BAR CHART FOR SFG WASHING LINE

Name Of Work: Subedarganj-provision of two no. washing pit lines of 26 coach length each with 01 stabling line of equal length at Subedarganj Railway Station with connected works like stabling lines, hydrant lines, track
work, C&W building and other misc. works.

Name & Address of Contractor: AKANSHA KIPL JV, 38/1/35,Lowther Road, Tulsiani Enclave, George Town, Allahabad-211002.

Agreement No.: 75-W/230/DY CE/C/ALD dated: 31.08.2018

Total Progress Balance % Progress


S.No. Activity Unit upto scope on of work till Apr'22 May'22 June'22
Scope 31.03.2022 01.04.2022 date

1. Earthwork from BMU End to Bridge No.41 Cum 55000 47000 8000 85.45% 4000 4000
2. Minor Bridge No.41,42,43 No. 3 3 NIL 100.00%
3. C&W Building No. 1 1 NIL 100.00%
4. 11 KV Electric Substation No. 1 1 NIL 100.00%
5. Washable Pit Line ( 02 nos. X 26 coach ) No. 2 2 NIL 100.00%
6. Ballast Work. Cum 7300 2400 4900 32.88% 2600 1150 1150
9. Track Linking over Washing Pit Line Metre 1160 1160 NIL 100.00%
10. Track Linking Metre 2740 NIL 2740 0.00% 400 660 1680
11. T/O Linking No. 6 NIL 6 0.00% 2 2 2
12. Derailing Switch Linking No. 3 NIL 3 0.00% 1 1 1

NOTE:
1. Track linking work of new shunting neck and Earthwork from existing shunting neck dead end towards Tower wagon shed will be completed as per the progress of removal of obstruction such as OHE Mast, S&T location boxes,brick
masonry duty hut,etc. from Bridge No.42 to SFG End.

Washing Pit Line SFG Financial Status as on 31.03.2022

S.No. Details Amount


1. Agreement cost of work : 184921282.00
2. After 3rd variation cost of work 241753833.00
3. % of variation from agreement 30.73%
4. Total Payment till date 31.03.2022 191259929.00
5. Balance Amount 50493904.00