Professional Documents
Culture Documents
Guideline-WCDMA
Site Solutions
FSIA FRGP
FSEC/S
FSIA/FSMD
interfaces
Transmis
2 HU sion PIU
Dimension
FSIA
Dimension : 447mm (W) X 300mm (D) X 89mm(H)
1-2Extension
PIU
30 cm
FTFB
For internal use
6 © Nokia Siemens Networks Presentation / Author / Date
RF Module
RF Module
Triple RF Module.
Three Transceivers with Tx for two Carriers.
Three Transceivers with Rx for two Carriers.
Three Linear Power amplifiers in the Triple RF Module.
Three RF Filters with Main and Diversity Branch.
“FRGP“ is Triple RF Module for 2100MHz
FRGP
FMFA
OD Distributed BBU + RRU (Node B inside the Existing Outdoor Transmission Rack/ OD Flexi BTS &
1 Scenario 1 tripple RF Module on Pole)
ID Distributed (System Module Inside Existing Transmission rack / Flexi BTS & Tripple RF Module on
3 Scenario 3 Pole)
4 Scenario 4 OD Classic On Pole (System Module & Tripple RF Module on Pole with feeders)
ID Distributed with Antenna Swap (System Module inside the existing Transmission rack & tripple RF
5 Scenario 5 Module on Pole )
6 Scenario 6 ID Classic (System & RF Module Inside the Shelter in the existing Transmission Rack)
ID Distributed (System Module inside the shelter Transmission rack / Flexi BTS & Single RF Module 3
7 Scenario 7 Diff POles)
OD Distributed (System Module inside OD Transmission rack / Flexi OD BTS & Single RF Module on 3
8 Scenario 8 Diff Poles)
9 Scenario 9 OD Distributed ( Sys Module & 1 RRU on Pole and Single RRU RF Unit on 2 Diff poles)
Installation
3G Elements
Place
Indoor System 19'' Transmission
Module (ISM) Rack
19'' Transmission
Triple RF Module Rack
FIU (only for Flexi 19'' Transmission
Hopper) Rack
Twin Diplexer for
Indoor Site Ladder
For internal use
20 © Nokia Siemens Networks Presentation / Sanjay Majumder
Indoor Distributed in 19” Rack
3G Installation
Elements Place
Indoor System 19'' Transmission
Module (ISM) Rack
Tower Top
Triple RF Module Mount/Platform
Twin Diplexer for
Indoor Site Ladder
FIU (only for Flexi 19'' Transmission
Hopper) Rack
Requirement:
existing OD sites-Space required on outdoor foundation for
IP55 rack installation (800x800mm) (part of 1800*1200 OD
Platform)
O/D sites-Duct or cable tray required from shelter or Power
plant to existing 2G OD BTS for laying of Power & PCM cable
OD sites- EGB with 2 nos hole along with nut and bolt is
required. Provision of grounding in tower top
63A-1no. MCB required for power taping of IP55 rack (back
end BB/PP/DG/AC up-gradation is IP’s responsibility and they are
expected to complete the same before offering the site RFI)
Additional GSM pole(60-120 mm Dia.) required at the at the
height where TTSL existing 2G GSM antenna are mounted. This
is for mounting of RRU
Space required
15U IP 55 Rack
for Power & OFC cable routing in HCT &VCT
RF module
Optical cable +
DC power cable
System module
For internal use
25 © Nokia Siemens Networks
NSN solution– Pole solution S1/1/1 DC
Pole solution
Requirement: MCB 32A-1no. 16A-1no. Required (back end
BB/PP/DG/AC up-gradation is IP’s responsibility and they
are expected to complete the same before offering the site
RFI)
Provisioning of 2nos Holes with nut& bolt in IGB & EGB
Existing pole should be (60-120 mm Dia.) if not then new
pole required Entire NodeB on The Pole
With Outdoor System
Remarks : a)if all GSM antenna install in single pole (dia module
60mm-120mm) then no pole required for BTS mounting
b) GSM Antenna mount in different location then cable tray
required for feeder cable routing
Power
3.)
Optical cable , 2m
Note : For FXxx rel. 2.2 RF modules EMHA Flexi EDGE Mech. Module 3U has to be used for installations w/o cabinet
FMHA includes front and rear covers , mounted cable tunnels , screws , and ground cable(s )
Flexi mounting covers for back and front are optional 3U (FMCA) module
covers that are required in installations without a cabinet.
The primary functions of the covers are to provide protection against wind-
driven rain, visual protection, and mechanical
NOTE: FMCA required for BBU+RRU type installation to protection of RF module and
pole classic Type Installation to protection of RF module &system module both
For internal use
33 © Nokia Siemens Networks Presentation / Author / Date
NODE
NODEBBSDR
SDRFORMAT
FORMAT
Microsoft Excel
Worksheet
1. Remove the fixing studs from the Module Casings. Remove the Cable
support plates from the casings. Loosen the Module fixing screws.
2. Then connect the FCM-FTM card supplied with the TRS sub module. Align
and guide the TRS sub module on System Module.
3. Connect the ESD wrist strip with cabinet and wear it before proceeding for the
Modules installation.
Align the Transmission Sub module with the Guide Pins in the System module
and push the TRS Sub module in place.
NOTE:-If your TRS is either FTIA, FTIB, FTJA, or FTOA, do one of the following:
• FTIA/FTIB: insert a SFP Ethernet transceiver (not included in the delivery) into the GE slot.
• FTJA: Insert the SFP transceiver to the EIF1 slot.
• FTOA: Insert the SFP SDH transceiver to the FTOA.
The SFP transceiver is optional for the FTIA, FTIB and FTJA, and mandatory for the FTOA.
PREPARE AND
CONNECT
THE POWER CABLE
AT
+VE AND –VE
TERMINATION
POINT
RESPECTIVELY
RFF 3/8”-50 13 mm 25 mm
RFF 1/2”-50 15 mm 30 mm
RF 1/2”-50 80 mm 160 mm
NOTE: Given values are for NK Cables feeder cables, other manufacturers’ may have different
values, check the proper values before implementation from manufacturer’s data sheets
NOTE: Given values are for NK Cables feeder cables, other manufacturers’ may have
different values, check the proper values before implementation from manufacturer’s
data sheets
INSTALLATION
Verify that antenna supports/poles are installed and in
right location.
Check the delivered antennas & installation hardware
are correct and complete.
Fix the down tilt kits to the antenna.
Hoist the antenna up to the antenna support.
Note: when hoisting antenna in foul weather
conditions, it is necessary to control antenna
movement to avoid damage. Use ropes etc.
Install the antennas on the antenna support exactly
vertical or with a specified offset.
Use the data specified in the BTS Site Installation
Parameters to set the antenna height,
vertical/horizontal separation, direction and down tilt.
Connect one end of the antenna jumpers to the
antennas, leaving the opposite ends open.
Note: the open ends should be protected from
moisture.
Clamp/tie the jumpers to the antenna support.
Secure the antenna fixing clamps with the DOUBLE
LOCK NUTS provided.
OK NOT
OK
OK NOT
OK
3 meter 3 meter
Jumper Jumper Jumper Cables have to be installed as straight as
possible.
Avoid additional bendings.
Follow manufacturers bending instructions.
Proper tools have to be used during jumper
installation.
All cables have to be fixed properly.
Prefabricated jumpers have to be used always
when possible.
On existing sites most practical solution should be
used.
Think about future.
OK
NOT
O OK
K
OK NOT
OK
1.5meter 1.5meter
Jumper Jumper Jumper Cables have to be installed as straight as
possible.
Avoid additional bendings.
Follow manufacturers bending instructions.
Proper tools have to be used during jumper
installation.
All cables have to be fixed properly.
Prefabricated jumpers have to be used always
when possible.
On existing sites most practical solution should be
used.
Think about future.
Crimp Terminal
Grounding Wire 'Tail' Cable Tin Plated Copper Lug
2
16mm 8.4mm diameter (M8)
600mm fixed lenght
The grounding kit must always be positioned on the straight part of feeder cable and never on a bend
or curve in the cable.
Grounding kit's earthing cable can be cut or extended to make grounding cable connection to bar as
straight as possible.
Feeder Cable
Up instead of
Upside Down! Down!
On Cable Bend!
Loops!
Antenna
Jumper Cable or
Antenna Connector
Earthing Kit
FEEDER
RF Cable GROUNDING
Earthing Kit
bar
d Alternative Orientation
for Grounding Bar
Ground Cable (Tail)
600mm long
Feeder Cable
Ground Cable to Main
Site Ground System
Note: Grounding bar should be fixed directly
to the tower where the tower is itself
the main ground down-conductor!
RF Cable
Earthing Kit
Alternative Orientation
for Grounding Bar
(beside cable ladder)
d Grounding Bar
(behind cable ladder)
FEEDER
GROUNDIN Ground Cable to Main
Site Ground System Note: Grounding bar should be fixed directly
G bar to the tower where the tower is itself
the main ground down-conductor!
WEATHER PROOFING
NEEDED
All ourdoor antenna line connections, grounding kits and wall entries
have to be weather proofed.
Connections where weather proofing is needed:
• Feeder to feeder
• Feeder to antenna
• Feeder to EMP (if located outdoor) BTS
Grounding kits have to be sealed according to manufacturer
instructions.
Wall feed through have to be properly sealed.
Ensure that all connectors are on correct torque before sealing!
1. ONE WRAPS OF
INSULATION TAPE
(OVERLAPPING 50%)
20 50 50 20
The grounding kit must always be positioned on the straight part of feeder cable and
never on a bend or curve in the cable.
Grounding kit's earthing cable can be cut or extended to make grounding cable
connection to busbar as straight as possible.
Acceptable
installation
-CONNECTION TO BE TAPED
USING
VINYL ELECTRIC TAPE
-CONNECTION TO BE SEALED
USING
RUBBER SPLICING TAPE
-CONNECTION TO BE TAPED
USING
VINYL ELECTRIC TAPE
-AFTER WEATHER PROOFING
OF CONNECTORS/GROUNDING
KITS ,CABLE TIES TO BE USED
OVER THE SAME
Not OK :
Crimping not
acceptable
DC +
DC -
DC +
DC -
7 Fire and Smoke Alarm Light Blue + Black Blue 9 FIRE AND SMOKE
8 Temp High White + Black White 8 ROOM TEMP HIGH
Light Gray + Light
9 Low Fuel Level Gray Balck 5 LOW FUEL LEVEL
10 Low Oil Pressure Red Black + Red Blue 6 LOW OIL PRESSURE
Orange Red + Orange
11 AIRCON FAILURE Light Gray 7 AIRCON FAILURE
RECTIFIERS MAINS Orange Black +Orange RECTIFIERS MAINS CUT
12 CUT OFF Green 11 OFF
For internal use
102 © Nokia Siemens Networks TTSL Ver 002
KRONE DDF-Labeling and Patching
https://sharenet-ims.inside.nokiasiemensnetworks.com/livelink/livelink?func=ll&o
bjId=423968022&objAction=Browse
Note:-
Note:-for
formore
moreupdate
updateon
onTelecom
TelecomImplementation
ImplementationGuidelines
Guidelines, ,Follow
Followthe
the
above link for Latest Quality Bulletin.
above link for Latest Quality Bulletin.