Professional Documents
Culture Documents
Page 1 of 2
25 June 2020
XXX
Municipality of XXX,
Province of XXX, Philippines
Moreover, Subcontractor reiterates that this work is not to be executed under similar
conditions as any other item in the Contract. Since the project is already operational,
Subcontractor is only given limited time (night) and space to undertake the works which
lead to high difficulty and prolonged duration. Kindly note that, the consideration of
XXX/OP-7174-122-19
Page 2 of 2
Subcontract rates is at the given normal condition of the implementation of the process
and such external factors are not involved.
Notwithstanding the above, Subcontractor hereby informs the Contractor that such
provision of additional items cannot be complied and executed by the Subcontractor
with the following reasons:
Further, original works for CCTV System has been completed and operational at
Site. Also, functionality test has been carried out and pre-commissioning test is
to be undertaken. Hence, these instructions would require repetition of test and
documentation process.
2. Demobilized Equipment
It has come that Subcontractor considered to demobilize the necessary
equipment utilized for the original scope of work since such scope was already
completed and served at site.
Project Manager