Discipline

Percentage Deviation from the Planned Schedule

Review

Now Sub-Contractor is ahead of the Planned Schedule by 0.31%. Sub-Contractor could have achieved another 0.40% of Progress if the Foundations V-237-004A/B, V-237-005A/B, V-2371 - Equipment FDN 0.31% 011A/B, V-237-012A/B, V-231-004 A/B, V-231-005 A/B, V-237-006, V-237-007, V-237-009,V-235-002 were released which one still under hold due to Sub Pipe Rack-4,6,78,9and AIR COMPRESSOR SHELTER-AE. In this regard please refer to Sub-Contractor Weekly Report No # 9 dated 28.5.2011 Item # 10(Area of Concern) and letter # 090768/L/ND-1156 dated 07.08.2011.

- Equipment Structure FDN

-0.31%

Sub-Contractor accepts the delay.

Shelter for C-231-001-A (Structure-Y) 4 Numbers footings, Shelter for C-231-001-B (Structure-Z) 3 Numbers footings, Shelter for C-235-001-B (Structure-AC) footings is under Hold due 3 - Shelter FDN -0.29% to interference of Sub Pipe Rack-6,7 and 9 contributing 0.25% slippage.

- Other FDN (Hydrant, Pit, etc.)

Not Applicable

- U/G Concrete Structure

-1.43%

Due to lack of enough confined space manpower Sub Contractor accepts the delay.

Sub Contractor received Revised AFC Drawings for Only AOC Lines on 13.09.2011 U/G Piping Works But the Company is not allowing Sub Contractor to carry out civil works unless the 6 - Civil work for U/G Piping -3.76% Issued AFC Drawings are Approved by Company .In this regard please refer to Sub-Contractor Weekly Report No # 22,23,24 dated 20.8.2011, 27.8.2011, 03.09.2011, 10.9.2011, Item # 10(Area of Concern) and Contractor MOM # 090768/MW/DN/021, MOM # 090768/MW/DN/020, Dated 29.08.2011, 22.08.2011 respectively - Item # 3 in QA/QC.

- Manhole & Catch Basin

-0.05%

Sub Contractor Received Revised AFC Drawings for Only AOC Lines on 13.09.2011 and Already 5 Numbers Manholes are casted as on 20.09.2011 ,The delay accumulated due to the holds in the past.

Page 1 of 1