel.
13.Ensured proper
housekeeping at higher
elevation platforms & no
stacking of material.
14. Ensured tool Lanyard used
to prevent the accidental fall of
tools.
Page 234 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
15. Ensured Never throw
materials or allow them to drop
(Bombing).
16. Ensured Suitable and
sufficient warning signage shall
be displayed for the awareness
and controlling of unauthorized
entry in work areas.
17.Compliance of proper &
adequate PPE.
18. Good Housekeeping.
Task No.06: Chemical and Hazardous Substances (if any).
*Incompetent Environmental Workers Yes 1.Ensured all Chemicals is 1 5 5 25 1.Good housekeeping shall be 1 5 1 5
persons/Lack of pollutions burn, DM COSP handled by a competent & maintained.
knowledge about Inhalation, Chapter18 trained person with a sound
chemical. Mixing of irritation Fire, & knowledge of the health hazards 2.Suitable warning signage shall
chemicals. Eye damage. As applicable associated with such chemicals. be provided.
Exposure to Dermatological 2. Ensured all personnel has
Chemical aerosols Mucous been completed the adequate
/acid / Spillage and membrane Hazardous Substances in- 3. Vacuum facility shall be used
Environment Infection & house training from ESC. instead of using blower for
Hazard. respiratory 3. Ensured all chemical MSDS cleaning purpose.
Problems for and COSHH Risk Assessment
people with available in Chemical storage 4. Conducting the pre task TBT
allergies, area and Site location and it has and communicated MSRA,
chemical been maintained regularly. COSHH & MSDS to work crew.
splash & body 4.Ensured employees handling
parts Injury. chemicals must wash their 5. Proper warning signage with
hands and face after finishing emergency contact number
Causes eye works. provided.
burns. May 5.Ensured all the chemical and
Page 235 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
cause other auxiliaries are stored in a 6.Emeergency Eye wash
chemical shaded, proper ventilated and Station Shall be provided.
conjunctivitis isolated from fire hazard.
and corneal 6.Ensured the storage is 7. Trained First aider available
damage checked on regular basis for in site.
any leakage or accumulation of
Contact with fumes. 8. Comply with the DEWA
liquid causes 7. Ensured Drip trays has been emergency procedure and ESC
severe burns provided. emergency response plan and
and ulceration. 8. Ensured No Smoking or any display DEWA emergency
May penetrate naked flames are strictly contact numbers and control
the skin and prohibited in the storage area room, Security numbers & ESC
cause severe and Signages in place. emergency numbers.
tissue and 9. Ensured Provision of Fire
bone extinguisher and Spill kit
destruction available on adequate location.
10. Ensured Adequate PPE
Inhalation: (Chemical Resistant Gloves,
Causes Half face mask & Face shield
chemical burns and Rubber Boot, etc) provided
to the as per MSDS.
respiratory 11. Eyes: Wear appropriate
tract. protective eyeglasses or
Inhalation may chemical safety goggles
be fatal as a 12. Skin: Wear appropriate
result of protective gloves to prevent skin
spasm, exposure.
inflammation, 13.. Respirators: A respiratory
edema of the protection is mandatory.
larynx and 14.. Wash thoroughly after
bronchi, handling.
Page 236 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
chemical 15.. Do not breathe dust, vapor,
pneumonitis mist, or gas.
and pulmonary 16.. Do not get in eyes, on skin,
edema. or on clothing.
Aspiration may 17... Do not ingest or inhale.
lead to 18. Discard contaminated
pulmonary shoes.
edema.
Depletes
calcium levels
in the body
which can lead
to
hypocalcemia
and death.
May cause
systemic
effects
Ingestion:
Harmful if
swallowed.
May cause
severe and
permanent
damage to the
digestive tract.
May cause
kidney
damage. May
cause
Page 237 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
perforation of
the digestive
tract. Causes
severe
digestive tract
burns with
abdominal
pain, vomiting,
and possible
death.
Inorganic
fluorides can
be harmful.
Acute
exposure to
fluorine
compounds
can lead to
digestive tract
burns, and
abdominal
pain. Fluoride
can reduce
calcium levels
leading to fatal
hypocalcemia.
May cause
systemic
effects.
Task No.07: Chemical Cleaning/Flushing activity in FG pipe lines.
Wrong Connection Damage Workers, Yes 1. Ensured DEWA PTW, LC 2 5 5 50 1. Shall conduct the pre task 2 5 1 10
Page 238 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
& incorrect routing property, Supervisor/ DM COSP and ESC LOTO permit has TBT and communicate
of hoses. Contamination Environme Chapter18 been obtained prior to start approved MSRA to work crew
/Unexpected & Personnel nt. & work. and keep the MSRA copy in the
/uncontrolled injury As applicable 2. Ensured valid Site note has work place.
release of been issued for chemical 2. Shall carried out any work
chemicals or cleaning/flushing works. over or near where cleaning
flushing medium/ 3. Ensured Only trained and flushing is being conducted.
Improper filling Competent person perform the 3. Carbon Steel/ GRP line tank
system / Task under proper and shall be used for mixing and
Overflowing or competent supervision. filling works. Provision of Proper
spillages of 4. Ensured Pump skid, mixing access to the Tank.
chemicals. tank, chemical dosing pump, 4. provision of Flow metre level
water transfer pump, water to avoid over flow in Storage
tanker, Air Compressor etc., Tank.
has been place correctly as 5. All personnel shall have
mention in correct as per "Stop Work" authority whenever
Method of statement and Lay there is concern for safety
out. during Cleaning operations.
5. Ensured Air compressor/ 6. PH level (as per MS) shall
manifold and gauges are not exceed. If it is exceeding, It
calibrated and Certified by will be neutralizing by Manual
approved third party. Dozing Pump.
6. Ensured safety wipe check 7. Provision of adequate in-
has been provided in all air house training from ESC for
compressor hose connections. Hazardous Substances,
7. Ensured Pump skid, mixing working in operational area &
tank, chemical dosing pump, LOTO.
water transfer pump, Hoses, 8. Chemical cleaning/Flushing
Boiler , Gauges and Fittings in progress signages, hard
(coupling) having Technical barricades or other protective
Data Sheet and has been barriers shall be placed in a
Page 239 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
inspected and monthly color manner and Adequate
code in place. watchmen shall be provided to
8. Ensured all hose coupling avoid the Unauthorized entry.
joints having lock pin (used for Provision of Safe zone to
additional secure) and PVC drip protect personnel and the public
tray has been provided in all from unanticipated pressure
hose coupling joints and Ensure release or equipment failure.
all hoses and hose fittings are 9. Never tighten connections
free from crack/damage. that are under pressure. If a
9. Ensured the physical Pre leak develops, you must
inspection has been conducted depressurize to a safe level and
with the DEWA, ESC team then re-tighten.
before the cleaning/flushing 10. Ensure that the pipeline and
activities. equipment will not exceed its
10. Ensured adequate Vents maximum pressure as
has been installed as per MS. mentioned in MS Additional 5%
Ensured the vents are open (if capacity and pressure gauges
required) during water filling. shall use for cleaning/ flushing
Vent relief valve and gauges purpose.
has been certified. 11. If require Valves shall be
11. Ensured Drains and vent of Isolated and LOTO procedure
all instrument manifold has shall follow, proper scaffold
been open to avoid over shall built over the fence for
pressurization (if required). hoses crossing or routing
12. Ensured continuous purpose and Fencing and
monitoring of both end and of surrounding area shall be
all joint for any leakage of isolated and Ensure the Proper
pressure / failure. drainage system in place.
13. Ensured No repair and re 12. The pressure pump/air
works made while line under compressor shall be attended
operational. constantly by an authorized
Page 240 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
14. Ensured Do not holding or person.
increasing the pressure more 13. DM approved Certified fire
than stipulated time as watchmen’s shall be provided.
mentioned in method 14. All chemical flushing water
statement. Shall be disposed off through
15. Ensured all chemical MSDS DEWA/DM approved disposal
and COSHH Risk Assessment vender and disposal certificate
available in Chemical storage shall be submitted to
area and Site location and it ESC/DEWA.
has been maintained regularly. 14. Shall follow the DEWA
16. Ensured all the chemical emergency procedure and ESC
and other auxiliaries are stored emergency response plan and
in a shaded, proper ventilated display DEWA emergency
and isolated from fire hazard. contact numbers and control
17. Ensured No Smoking or any room, Security numbers & ESC
naked flames are strictly emergency numbers.
prohibited in work location and
storage area.
18. Ensured all the system has
been depressurized before
leaving the site
19. Ensured Adequate Fire
extinguisher and Spill kit has
been provided
20. Ensured Adequate PPE
provided as per MSDS.
Task No.08: Temporary Electrical power supply and use of Hands and Power tools
*Manual handling/ Personnel workers Yes 1. Ensured All Electrical Power 1 10 5 50 1. Conducting specific TBT to 1 10 1 10
Potential pinch injury, DM COSP tools has been inspected communicate the MSRA to the
points/poor Electrocution Chapter monthly and color coded by work force before start the
posture/potential may cause 7.4.1, authorized electrician. task.
Page 241 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
works at height and fatality, hand Chapter14 &16 2. Ensured undertake daily 2. Power tool guards must be
fall/ falling object/ injury, cut, & inspection for DB with using correctly fitted before use. The
electrocution abrasions, As applicable checklist and its recorded. speed of grinding machines
muscle, 3. Ensured conducted the Prior must be properly governed and
strains, burn, inspection & affix the sticker by checked. The maximum (RPM)
fire &Property the ESC EHS. DEWA/ESC should be marked on the tool.
damage monthly color code & inspection Only the correct disc should be
process is followed. fitted for the grinder in use. Fit
3. Ensured all electrical power grinding discs properly. The
supply through 30mA RCD and source of power must be
Grounded. isolated from power-driven
4. Ensured using insulated & tools.
right tool for right job. 3. Use of approved industrial
5. Ensured Operatives is aware sockets.
of potential pinch point and
using of Proper PPE. 5.provision of Fire points with
6. Ensured all damaged tools suitable Fire extinguisher. (
has been segregated & returned CO2 ).
to store for disposal. 6. Always Follow the LOTO
7.Eusured un attended power system.
tools has switched 7. Provision of Suitable earthing
off/disconnected & all tool has for all temporary power supply
been stored in tool kits when equipment.
not required.
8. Ensured not using 8. All Site DB boxes to be kept
Homemade & Fabricated tools. padlocked. All tools
9. Ensured hand tool has disconnected from electrical
lanyard for prevent the falling supply prior to cleaning /
object. servicing etc.
10. Ensured trained &
Authorized personnel has been 9. Hazard Signage to be placed
Page 242 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
complete the Electrical DB and on all Electrical panels and
Power Installation under Display the Contact number of
supervision of competent Authorized electricians.
electrical supervisor.
11. Ensured using 220/110-volt
power tools with Dead man
switch.
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
shelter & Cool Headache, Guideline adequate water coolers/cool and shady area.
water Nausea, & water and using fans or Air 3. Do not leave the person
Cramp, Rapid As applicable conditioning. alone. If person is
weak Pulse 3. Ensured Provision of unconscious, do not give them
and breathing, mechanical aids-where possible water.
Loss of to reduce the physical work 4.Continue to cool their body
appetite rate. temperature until medical
4. Ensured Scheduling works assistance arrives and they can
Fatal or serious
only when the temperature is be taken to a medical facility for
health effects below asset level or at cooler further cooling and monitoring
times of the day and Increased of body temperature and
the work rest cycles. functions.
5. Ensured No alone working 5.Monitor the condition of your
and Avoided direct sun light co-worker periodically.
exposure. 6. Heat related illness could
6. Ensured Buddy System has cause a person to become
been maintained. confused or loss of
7. Ensured enough cool consciousness. A close
water/drinks is available in the supervision by a competent
workplace and encouraged supervisor is warranted during
workers to drink it frequently.is entire activity.
small amount even if not feeling 7.All workmen should aware
thirsty. Encourage them to about sites facility and
increase the salt intake with emergency contact numbers &
meals than usual. Provision of Internal awareness
8. De hydration Urine Chart training & Tool box talk about
has been displayed in the toilet Heat stress to workers/
& welfare facility area. Especially new workers.
9. Adequate electrolytes and 8. Reduce the working hours.
(ORS) & Hygienic ice cube for Assign two groups shift wise for
Cool water has been provided. a particular job. Personal
Page 244 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
9. First Aid/ Medical facilities cooling systems and breathable
shall be available all the times fabrics which helps workers in
at work site. hot environments. Providing
10. Ensured Complying with periodic rest breaks with cool
DM Mid-day break Schedule. refreshment and rest facilities in
11. Ensured Provision of Air cooler conditions.
conditioner rest room during
Mid-day break hours.
Task No.10: Waste Management & House keeping
*Lack of Training/ Slip/Trip and workers Yes 1. Ensured Conducting the pre 2 5 5 50 1.Conducted TBT & awareness 2 5 1 10
Cultural behavior Falls, Fire DM COSP task TBT performed. training to the works force about
Chapter_ 3.17 2. Ensured segregate the waste management system.
& Electrical & mechanical
As applicable dismantling material and 2. Provision of housekeeping
properly stacked and team.
barricaded the area in permitted
place. 3. Display the Proper
3. Ensured Using mechanical label/signage in all waste skip in
Devises to avoid manual multi languages.
handling.
4. Ensured Proper & valid 4. Provision of close food waste
material Exit pass required for skip.
removing the materials from
site. 5. All Chemicals and
5. Ensured Kept the work area Contaminated Shall be
neat and clean. disposed off through DM
6.Ensured Access routes is approved disposal vender and
clean from all obstruction to managed as Per project CEMP
avoid chances of slip, trip and
fall.
Page 245 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
7. Ensured Maintaining proper
cable management.
8. Ensured Provision of
adequate skip for Food /
General plastic and paper
waste.
9. Adequate PPE Has been
Used As per MSDS.
Task No.11: Emergency Response
* Unauthorized Severity of All Yes 1. Ensured the pre task TBT 2 10 1 20 1.Close supervision required all 2 10 0.5 10
entry into the Illness will employees DM safe & performed and Introducing the the times.
existing operational increase if not Healthy first aid team.
area. given Guidelines 2. Ensured Strictly Following 2.Restricted the Unauthorized
* Lack of training immediate & the DEWA emergency entry.
and Awareness/ medical As Applicable procedure and ESC ERT team
fire, toxic gas attention & 3. Adequate fire point and
plan & displayed DEWA
release/chemical fatality Emergency spill shall be
spill, workplace emergency contact numbers, provided.
violence control room, Security numbers
& ESC emergency numbers.
3. Ensured Emergency access
way maintained clear at all
times.
4. Ensured All the workers has
been trained for emergency
plan procedures.
5. Ensured MSRA & MSDS
provided and communicated to
work force.
Page 246 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
6. Ensured and Informed the
evacuation procedure and
Assembly point location to work
Crew.
Task No.12: Night working activities (If applicable)
*Improper Slip and Trip Site Yes 1. Ensured PTW obtained from 2 5 5 50 1. Provide more supervision to 2 5 1 10
illumination, Body injury Workers/ DM Technical Dewa for the night work ensure workers are more
workers fatigue. muscle strain Supervisor Guidelines activates. closely monitored.
GU-66 2. Ensured Authorized
& Supervisor responsible for the 2. Avoid assigning complex
As Applicable adequate lighting provided on tasks to night shift.
working area.
3. Ensured Lighting has been 3. Approved first-aider must be
comfortable and not exposed available in case of emergency.
employees or surrounding for
disturbing glare. 4. Additional emergency vehicle
4. Ensured Lighting fixture should be kept in standby.
suitable for the area as installed
5.Ensured Job rotation
implemented and break given
on regular intervals
6. Ensured First aid facilities
and oral rehydrates such as
Cold Drinking Water, Tang,
Glucose etc
7. Ensured Avoid alone
working.
8. Ensured Minimum 100 lux
illumination provided.
9. Ensured EHS coverage shall
be available full time.
Page 247 of 249
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B
Notes :
Project Name: AWEER Power Station "H" Phase IV Assessment Date: 02/05/2021
Activity/Area/Equipment: Method statement & Risk Assessment for Chemical Cleaning of Ref. No.: 3761800008-E-08-M-E-65750_A
Fuel gas line at UEN by Mono-phase Circulation method/As listed in MS
Assessor(s): Sumit Bajpai (Site Engineer)/ Fredrick (Safety Officer) Rev Date:
Reviewed By: Karthikeyan (Site Manager) Next Rev Date:01/11/2021
Rev.No .A
SP06: Annexure III B