You are on page 1of 18

Respon

sibilities
Legend SITE TEST REPORT DATE : 3/08/2017
CSD
Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 1 of 18
T12
GENERAL INFORMATION.
TRANSFORMER NAME PLATE DETAILS:
Serial No : 024041501
Make : ELSEWEDY TRAFO Rating Power : 20 MVA
Rated Voltage : 33/13.8 KV Rated Current : 349.91/836.74 A
Number of Phases : 3 Standard : IEC 60076
Rated Frequency : 60 Hz Type of Cooling : ONAF
Vector Group : YN yn0 Oil Temperature Rise : 45C
Winding Temp Rise : 50 C Design Ambient Temp : 55 C
Total Mass : 37500 Kg Total Mass : 137500 Kg
Transport mass with Oil : 32100 Kg Mass of Oil : 9000 kg

TAP CHANGER POSITION 5


SHORT CIRCUIT IMPEDANCE 7.95 %
REFERENCE POWER 20 MVA
TAPPING RANGE 33 KV (33(+4&-7)X1.43%)/13.8KV

HV LV
TAPPING VOLTAGE CURRENT(A) VOLTAGE CURRENT(A)
POSIION V V
20MVA 20MVA
1 34888 330.98
2 34416 335.52
3 33944 340.18
4 33472 344.97
5 33000 349.91
6 32528 354.98 13800 836.74
7 32056 360.21
8 31584 365.69
9 31112 371.14
10 30640 376.85
11 30169 382.75
12 29697 388.83

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 2 of 18
T12

INSULATION LEVEL
1 H.V LINE TERMINAL L1/AC KV 170/70
2 H.V NEUTRAL TERMINAL L1/AC KV 170/38
3 L.V LINE TERMINAL L1/AC KV 95/38
4 L.V NEUTRAL TERMINAL L1/AC KV 95/38

MECHANICAL CHECK AND VISUAL INSPECTION.


ITEM DESCRIPTION DONE REMARKS
1 Check the impact Recorder for any abnormal impact during transit. OK
2 Check all components are installed. OK
Check quality of paint, lifting lugs, quality of weld areas rust spots and wheel OK
3
stoppers.
4 Check nameplates information ( visible place )as per contract specifications OK
5 Check tightness of all bolts (torque wrench method). OK
Check that all groundings are securely connected. OK
6 (at least two grounding points to main tank are available)
7 Check that the piping to Buchholz relay has proper slop. OK
8 Check that the tank pressure is positive.( if applicable ) OK
9 Check the valves between the tank and radiator (To be open). OK
Check the HV LV and Tertiary (if applicable) bushing for any damage and OK
10
completeness.
11 Check the color (to be blue) and quantity of silica gel in breather and oil pot level. OK
12 Check heaters and humidity meters in local panel at correct setting. OK
13 Check phase marking in cable box and it should match with GIS and cables. OK
14 Check all pipes hoses and fan protection (not rubber or plastic). OK
Check the vertical horizontal clearances of live parts to adjacent grounded point to OK
15
conform standard.
16 Check integrity of diaphragm / air bag in the conservator. OK
17 Perform all of the manufacturer specific checks. OK
18 Check labeling of all auxiliary devices as per approved drawing. OK
19 Check proper operation of all auxiliary devices as follows :
a. Tap changer ( upper lower out of step and interlock)
b. Oil level gauges.
c. Top oil temperature gauges.
d. Winding temperature gauge
e. OLTC Oil / Gas surge (pressure) relay.
f. Pressure relief device.
g. Push buttons and indicators.
h. Oil sampling port (main tank & OLTC).
i. Upper and lower main tank valves.
j. Tap changer diverter switch compartment, oil filtering pumps and filter in
good condition (if available).

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 3 of 18
T12
k. Cooling fans / pumps (for all settings).
l. Buchholz relay
20 Check Oil leakage by applying 0.35kpa over pressure for 24 hrs. OK
21 Check that the sampling devices are reachable. OK
Check oil level in main tank, conservator, tap changer tank and bushing etc. test the OK
22
oil level gauges and their alarms.
23 Bleed trapped air at the bushing turrets and tank top. OK
24 Check flow of oil in flow meter in correct direction and proper rate (if applicable ) OK
25 Check all external wiring for correctness and tightness. OK
Check on line insulating oil dissolved gas and ,moisture monitoring system OK
26
(if installed )
27 Check pocket of temperature sensors have oil inside OK

ELECTRICAL TESTS:
ITEM DESCRIPTION DONE REMARKS
1. Core insulation resistance test. OK
2. Winding insulation resistance test and Polarization Index test at 5 kV DC. OK
3. Winding resistance test (all taps). OK
4. Excitation current measurements test at 10 KV. OK
5. Insulation power factor and bushing test at 10 kV AC. OK
6. Vector relationship test. OK
Winding temperature device test by heating the sensor in oil bath . Also check OK
7.
by current injection. Setting as per approved drawing to be applied and tested.
Oil temperature device to be calibrated by heating in oil bath. Setting as per OK
8.
approved drawing to be applied and tested.
9. Percentage Impedance test (at Low, Normal and High taps.) OK
10. Turns Ratio Test.(all taps). OK
11. Magnetic Balance Test. (at Low, Normal and High taps.) OK
On load tapchanger tests : OK
a. Check current and voltage ratings of Tap changer motor.
b. Raise/Lower control (Local remote) and indication , and perform
adjustment as required.
c. End of tap travel control.
d. End of winding travel control (both ends).
e. AVR setting of bandwidth, mid point, time delay , etc., and adjust as per
approved setting.
12.
f. Master/ Slave check out of step blocking alarm.
g. Master/ Slave control check either transformer as master.
h. Parallel operation Disturbed check alarm.
i. Check that the windings are not open circuited during tap changing.
This should be done during the winding resistance test.
13. Cooling System Check. OK
Check for current and voltage ratings of all motors for tap changer and fans OK
14. match to SEC standard supply. Check that MCBs for protection are set at proper
overload settings.
DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 4 of 18
T12
Fan motor currents shall be measured and checked against rating. Check wiring OK
15.
size is adequate to carry the current.
Check that the phase sequence of supply voltage to fan motors is correct. Check OK
16. fan rotation direction and confirm and air flow is towards Radiator.
MCBs in cooler control cubicle to be checked by current injection for alarm and OK
17.
trip.
Bushing current transformer tests : OK
a. Polarity.
b. Insulation resistance.
c. Secondary winding resistance (all windings and all taps).
d. Current Ratio (inject current).
18. e. Magnetization Characteristics (Minimum five points below and two points
above the knee point).
f. Verify secondary circuits, terminal to terminal.
g. Burden test.
Demagnetize CT cores after all tests. Ensure no open circuit on CT
secondary side.
Functional checks for the following : OK
a. Liquid level (alarm and trip).
b. Top oil temperature device: fans/ (stop, start alarm and trip).
19. c. Winding temperature Device.
d. Buchholz Relay (alarm and trip).
e. Oil/ Gas surge (pressure) relay (alarm and trip).
f. Pressure relief device (alarm and trip).
Insulating Oil Tests : OK
Prior to energization , the contractor shall submit insulating oil test reports
tested at an independent laboratory , for the following :
a. Dielectric strength
1. ASTM D 877 (2.5 mm gap) for unprocessed oil and for OLTC oil.
2. ASTM D 1816 (1.0 mm gap) for oil in Main tank.
b. Acid Neutralization Number (ASTM D 974).
c. Interfacial Tension (ASTM D 971).
20. d. Color (ASTM D 1500).
e. Moisture content (ASTM D 1533).
f. Power Factor Test (ASTM D 924).
g. Dissolved gas in oil Analysis (ASTM D3 612).
H. Dielectric dissipation factor, resistivity, sediment and /or perceptible
sludge.
Another Oil sample shall be given to SEC transmission for their own
analysis and comparison purposes. Asyringe oil sample shall be taken by
contractor.
A Main tank insulation Oil sample for dissolved gas analysis shall be taken OK
immediately prior to first energizing
21.
a power transformer and another sample three days after continuous
energization.
ELECTRICAL TEST:

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 5 of 18
T12

1. CORE INSULATION RESISTANCE MEASUREMENT


Oil Temperature:- 25
Amb. Temp. : 25

Voltage applied : 1000 V DC Acceptable Value: - 200 M OR Above

CORE TO EARTH FRAME TO EARTH CORE TO FRAME

2. WINDING INSULATION RESISTANCE MEASUREMENT:

Oil Temp : 25 C

Amb. Temp : 25 C

Voltage Applied : 5000 V Acceptable Value: - > 200 M

MEASURED INSULATION RESISTANCE (G)


TIME
HV EARTH( LV GROUND) LV EARTH (HV GROUND) HV LV
1 Minute
10Minute
PI=10min:
1 min:

Acceptable Value for Polarization Index = Not less than 1.25

Equipment Used : Insulation Resistance Tester


Make :
Model No. / Sl. No. :
Calibration Date :
Next Calibration Date :

3. VECTOR RELATIONSHIP TEST.


DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 6 of 18
T12

Vector Group of Transformer : YNyn0 Oil Temp. : 21


Amb. Temp. : 25
Transformer was excited from H.V. winding with a suitable Low three phase power supply and Vector Group checked.

VECTOR RELATIONSHIP TEST.


Vector Group of Transformer : YNyn0
Transformer was excited from H.V. winding with a suitable Low three phase power supply and Vector Group checked.
Short 1U and 2U in transformer.

VECTOR DIAGRAM PLOT 1U,2U

2N

2W 2V

1N

1W 1V

MEASUREMENT: TAP NO: 1

1U-1N 1V-1N 1W-1N 1U-1V 1V-1W 1W-1U 2U-2N 2V-2N 2W-2N

1U-2U 1V-2U 1W-2U 1N-2U 2U-2V


1U-2V 1V-2V 1W-2V 1N-2V 2V-2W
1U-2W 1V-2W 1W-2W 1N-2W 2W-2U
1U-2N 1V-2N 1W-2N 1N-2N
Relationship required

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 7 of 18
T12

MEASUREMENT: TAP NO: 5

1U-1N 1V-1N 1W-1N 1U-1V 1V-1W 1W-1U 2U-2N 2V-2N 2W-2N


123.6 124.3 124.6 213.8 215.3 214.5 51.53 51.74 51.87

1U-2U 1V-2U 1W-2U 1N-2U 2U-2V


1U-2V 1V-2V 1W-2V 1N-2V 2V-2W
1U-2W 1V-2W 1W-2W 1N-2W 2W-2U
1U-2N 1V-2N 1W-2N 1N-2N
Relationship required

MEASUREMENT: TAP NO: 12

1U-1N 1V-1N 1W-1N 1U-1V 1V-1W 1W-1U 2U-2N 2V-2N 2W-2N

1U-2U 1V-2U 1W-2U 1N-2U 2U-2V


1U-2V 1V-2V 1W-2V 1N-2V 2V-2W
1U-2W 1V-2W 1W-2W 1N-2W 2W-2U
1U-2N 1V-2N 1W-2N 1N-2N
Relationship required

Equipment Used : Multimeter


Make : Fluke
Model No. / Sl. No. : 179/ 23350081
Calibration Date : 25/03/2016
Next Calibration Date : 24/03/2017

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 8 of 18
T12
1. WINDING TEMPERATURE INDICATOR TEST

A. CALIBRATION BY CURRENT INJECTION (THERMAL IMAGE TEST)

METHOD:
1. Connect the current injection source on the heater element of winding temperature.
2. Note the initial temperature of winding temperature indicator before any injection.
3. Inject the full load current (secondary value) in the heater element of winding temperature indicator.
4. Keep on injecting the full load current for 40 minutes and observe the increase in temperature at regular intervals (5
minutes).
5. Note the value of temperature after 40 minutes.
6. Calculate the temperature increment by subtracting the initial temperature value from the 40 minute reading.
7. Compare this temperature increment value from the manufacturer data.

DIAGRAM:
Built in Variable Resistor

Current Injection
Source
Heater Element

Winding Temperature Indicator

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 9 of 18
T12
WTI H.V TYPE OF TEMPRATURE GAUGE: AKM-35

Instrument : SINGLE PHASE RELAY KIT


Make : MEGGER
Model No/ Sr. No : SVERKER 780/ 1301356
Calibration Date : 25/11/2016
Calibration Due Date : 24/11/2016

CT RATIO:

Full Load Secondary Current, I1= 2 A


HEATER TEST
Heater Current, I2 = 2 A
INJECTED FULL LOAD CURRENT 2A
I2 / I1 = 450/ 2A
INITIAL TEMPRETURE READING 25 C

STEADY TEMP. AFTER 40 MINS 50 C


TEMPERATURE INCREMENT 25 C

CT RATIO:
WTI L.V
HEATER TEST
Full Load Secondary Current, I1=2 A
INJECTED FULL LOAD CURRENT 2 Amp
Heater Current, I2 = 2 A
INITIAL TEMPRETURE READING 25 c
I2 / I1 = 900/ 2A
STEADY TEMP. AFTER 40 MINS 50 c

TEMPERATURE INCREMENT 22 c
B. CALIBRATION OF SENSORS BY HEATING TYPE OF TEMPRATURE GAUGE: AKM-35

Instrument : Drywell
Make : Fuke
Model No : 9140
Calibration Date : 05-09-2015
Calibration Due Date : 04-09-2016
S. No. : B39281
Each sensor will be heated in the heating calibrator and compare and recorded with the instrument reading.

REF. TEMP. C
WTI H2
WTI X2
DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 10 of 18
T12

FUNCTIONAL TEST

OPERATION
DEVICE FUNCTION SETTING REMARKS
PICK UP DROP OUT
Start Air Fan OK
WTI(HV) Alarm OK
Tripping OK
OPERATION
DEVICE FUNCTION SETTING REMARKS
PICK UP DROP OUT
Start Air Fan OK
WTI(LV) Alarm OK
Tripping OK

Criteria : Pickup value shall be within 1%

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 11 of 18
T12
2. - OIL TEMPERATURE INDICATOR TEST
B. CALIBRATION OF SENSORS BY HEATING TYPE OF TEMPRATURE GAUGE: AKM-34

Instrument : Drywell
Make : Fluke
Model No : 9140
Calibration Date : 05-09-2015
Calibration Due Date : 04-09-2016
S. No. : B39281
Each sensor will be heated in the heating calibrator and compare and recorded with the instrument reading.

REF. TEMP. C
OTI

FUNCTIONAL TEST
OPERATION
DEVICE FUNCTION SETTING REMARKS
PICK UP DROP OUT
Start Air Fan OK
OTI Alarm OK
Tripping OK
Criteria : Pickup value shall be within 1%

3. COOLING FAN FUNCTION CHECK


Meter used : Leakage Tester
Make : Fluke
Sl.No : 3325010
Calibration Due Date : 3/03/2016
Fan Motor Rating : 0.75kw

Current ( A ) Direction of
Fan No. Serial no Time to Trip with 1 Phase remove out
Starting Running (Amp/Sec) Rotation
1 W0281490/023 OK
2 W0281490/016 OK
3 W0281490/020 OK
4 W0281490/022 OK
5 W0281490/015 OK

Over Load Current setting: 1A Total Current (All Fans Operating) : 6.1 A

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 12 of 18
T12
6.PERCENTAGE IMPEDANCE TEST:
Oil Temp. : 23
Amb. Temp. : 25

Measured Short circuit current in Primary Measured Short circuit current


Applied voltage (volt)
(Ampere) in secondary (Ampere)
Tap
position
Avg.
1U-1N 1V-1N 1W-1N Avg. Volt. 1U 1V 1W 1N Current 2U 2V 2W 2N

12

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 13 of 18
T12

7.OLTC FUNCTION CHECK.

NAME PLATE DETAILS:


Make : MR Type :
No of Taps : 12 Year :
Sl.No. :
ITEM DESCRIPTION REMARKS
1 Perform adjustment of OLTC as per manufacturer's Instruction below. OK
In every operating position the position indicator of motor drive and tap changer read the same OK
I
position.
Ii Check that both end position the electrical and mechanical limits functions automatically. OK

Iii Check oil level in tap changer diverter conservator. OK


V Check condition of silica gel in tap changer breather. OK
Vi Check tightness of ground connection of the tap changer. OK
Vii Check tightness of ground connection for motor drive housing. OK
2 Check stop valves between oil conservator and tap changer are open. OK
Check manual crank position. Check that insertion of crank interlocks prevents electrical OK
3
operation.
4 Ensure heater is connected. OK
5 Check that drive mechanism and tap changer turn in the same direction. OK
Using crank carry out a few steps in one direction till the diverter switch operation takes place OK
6
(a distinct sound is heard). Note the number of crank turns.
7 Check supply voltage for motor, control and auxiliary circuit. OK
Check phase sequence of motor supply voltage and conformed the direction of rotation is OK
8
correct.
With selector in 'LOCAL ' operate 'LOWER' push button and keep it in pushed condition till the OK
motor stops. Make sure that driving motor is automatically switched off when the tap changer
9
has performed one switching operation.
Check operation counter.
10 Repeat the item 9 with push button 'RAISE' kept in pushed condition. OK
11 Check operation counter. OK
Operate to the end position and check that the operation of push button in the same direction OK
12 does not function any more. Ensure that while hand cranking the termination gear will get
blocked after 2-3 revolution of the crank.
OK
13 Put the selector in REMOTE and conformed NO OPERATION from local control.
Check the running current of drive motor. OK
14

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 14 of 18
T12
8.MAGNETIC BALANCE TEST:
Apply Voltage between two phases of H.V. side. Oil Temp : 23 C
Measure the Voltage at H.V. Amb. Temp.: 25 C

TAP NO: 01

ENERGIZED
HV 1U-1N 1V-1N 1W-1N 2U-2N 2V-2N 2W-2N
TERMINALS
1U-1N
1V-1N
1W-1N

TAP NO: 05 Normal

ENERGIZED
HV 1U-1N 1V-1N 1W-1N 2U-2N 2V-2N 2W-2N
TERMINALS
1U-1N
1V-1N
1W-1N

TAP NO: 17

ENERGIZED
HV 1U-1N 1V-1N 1W-1N 2U-2N 2V-2N 2W-2N
TERMINALS
1U-1N
1V-1N
1W-1N

Equipment Used : Multimeter


Make :
Model No. / Sl. No. : 179/ 23350081
Calibration Date : 25/03/2016
Next Calibration Date : 24/03/2

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 15 of 18
T12

9.FUNCTIONAL CHECK OF AUXILIARY EQUIPMENTS

DESCRIPTION TERMINALS FUNCTION

Alarm Low
1.Oil Level Indicator for Tap changer ( +F65 ) X1-10,11 OK
MAN-MR
TYPE:MTO-ST160G/2C0 High Trip
SERIAL NO:1504257 X1-12,13 OK

Alarm Low
2. Oil Level Indicator for Transformer (+F64) X1-6,7 OK
MAN- MR
TYPE-MTO-ST160G/2C0 High Trip
SERIAL NO:150454 X1-8,9 OK

3. Bucholz Relay (F61) Alarm


OK
X1-4,5
MAN- CEDASPE
MODEL- EB079A27N Trip
SERIAL NO-TH0903 X2-1,2 OK

4. Pressure Relief Device Transformer(+F62) Alarm


OK
MAN-CEDASPE X2-3,4
Trip
MODEL: CPR3-MT
X2-5,6 OK
SERIAL NO.TH0903
Alarm
5.OLTC Pressure relief Device(+F63) X2-7,8 OK
MAN-MR
MODEL: 0,65-CD Trip
SERIAL NO.1496307 X2-79,89 OK

6. OIL SURGER (+F66)


MAN- CEDASPE TRIP
OK
MODEL:900-014-02
SERIAL NO.50219000-1-3
Alarm
7.RUBBER BAG LEAKAGE
X1-129,139 OK
MAN- MR

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 16 of 18
T12
Alarm
8.WTI(HV) ( F71 ) X1-14,15
OK
MAN MR
CODE:MT-ST/60SK/TT/4/10M Trip
SERIAL NO.1504252 X2-11,12 OK

Alarm
9 WTI (LV) ( F72 ) X1-16,17 OK
MAN - MR
CODE MT-ST/60SK/TT/4/10M Trip
SERIAL NO.1504251 OK
X2-13,14
Alarm
10.OTI(HV) (F73 ) X1-18,19 OK
MAN MR
CODE: MT-ST/60SK/TT/4/10M Trip
SERIAL NO.1504248 X2-15,16 OK

10.MAGNETIZING CURRENT TEST

Meter used :DELTA4300


Make :MEGGER
Sl.No :
Calibration Date : 2017

HV WINDINGS

TAP# APPLIED VOLTAGE(V) MEASURED CURRENT( mA)


1U-1N 1V-1N 1W-1N IU IV IW
1
2
3
4
5
6
10KV
7
8
9
10
11
12

LV WINDINGS

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 17 of 18
T12
APPLIED VOLTAGE MEASURED CURRENT
2U-2N 2V-2N 2U-2N 2U 2V 2W 2N
2KV

11. DIELECTRIC BREAKDOWN TEST OF OIL


Test Instrument : OIL TESTER
Make : MEGGER
Calibration Date : 29/11/2017
Model / Sl. No. : OTS100AF/101151973
The transformer insulating oil was tested for Dielectric strength using oil tester (ASTM Std.)
1. Transformer main tank top oil sample
Dielectric strength required : 50kv
Oil Temp. In deg. C : 25
Elect
Dielectric Strength ( kV )
rode
No Average Gap Result
Number of Tests (mm)

2. Transformer main tank bottom oil sample


Dielectric strength required : 50kv
Oil Temp. In deg. C : 25
Elect
Dielectric Strength ( kV )
rode
No Average Gap Result
Number of Tests (mm)

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:
SITE TEST REPORT DATE : 3/08/2017

Contractor PACOST INTL

7025 33/13.8 KV S/S, RIYADH


Site : SEC COA CONTRACT NO 4400005528
20 MVA , 33/13.8 KV POWER TRANSFORMER Sheet : Page 18 of 18
T12

Transformer OLTC oil sample


Dielectric strength required : 50kv
Oil Temp. In deg. C : 25
Elect
Dielectric Strength ( kV )
rode
No Average Gap Result
Number of Tests (mm)

NOTE: Applicable Standard For Main tank: ASTM D 1816


For OLTC : ASTM D 877

DATE :

Tested By PACOST INTL. Witnessed by SEC-COA-TESTING.


Mr. Mohamad Taguir Mr.
Date & Signature: Date & Signature:

You might also like