Subject: Slow Progress at Available Work Fronts – Delays due to reasons out of control

Dear Sir,

1. Analysis based on approved Clause 8.3 Programme:

This delay is according to the clause 8.3 Programme without incorporating our notices to claim and claim final
submissions with Extension of Time attributed to various delays caused that are beyond the control of the
contractor. If these delays are considered, we are not delayed in any work.

A detailed analysis of the negative variance derived by using Clause 8.3 programme is shown below;

Planned Actual Variance


Items Major reason of Delay
% % %
Part 7 - Works for - Delayed appointment of nominated Sub-contractor by
3.20% 2.00% -1.20%
WD the Engineer / Employer
Delayed appointment of nominated Sub-contractor by the
Part 8 - Works for
0.40% 0.40% 0.00% Engineer / Employer – However we have expedited and
ED
recovered the delay due to this event till date.
- New NDRC Requirement at City Road led to delays in
Part 9 - Irrigation
1.10% 0.99% -0.11% additional NOC and new sub-contractor approval
Works
procedures
- Drainage system yet to be finalized by the Employer –
Part 12 - soak away works could not be commissioned due to delay
1.60% 0.61% -0.99%
Drainage Works in the decision by the Employer / the Engineer.
- Till date final decision not received.
- Decision of changing all the Luminaires in the project
Part 16 - Road issued in December 2017, 9 months after project start.
2.40% 2.30% -0.10%
Lighting Works - Delay in finalization of supplier for LED Luminaires by the
Employer
- Delay due to rejection of relocation of existing 900mm
Part 17 - dia Water line as required
10.80% 0.08% -10.73%
Underpass Works - Additional requirements and procedural delays for
Traffic Diversion approvals

Part 18 - Bridge - Delay due to relocation of existing Irrigation line –


3.57% 3.36% -0.21%
Works - BR-1 variation work

- Delay caused due to instruction from the Employer / the


Engineer to delay commencement, on the understanding
that complete closure of underpass shall be approved.
Part 21 - Camel
0.50% 0.13% -0.37% - However, the final decision issued to complete the work
Crossing No. 3
with lane by lane closure.
- This has led to redesign of formwork and traffic
diversion and delayed the commencement of the work.
Part 22 - Bridge
Works - Junction-
8.44% 9.61% +1.17%
2-BR-1, BR-2, BR-
3 & BR4
Part 23 - Bridge
Works - Junction- 4.25% 4.35% +0.09%
3-BR-1 & BR-2

As can be seen from the above table, is from Waterworks delay, Drainage works delay and Underpass works
delay (Delay due to Design changes, waterworks relocation and Traffic Diversion approvals). Hence, most of

Page 1
the total variance is from these three items. The contribution of all other areas to the negative variance is
negligible, which clearly indicates that we are performing the activities according to the plan.

2. Analysis based on submitted Claims:

as on 6th October 18, Planned Progress of works is 62.47% with a variance of +6.93%.

So it is clearly evident from the above details that wherever front is available without any hindrance,
contractor showed good progress and major reasons for the variance in the progress is beyond the control of
the contractor, for which the Extension of Time Claims have been submitted.

This is for your information and record.