Ampa Fairley Rationalisation Project


Section 1.2 Document No.
Commercial Bid Requirements
Attachment 5

Account code 4140 Heat Recovery Steam Generator

Measuring Unit Set

Scope This account code applies to the sub account codes:


 HRSG

4140-01 Boiler, Transition Duct Burners


4140-02 Gallery, Structure, Auxiliaries
4140-03 Inlet duct, Divertor , By-pass stack
4140-04 Flue Gas Stack

Extent of Work
Work elements to be included are as follows
Work Component Work Element Weighted Value %
01 : Boiler Unit

Assembly 1) Preparation of Foundation 90%


2) Placing Low Beams and Floor
3) Installation of Main Columns and Side Panels
4) Installation of site installed Insulation
5) Assembly of Tube Bundles, Roof Portions and
interconnecting piping
6) Completion of Side Panels
7) Erection of Transition Ducting
8) Installation of burners
9) Completion of floor panels

Final check Refer to “Final Check” in this subclause. 10%

100%

/conversion/tmp/activity_task_scratch/656279635.doc Page 1 of 4
o
Ampa Fairley Rationalisation Project
Section 1.2 Document No.
Commercial Bid Requirements
Attachment 5

Account code 4140 Heat Recovery Steam Generator


02 : Gallery

Installation 1) Assembling and Installing parts of gallery and 90%


platforms by bolting and/or welding;
- Column
- Beam
- Brace
- Ladder
- Stair
- Handrail
- Safety cage
- Grating
- Other parts of gallery
Including the following works;
- Cutting and finishing drain hole in platform
- Cutting and finishing hole in platform
- through which piping is installed
Leveling the platform
Installation of the Steam Drum
Final Check Refer to “Final Check” in this subclause 10%

100%

03 : Inlet Duct

Installation 50%
1) Preparation of Foundation
2) Installation of Divertor Assembly
3) Connecting and welding By pass Stack sections
4) Placing of By Pass Stack
Alignment 40%
1) Alignment of stack
2) Attaching accessories to
stack by bolting and/or welding;
3) Assembling and installing parts as
follows to stack by bolting and/or welding;
10%
Final Check
100%

04. Flue Gas Stack

Installation 1) Preparation of Foundation 50%


2) Connecting and welding stack sections
3) Placing of stack

/conversion/tmp/activity_task_scratch/656279635.doc Page 2 of 4
o
Ampa Fairley Rationalisation Project
Section 1.2 Document No.
Commercial Bid Requirements
Attachment 5

Account code 4140 Heat Recovery Steam Generator


1) Alignment of stack 40%
Alignment 2) Attaching accessories to stack by bolting and/or
welding;
3) Assembling and installing parts as follows to
stack by bolting and/or welding;

Final Check Refer to “Final Check” is this subclause 10%

100%

FINAL CHECK

1) Air leakage test of duct


2) Opening and closing manholes and other openings for inspection purposes
3) Function check and adjustment of such parts as follows;
- Shutdown device
- Other operating parts
4) Rechecking and adjusting safety valve setting
5) Final check as per the Technical Documents

Supply Condition by CONTRACTOR


Part Description Supply Condition

01: Boiler Unit

1) Boiler Unit- - prefabricated in pieces


a) Tube Bundles - welded in bundles
b) Panels - flat panels prepared for welding, factory insulated
c) Columns - prefabricated with flange plates, gusset plates and bolt
holes.

02 : Gallery

1) Gallery
a) columns, beams and braces - prefabricated in several members with flange plates,
gusset plates and bolt holes
b) stair - prefabricated in pieces
c) ladder - prefabricated in pieces
d) safety cage - prefabricated cage rings and flat bars
e) handrail - prefabricated in pieces
f) grating - prefabricated in pieces

03 : Inlet Duct

1) Support - standard steel products such as shaped steel


2) Duct - prefabricated plates with stiffener

/conversion/tmp/activity_task_scratch/656279635.doc Page 3 of 4
o
Ampa Fairley Rationalisation Project
Section 1.2 Document No.
Commercial Bid Requirements
Attachment 5

Account code 4140 Heat Recovery Steam Generator


3) Stack - prefabricated in sections and edge prepared.

04 : Fuel Gas Stack

1) Stack - prefabricated in sections and edge prepared

Work Measurement
1. Quantity to be measured Erection of installed component

2. Method of measurement Measurement is calculated by the installed


components indicated in the Technical Documents
prescribed in 3 below.
3. Technical documents for measurement AFC drawings
Packing list

/conversion/tmp/activity_task_scratch/656279635.doc Page 4 of 4