BALANCE OF WORKS - ACS

COMSEC I-TECH CORPORATION


Project Start: Wed, 8/2/2023
Display: Daily
Display Period: 1

PLAN PLAN PLAN


WBS TASK DESCRIPTION PROGRESS MANPOWER COMMENTS
START END DAYS

1 WATCHTOWER/ AEROPACK (Testing & Commissioning) 8/16/23 8/26/23 11 2


1.1 A1 Building
1.2 Testing & Commissioning 0% 8/16/23 8/18/23 3 pre-tested witnessed by DCI
1.3 A2 Building
1.4 Testing & Commissioning 0% 8/19/23 8/22/23 4 pre-tested witnessed by DCI
1.5 A3 Building
1.6 Testing & Commissioning 0% 8/19/23 8/22/23 4 pre-tested witnessed by DCI
1.7 A4 Building
1.8 Testing & Commissioning 0% 8/23/23 8/24/23 2 pre-tested witnessed by DCI
1.9 A6 Building
1.10 Testing & Commissioning 0% 8/23/23 8/24/23 2 pre-tested witnessed by DCI
1.11 A7 Building
1.12 Testing & Commissioning 0% 8/23/23 8/24/23 2 pre-tested witnessed by DCI
1.13 WatchTower Building
1.14 Testing & Commissioning 0% 8/25/23 8/26/23 2 1 DC configured but not connected; conduit layout to be identified by others
2 NATURA (Testing & Commissioning) 8/29/23 9/8/23 11 2
2.1 C1A Building 21 of 23
2.2 Inspection/ Testing of Works done by others 0% 8/29/23 8/30/23 2 joint inspection; 2 SRIs
2.3 Troubleshooting on Cabling Works done by others, if any 0% 8/31/23 9/5/23 6
2.4 Testing & Commissioning 0% 9/6/23 9/8/23 3
2.5 C1B Building 8 of 8
2.6 Inspection/ Testing of Cables done by others 0% 8/29/23 8/30/23 2 joint inspection
2.7 Troubleshooting on Cabling Works done by others, if any 0% 8/31/23 9/5/23 6
2.8 Testing & Commissioning 0% 9/6/23 9/8/23 3
3 PREMIUM (Testing & Commissioning) 9/9/23 9/23/23 15 2
3.1 B1 Building
3.2 Inspection/ Testing of Cables done by others 0% 9/9/23 9/12/23 4 joint inspection
3.3 Troubleshooting on Cabling Works done by others, if any 0% 9/13/23 9/18/23 6
3.4 Testing & Commissioning 0% 9/19/23 9/23/23 5 need permanent 220v power supply for ACS Contoller AGP
3.5 B2 Building 17 of 48
3.6 Inspection/ Testing of Cables done by others 0% 9/9/23 9/12/23 4 joint inspection
3.7 Troubleshooting on Cabling Works done by others, if any 0% 9/13/23 9/18/23 6
3.8 Testing & Commissioning 0% 9/19/23 9/23/23 5
3.9 B3 Building 5 of 5
3.10 Inspection/ Testing of Cables done by others 0% 9/9/23 9/11/23 3 joint inspection
3.11 Troubleshooting on Cabling Works done by others, if any 0% 9/12/23 9/17/23 6
3.12 Testing & Commissioning 0% 9/18/23 9/22/23 5 need permanent 220v power supply for ACS Contoller AGP
3.13 B6 Building 5 of 5
3.14 Inspection/ Testing of Cables done by others 0% 9/9/23 9/11/23 3 joint inspection; confirm power supply needed (D#01,08,16,17)
3.15 Troubleshooting on Cabling Works done by others, if any 0% 9/12/23 9/17/23 6
3.16 Testing & Commissioning 0% 9/18/23 9/22/23 5 need permanent 220v power supply for ACS Contoller AGP
3.17 B7 Building 6 of 6
3.18 Inspection/ Testing of Cables done by others 0% 9/9/23 9/11/23 3 joint inspection; drop bolt
3.19 Troubleshooting on Cabling Works done by others, if any 0% 9/12/23 9/17/23 6
3.20 Testing & Commissioning 0% 9/18/23 9/22/23 5 need permanent 220v power supply for ACS
4 ACS SERVER AND CLIENTS/ FINAL TESTING 8/7/23 9/28/23 53 2
4.1 Configuration 85% 8/7/23 8/22/23 16 installation and configuration ACS for adjustments during T&C; interconnection to clients done.
4.2 Delivery at Site 0% 8/23/23 8/23/23 1
4.3 Installation at Site 0% 8/24/23 8/26/23 3
4.4 Synchronization of Database 0% 8/27/23 8/30/23 4 Network Backbone needed to be in place
4.5 Pre-Testing 0% 8/31/23 9/9/23 10 Network Backbone needed to be in place
4.6 Final Testing 0% 9/10/23 9/28/23 19 Network Backbone needed to be in place

Insert new rows ABOVE this one