Professional Documents
Culture Documents
8 July 2013
Prepared for
AECOM
Prepared by
AECOM Australia Pty Ltd
Level 9, 8 Exhibition Street, Melbourne VIC 3000, Australia
T +61 3 9653 1234 F +61 3 9654 7117 www.aecom.com
ABN 20 093 846 925
8 July 2013
AECOM in Australia and New Zealand is certified to the latest version of ISO9001 and ISO14001.
AECOM has prepared this document for the sole use of the Client and for a specific purpose, each as expressly stated in the document. No other
party should rely on this document without the prior written consent of AECOM. AECOM undertakes no duty, nor accepts any responsibility, to any
third party who may rely upon or use this document. This document has been prepared based on the Client’s description of its requirements and
AECOM’s experience, having regard to assumptions that AECOM can reasonably be expected to make in accordance with sound professional
principles. AECOM may also have relied upon information provided by the Client and other third parties to prepare this document, some of which
may not have been verified. Subject to the above conditions, this document may be transmitted, reproduced or disseminated only in its entirety.
Quality Information
Document Structures "How To" Guide
Ref
Prepared by Max Un
Revision History
Authorised
Revision
Revision Details
Date
Name/Position Signature
Table of Contents
1.0 Introduction 1
2.0 Regulatory and design standards 1
3.0 Common types of integral bridge 2
3.1 Embedded abutment on pile foundation 2
3.2 Semi-integral bridges 3
3.3 Portal frame 4
4.0 Construction methods 4
4.1 Bottom-up construction and top-down construction 4
4.2 Use of falsework or temporary supports in superstructure construction 6
4.3 Staging of construction 7
5.0 Design approach 8
5.1 Design loads 8
5.1.1 Stage 1 Dead load 8
5.1.2 Additional dead load, superimposed dead load and live load 8
5.1.3 Thermal effects 9
5.1.4 Long term effects 10
5.1.5 Earth pressure 10
5.1.6 Other loads 11
5.1.7 Load factors 11
5.2 Soil-structure interaction 12
5.2.1 Lateral passive earth pressures for embedded abutment on pile foundation 13
5.2.2 Lateral passive earth pressures for semi-integral bridge 14
5.2.3 Lateral passive earth pressures for portal frame 15
5.3 Modelling 15
5.3.1 Modelling the structure 15
5.3.2 Applying load cases to the model 17
5.4 Foundation design 22
5.4.1 Longitudinal movement of structure 22
5.4.2 Pile design 23
5.4.3 Spread footing design 23
5.5 Deck design 24
5.6 Abutment design 24
5.7 Miscellaneous 25
5.7.1 End diaphragm 25
5.7.2 Wing wall 25
5.7.3 Approach slab 26
5.7.4 Bearing 26
5.8 Detailing 26
5.8.1 Deck to abutment 26
5.8.2 End of girders 27
5.8.3 Backfill behind abutments 27
5.8.4 Sleeve to the piles 28
5.9 Consulting with geotechnical engineers 29
6.0 Issues for design and construction 30
7.0 Examples 31
7.1 Embedded abutment on pile foundation 31
7.2 Semi-integral bridge with end diaphragm 47
7.3 Semi-integral bridge with debond layer at deck ends 60
8.0 References 73
Appendix A: Backfill properties 74
Appendix B: Value of Kp 77
1.0 Introduction
Integral bridges are designed without any expansion joints or sometimes bearings. This avoids costly repairs to
expansion joints or bearings. The abutments of integral bridges are attached to the bridge (see Figure 1), and
they have to move horizontally in response to temperature fluctuations and other horizontal loads in the bridge.
Due to these movements, passive earth pressures build up behind the abutment on the resisting side(s).
Therefore, interaction between the bridge and the soil should be estimated for the design of integral bridges.
The deck of the integral bridge is typically constructed with cast in-situ reinforced concrete or precast prestress
concrete beams with cast in-situ deck. When prestress concrete beams are used, the structure would be checked
further with secondary long-term effects such as shrinkage and creep. It will be discussed in the following
sections. There are a few types of integral structure forms including portal frame, embedded abutment and semi-
integral bridge.
A general design approach will be shown, followed by considerations regarding in construction and detailing.
Examples of the integral bridge design are demonstrated based on past projects. Calculation is only shown for
items required special consideration in integral bridge.
Besides, there are some guidelines stated in Bridge Technical Note BTN 2012/003 - Design of Integral and Semi-
Integral Bridges published by VicRoads. It stated that integral bridge should have:
• Maximum overall length not exceed 70m;
• Maximum skew angle not greater than 30°.
Bridge expansion and contraction will impose displacements on the head of the piles, resulting in large bending
moments in the piles. Therefore, flexible piles would be used, or a free length is provided to reduce the curvature
(and hence the moment) in the piles. The pile can be sleeved or wrapped in compressible materials for a certain
length as shown in Figure 3. Piles should be constructed in a single row in each abutment and in vertical to allow
flexibility.
Expansion
High curvature
of pile
(a)
Expansion
Sleeve
(b)
Figure 3: Embedded abutment on pile foundation under thermal expansion: (a) without sleeve, (b) with sleeve around piles
(a)
Debond layer
(b)
Figure 4: Semi-integral bridges: (a) with end diaphragm, (b) with debond layer at deck ends
Because the backfill is filled to full height behind the wall, the magnitude of the passive pressures acting on the
back of the wall is likely to be significant. It is important to ensure the structure is strong enough to resist the
lateral pressure built up behind the wall and yet flexible enough to accommodate the longitudinal movement.
Top-down construction is usually applied for underpass construction. After the substructures are constructed, the
bridge deck is constructed on existing ground level. Then the deck is made integral into the substructures.
Excavation is then carried out below the deck and earth is filled behind the abutment finally. Usually this
construction method is preferred for construction of underpass, in which the deck can act as a prop to the
retaining walls.
Step 2*: Erect precast beams on substructures Step 2: Construct deck and make integral
* Step 2 and step 3 can be done in the same step if superstructure is cast in-situ on falsework.
Due to the nature of the construction methods, a girder/deck system using precast concrete beam is mostly
applied in bottom-up construction, while cast in-situ deck would be used in top-down construction. However, there
are some exceptions, for example:
• Deck is cast on falsework in the bottom-up construction;
• Post-tensioned slab is used in the top-down construction.
This is important as it defines the applied loads on the structure in a certain stages according to the structural
systems of the overall structure and the properties of the structural member. The bridge should be structurally
adequate in each construction stages and in operation.
If falsework or temporary support is used and it is removed after the deck is integral to the abutments, the dead
load of the deck members will also cause a restraint moment at the deck-abutment connections. However, there
would be less sagging moment at mid-span compared to the construction without falsework as shown in Table 2.
M=0
M+ve
M-ve M-ve
M-ve M-ve
M+ve
M+ve
Although the deck is cast on the formwork in top-down construction, it is not always supported on the formwork
before integral if it is post-tensioned. This is because the deck hogs due to the post-tension force and lifts it up
from the formwork. The deck is then simply supported on the abutments.
Stage 1 indicates that only vertical load from dead load and construction load is applied on the abutments; stage 2
identifies that the final structural form of the bridge is completed and all loads including additional dead load,
superimposed dead load, live load, and etc. are applied.
However, there are not always only two stages defined. Depending on the size and construction method of the
bridges, more stages can be defined. For example, the deck slab would be poured in several stages and multiple
spans are erected span by span. An example is shown in Figure 6. A structural analysis model should be set up
for each stage with corresponding structural system to study the bridge behaviour.
(a)
(b)
(c)
Figure 6: Example of construction of a two-span bridge: (a) Erection of precast beams, (b) deck continuous over pier, (c)
Integral to abutments
In this stage, the girder is considered to be simply supported and there is no influence from the adjacent girders.
The deck should be cast before the girders are integral with the abutments by the fender walls to avoid built-in
hogging moment at the supports.
For fully integral bridge, girders are supported on the seating pad or the temporary falsework at erection. The gap
between the soffit of the girder and the abutment is then grouted after the deck cast. Therefore, the support
condition of the girders is considered as simply supported for stage 1 loads.
5.1.2 Additional dead load, superimposed dead load and live load
After the deck is made integral with the abutments, further loads on the deck include other concrete features on
the deck (e.g., road barrier, ballast wall), superimposed dead load (e.g., deck wearing surface, ballast), and
various live loads according to AS5100.2. Depended on the construction sequences, more stage loads are
defined depended on the support condition and the structural members, for example, multi-span construction
(refer section 4 for details).
A recommended unit weight of dead load and superimposed dead load is shown below:
Table 3: Reference of unit weight of dead load and superimposed dead load
The live loads due to road traffic, railway traffic or pedestrian can refer to AS5100.2-2004. Note that the dynamic
load allowance for the railway traffic is derived from the span length of the bridge. For actions other than bending,
the dynamic load allowance for the railway traffic should be factored by 2/3.
The longitudinal live load such as braking forces and traction forces are particularly relevant in the design of the
abutments of the integral bridges. These loads cause longitudinal movements of the bridge. These loads should
be calculated according to AS5100.2-2004 clause 6 (for road traffic) or 8 (for railway traffic).
Expansion Contraction
Figure 7 shows the general response of the structure to each thermal effect. The above loads should be applied
to the structural model reflecting the final stage. The secondary effects due to the restraint condition are obtained
and combined with the primary effect (input load) for the final effect at serviceability limit state, but only the
secondary effects are considered at ultimate limit state. Note that top hot or top cold can occur with either thermal
expansion or contraction to create worse scenario for the structural members. For example, top hot with thermal
contraction: a sunny cold day.
Shrinkage and creep are calculated according to AS5100.5-2004 clauses 6.1.7 and 6.1.8. Only the effects after
erection should be applied to the structure model at the final stage. The effects on the girder before erection
should be analysed with the precast unit only.
The calculations of differential shrinkage and residual creep effect are referred to Appendix E of AS5100.5-2004.
Similar to differential temperature, the differential shrinkage is first applied to the structure model. The secondary
effects due to the restraint condition are obtained and combined with the primary effect (input load) for the final
effect at SLS for stress analysis, but only the secondary effects is considered for ULS strength design.
For residual creep effect, the calculation specified for continuous members can be applied to integral bridge due
to the restraint ends of the deck. According to Appendix E of AS5100.5-2004, the final stresses at any section
shall be the sum of:
[those occurring in each simply supported span calculated in accordance with Item (a)] + [those caused
by [1 - e-Φcc.j] x the continuity restraint moments resulting from the application of both the dead load and
prestress to the continuous composite section described in Item(a)(ii)]
The first item above refers to the stress distribution of the girder due to dead load after all losses under simply
supported condition at the time of interest. This can be calculated by using prestress design spreadsheets or
SAM.
The second item is calculated based on the residual creep factor, Φcc.j, which is the difference of creep factors
between final and at erection, calculated according to AS5100.5-2004 clauses 6.1.8 separately. The prestress
moment after all losses and the dead load of the girder are applied to the structural model. The resultant moment
is then obtained as the restraint moment. These two items are finally combined for the residual creep effect.
The differential shrinkage is applied as a primary sagging moment (similar to top cold) and the residual creep
effect due to prestressing usually causes the deck to hog (similar to top hot).
Due to the nature of the integral bridge, the amount of earth pressures at the ends of deck and abutments
depends on the longitudinal movement. At rest pressure, active pressure and passive pressure are determined on
the abutments depending on the applied loads and load direction. This will be discussed in detail in section 6.
To calculate the lateral earth pressure, the unit weight of the soil is required. It is usually assumed to be 19 kN/m3.
This number varies with the type of chosen backfill or residual soil.
Differential settlement between abutments should be analysed and estimated based on the structure details and
the geotechnical profile and thus input from geotechnical engineers is required to indicate the maximum possible
value. This would cause additional action at the integral abutments.
Dead load
Live load
BA 42/96 provides a guideline on the soil pressure applied on the structure. It also specifies the backfill material to
the integral abutments. The backfill material should be free draining selected granular fill with properties and
grading complying with Class 6N or 6P of table 6/1 of Specification for Highway Works. The relevant information
is provided in Appendix A.
The range of angle of internal friction (Φ’) of the backfill would be largely depending on the selected material. The
peak angle of the internal friction can be as low as 35°. This allows the bridge to accommodate thermal expansion
without experiencing high earth pressure. Backfill with an angle of internal friction of 55° can provide a very high
resistance to thermal expansion. Granular backfill to integral bridges exceeding 40m length should have a peak
angle of internal friction not greater than 45°. The zone of the granular backfill should extend up from the bottom
of the abutment wall to at least a plane inclined at an angle of 45° to the wall as shown in Figure 8.
After the deck is made integral into the abutments, filling earth behind the abutments is carried out. The backfill
should be done in layers and compacted behind both abutments simultaneously to avoid longitudinal load in the
early stage of the structure. Layers of 300mm deep are recommended.
Passive earth pressures (Kp) is obtained based on δ= Φ’/2 and taken from Eurocode 7 (refer Appendix B).
However, the value of Kp reflects the state when the soil is fully mobilised. This hardly happened on the integral
bridge as excessive movement of the bridge is reached. A value of K* is used instead. This value is calculated
based on the longitudinal movement at the top of the abutment, and the method of calculation varies with types of
structure. This will be discussed in the following sections.
In some cases, the value of Kp can be very high for integral bridges. Values in excess of 10 are not
recommended. A friction reducing layer between abutment concrete and backfill can be included to reduce Kp.
Also, it is recommended to consult with the geotechnical engineers for an appropriate value.
For passive earth pressures resisting longitudinal movement, a material partial safety factor of 0.5 is applied to
minimise advantageous force from the backfill. A material partial safety factor of 1.0 is applied when the earth
pressures is considered as load which creates disadvantageous effect.
5.2.1 Lateral passive earth pressures for embedded abutment on pile foundation
For embedded abutment on pile foundation, the distribution of lateral passive earth pressures suggested by BA
42/96 is:
• A uniform value of K* over the top two-thirds of the retained height of the wall, with
• Lateral earth pressure then remaining constant with depth as K* drops towards Ko
• If the lateral earth pressure falls to Ko then below that depth pressures are according to the in-situ value
of Ko.
2H/3
H
Pressure by K*
Pressure by Ko
Where d is the displacement at top of the retained earth, H is the retained height of the wall.
2H/3
H
Pressure by K*
Pressure by Ko
H/2
H
Pressure by Ko Pressure by K*
For portal frames hinged at the base of its legs, the value of K* is calculated by the following equation:
K* = Ko + (d/0.03H)0.6Kp
5.3 Modelling
5.3.1 Modelling the structure
The substructure and the superstructure of integral bridges should not be designed in two separated models as
the simply supported structures. Structural model including both substructure and superstructure should be used
for all loads analysis. One model with hinge deck ends is applied for the stage 1 dead loads and another one with
integral abutments is used for further loads.
The connection between the end of deck and the abutment is critical in the design. Depending on the structure
types, the abutments can be modelled in a few ways. Some examples are shown on next page.
Deck grillage
Stiff member
Abutment beam
Stiff member
In sleeve
No lateral
support Piles
Spring supports
Deck grillage
End screen
Support equivalent
to bearing used
(a)
Link slab
Deck grillage
Fender wall
Hinge or Stiff member
bearing
In sleeve
No lateral
Piles
support
Spring supports
(b)
Figure 14: Recommended model for semi-integral bridges: (a) with end diaphragm, (b) with debond layer at deck ends
Deck grillage
Spring supports
The length with no lateral support in Figure 13 depends on the actual length of the sleeve. The length with no
lateral support for portal frame in Figure 15 covers the height of wall from top of footing, and the earth pressures is
applied on this length.
It is important to obtain the input from the geotechnical engineers for the soil spring stiffness required.
For road traffic braking force, equations are specified in AS5100.2-2004 for both single vehicle stopping and multi-
lane moving traffic stopping. Both are related to the total vertical vehicle load on the deck. The minimum length of
a vehicle described for M1600 moving traffic is 25m. If the total length of the span of the integral bridge and the
approach slabs is longer than 25m, a full braking force is applied (e.g. 720kN for single vehicle). If the integral
bridge is shorter than 25m, it would be calculated based on the possible maximum traffic load on the bridge.
For example, an integral bridge of 20m long can support up to 9 axles of M1600. Therefore,
WBS = 120 x 9 + 6 x 20 = 1200kN
FBS = 0.45 x WBS = 540kN
For rail traffic braking force, it is determined with the loaded length only as specified in AS5100.2-2004. The
braking force would be very large as loaded length increases in long span bridges and multi-span bridges.
Differential temperature is only applied on the longitudinal deck member. Because of the restraint at ends of deck,
a secondary effect is generated. There are two ways to model it.
For models in SpaceGass, the primary moment and the axial force of the differential temperature can be applied
as a concentrated load at the ends of the deck for each beam. The analysis result is a final outcome which
consists of both primary effect and secondary effect. The secondary effect is required for input to the prestress
beam design spreadsheet. Therefore,
[Secondary effect] = [Final result] – [Applied primary effect]
This method is valid if the cross section of the longitudinal members remains unchanged over the whole span.
(a)
(b)
Figure 16: Applied thermal effects in SpaceGass: (a) Applied load, (b) Resultant moment (Primary + Secondary)
# Extract the bending moment diagram and subtract by the applied primary effect.
For models in SAM, the primary moment is applied to the whole length of the longitudinal members in the
structure module. This is different to SpaceGass as this results the secondary effect directly. This result can then
be used in the beam module of SAM for prestress beam analysis. An example is shown in Figure 17.
Please note that the guide of using SAM will not be shown in this guide.
(a)
(b)
Figure 17: Applied thermal effects in SAM: (a) Applied load, (b) Results of secondary effect
Other structural members, such as piles and abutments, should also be designed with the secondary effect,
because it is a response moment by the restraint to the deck from the abutment.
For semi-integral bridge, it is assumed that there is no rotation restraint at the ends of the deck hence there is no
secondary effect. However, the longitudinal movement and the rotation would be critical for bearing design.
Shrinkage and creep are applied to the model in a similar way to the thermal loads. Shrinkage strain and creep
strain are transferred to the equivalent thermal loads in degree Celsius (°C) or kelvin (K) by using the temperature
coefficient of the selected materials. The temperature coefficient of concrete is 11x10-6 per degree Celsius
suggested by AS5100.5-2004. For example, a thermal load of -20°C would be applied on the structure when the
shrinkage is calculated as 220x10-6. The shrinkage of the deck in the transverse direction would increase cracking
near the supports, because of the increased fixity and the low shrinkage of the abutment.
The creep strain is applied on the longitudinal members only, while shrinkage is applied on both longitudinal
members and transverse members. The load application of the differential shrinkage and the residual creep effect
is similar to differential temperature discussed in previous section, in which the primary moment and the axial load
are applied to the model.
It is suggested to apply a basic load case on model, for example passive pressure for K* = 1, on the abutment
and the associated torsion resulted from the difference between the force centre and the abutment centroid. The
passive pressure can be achieved by adjusting the factor to the basic load in a combination of load cases
throughout the iterations. The earth pressure on the active side is remained same in the iterations.
The earth filled behind one abutment resists the longitudinal forces. Passive earth pressure estimated with the
coefficient of K* is applied to this abutment and active earth pressure is applied to another abutment (At rest
pressure can be used if the movement on the active side is not large due to live load). A material partial safety
factor of 0.5 is applied to the passive earth pressure in this case.
Because of the restraint from the integral abutments, restraint bending moment would be large in the foundation
or the supporting members. Stiffness of those members should be reduced based on the cracked condition under
the load combination. Cracked section properties are applied for axial load and bending moment at such state.
This avoids the structural members attracting too much action. However, more longitudinal movement is then
expected.
Iterations are then carried out to determine K* and the design longitudinal movement. It is then checked with the
horizontal capacity of the earth behind the abutment. The iteration process is shown in Figure 18.
Check if longitudinal
movement converges
NO
YES
Besides, VicRoads also specified the maximum range of thermally induced cyclic movement at each abutment
shall not exceed ±20mm. In this case, passive earth pressure is applied on both abutments for thermal expansion
and active earth pressure is applied on both abutments for thermal contraction.
Depending on the project requirements, the differential settlement can be included to provide adverse effect. The
material partial safety factor for earth pressure should be applied to calculate maximum bending moment in the
pile. Any passive pressure on the abutment should be estimated with K* through the iterations demonstrated in
Figure 18.
The top of pile would usually be the critical section in bending moment. It is also important to check the section at
rock socket.
Because the top part of the pile is in sleeve, the clearance between the wall of sleeve and the pile should be
checked against the maximum pile movement to allow flexible bending of the pile.
For portal frame, cracked section properties would be applied to the wall if the bending moment is found large.
Further analysis is required since only the wall section within certain depth below the deck experiences maximum
bending moment (as moment reduces to zero at spread footing).
All bridge loads are applied in the load combinations which produce the above effects. Staging in permanent
effect should be applied carefully on the precast section and the composite section. It is recommended to extract
the results for each load case from the analysis model to a table, and then combine them with the load factors. It
is also convenient to use the analysis software SAM for prestress beam design.
Both primary and secondary effects of the long term effects and the thermal effects are included in the stress
assessment for SLS, but only secondary effect of those is included in ULS design. This is because the secondary
effect is caused by the moment restraint at the ends of the deck.
A strut and tie model would be used if the clear span between the piles is shorter than 4 times the overall depth as
specified in AS5100.5. Refer to work examples for setting of the strut and tie model. Besides, splice should be
checked with sufficient development length of the reinforcement.
5.7 Miscellaneous
5.7.1 End diaphragm
The passive lateral earth pressures can be very high if the movement of the bridge is large. For semi-integral
bridges, it exerts a very high pressure on the end diaphragm. A local check on the end diaphragm is required for
structural adequacy.
2) Maximum shear
V* = w(L/2-t)
For bridges with no skew, the wing walls are set in parallel to the bridge design line to avoid large passive earth
pressure. In this case, the wing wall is designed for a passive earth pressure based on K = 1. The design actions
are horizontal bending and shear force due to passive earth pressure (see Figure 21).
For skew bridges up to 30°, a passive earth pressure based on Kp is applied on the wing wall as shown in Figure
20. For larger skew, special treatment is required and it is not recommended.
M* V* Wing wall
Wing wall
K=1
K=1
Abutment
Kp Kp
Abutment
K=1 Kp
Figure 21: Lateral earth pressures on wing walls (no skew) Figure 20: Lateral earth pressures on wing walls (skew up to 30°)
5.7.4 Bearing
Elastomeric bearing is used on some types of semi-integral bridges. The design of this element for semi-integral
bridges is no different to design for simply supported spans. The design of elastomeric bearing can refer to the
Structures “How to” Guide – Bearing.
5.8 Detailing
5.8.1 Deck to abutment
The deck of the integral bridges is integral into the abutment through the fender wall. There are a few notes for
detailing in this region:
1. The main reinforcements in the deck are designed for the maximum tension due to the maximum
hogging moment at deck end. These reinforcements are bended 90° into the fender wall. A minimum
reinforcement spacing of 100mm would be adopted to avoid congestion in this area.
2. Sufficient lapping between the deck reinforcements and the starter bars from the abutment should be
achieved. The lap length shall not be less than 1.3 times the development length as the splice is not
staggered.
3. Space shall be reserved to land the approach slab (at least 200mm long).
For some semi-integral bridges, a debond layer is applied between the girder and the deck at the ends. This deck
is then acting as a link slab. The debond length is depended on the span length and rigidity of the structure. It is
usually around 1.2m to 1.5m. A detail analysis is required for the suitable debond length.
Besides, sufficient gap is provided between the end of girder and the fender wall. It should be large enough to
accommodate the movement and provide flexibility. An example is shown in Figure 23.
Figure 23: Details for end of deck of semi-integral bridges with debond layer
Figure 24: Onion shaped anchorage for strands projected into fender wall
Drainage is placed at the bottom of the backfill to avoid pore pressure building up. A friction reducing layer
between the abutment concrete and the backfill can be included to reduce the value of Kp. It can be a layer of
bitumen paint coating on the back face of the abutment. A typical example is shown in Figure 8.
The actual method depends on the types of pile in use. For bored piles, an oversize hole is prepared. Liner is then
placed surrounding the case. The thickness of the liner is depended on the required movement. Pictures of this
design are shown in Figure 25.
(a) (b)
Figure 25: Pictures of pile sleeve for bored piles: (a) Case with liner, (b) Installation
There are a few ways to install the sleeve to the driven piles. For the filled embankment, the driven piles can be
encased in compressible material and then filled up. An oversize hole can be pre-drilled and cased, after that the
pile is driven through the hole into the founding layer(s). Pictures of these designs are shown in Figure 26.
(a) (b)
Figure 26: Pictures of pile sleeve for driven piles: (a) Encased in compressible material, (b) In performed hole
The length of the sleeve is critical to the design of integral bridges. There is no quick answer on the length
required. It varies with the structure types, the expected movement, the foundation types, the ground profile and
etc. It shall be long enough to provide flexibility. A detail analysis is required. Usually, the sleeve is extended down
to the founding material to the piles. This is related to the foundation design and the geotechnical engineers shall
be engaged.
For some structures where a more accurate assessment of the magnitudes of the earth pressures is important,
such as cut and core structure, a geotechnical analysis of the structure may be warranted. This is usually involved
use of Plaxis or Wallap. A snapshot from Plaxis is shown in Figure 27.
(a) (b)
Figure 30: Forming of abutment: (a) Flush with the ends of the beams, (b) goes between the beams
7.0 Examples
7.1 Embedded abutment on pile foundation
General details:
Bridge details:
• Two lanes carriageway, 9.9m wide.
• 16.9m span.
• 3.45m wide footpath each side, total trafficable width is 13.5m.
• 6 no. 750mm deep troffs.
• 180mm minimum thick deck.
• 5 no. bored piles for each abutment, top 3m sleeved.
Backfill details:
• 1.5m depth to soffit of abutment.
• Internal friction angle, Φ’ ≈ 35°.
• Unit weight, γ = 19kN/m3.
General arrangement:
Construction sequences:
1. Drill oversize holes down to rock level, and then continue with normal size for rock socket.
2. Place liners then construct bored piles.
3. Cast abutment beams at existing ground level.
4. Excavate within span.
Stage 1 Dead load applied
5. Erect precast units on abutments.
6. Cast in-situ deck slab and fender walls.
7. Backfill behind abutments.
8. Construct approach slab, barriers, footpaths and surfacing. Further loads applied
Design loads:
Two stages of loading are defined according to the construction sequences. Calculation of the loading is done
based on Section 5.1 and step is omitted below.
Live load –
4 design lanes SM1600 within 13.5m wide deck.
Braking force: 720kN
Thermal effects –
For Region II, coastal, < 1000m above sea level,
Shade air temperature: -1°C ~ 44°C
Average bridge temperature: 5°C ~ 48°C
Differential temperature:
For Region 2 and bridge type 1,
Differential shrinkage:
Differential shrinkage strain: Φcs.j = 306x10-6
Primary moment = 954kNm
Earth pressures –
At rest pressure,
Lateral Earth pressure coefficient, Ko = 0.43
Lateral Earth pressure on U/S abutment = 0.43 x 19 x 1.5
= 12.26kPa
Net force on abutment = (12.26 x 1.5)/2
= 9.2kN/m
Passive pressure,
Lateral Earth pressure coefficient, Kp = 6.0 (see Appendix B)
0
Lateral Earth pressure coefficient, K* = (d/0.05H)0.4Kp
= 6(d/75)0.4 1
1.5
Net force on abutment, Fp = (K* x 19 x 1) x (1 x ½ + 0.5) K*
= 19K* kN/m Ko
SAM Model :
Structure module:
Free length
With this reduced pile stiffness, maximum actions (PE+LL) at top of pile:
SLS: Ns = 1200kN Ms = 560kNm
For ULS,
Assuming M* reaches the capacity 950kNm.
With this reduced pile stiffness, maximum actions (PE+LL) at top of pile:
ULS: N* = 1800kN M* = 820kNml
EI = ΦMu/k = 820/0.0057 = 144000kNm2
Longitudinal movement:
Apply passive earth pressure on the resistance side to braking force with a material partial safety factor of 0.5,
apply at rest earth pressure on another side with a material partial safety factor of 1. With braking force only, the
bridge displaces by 5mm. Use 5mm as an initial value for iterations.
Calculate K*,
K* = 0.5 x 6(d/75)0.4
= 1.01
Fp = 19K*
= 19.3kN/m
The result converges. The bridge longitudinal movement is 4.3mm, which is acceptable.
Pile design:
Load cases are combined to obtain the maximum effects on the pile as shown below. Passive earth pressure by
K* is calculated when load combination includes braking force and thermal expansion.
Combination N* (kN) Mx* (kNm) My* (kNm) M* (kNm) Vx* (kN) Vy* (kN) V* (kN)
ULS
N*max 1876 789 -63 791 27 301 302
M*max 1367 867 -59 869 25 327 328
N*min 173 -357 45 359 -27 -159 161
SLS
Ns 1231 603 -65 607 25 215 217
Ms 1042 659 -63 662 25 234 235
Ns min 191 -256 65 264 -32 -106 111
For 750mm dia. pile with 14N28 and f’c = 40MPa, the ultimate bending moment capacity under axial load:
With N12 helix ligs at 150mm pitch, the ultimate shear resistance, ΦVu = 900kN > V*
The maximum steel stress = 254MPa < limit = 300MPa (Spacing of reo ≈ 120mm)
The pile design is adequate structurally. It is then checked against the geotechnical resistance by the
geotechnical engineers.
Deck design:
Live load of SM1600 is positioned on the deck to generate maximum effects. Results are collected and
superimposed with the other effects.
This is a simplified calculation for prestress beam. Please refer to related “How-to” guide for more details.
At transfer check:
With 32 prestress strands, it satisfies the stress requirement at transfer.
Maximum compressive stress at bottom = 21.5MPa < limit = 0.6f’c = 22.2MPa
The maximum shear and torsion at D from the support are shown below. With shear ligs of N16 at 100mm
spacing,
Maximum V* (kN) T* (kNm) ΦVus (kN) ΦTus (kNm) Interaction
effect
V*/ΦVus + T*/ΦTus
V*max 1219 113 1388 1416 0.96
T*max 1052 127 1388 1416 0.85
Deflection -
Deflection under live load plus DLA = 9.6mm < 28mm (span/600)
Maximum hog deflection = 33mm < 56mm (span/300)
Section details:
P1 P2 P3
Backfill details:
• 2.9m depth to soffit of abutment.
• Internal friction angle, Φ’ ≈ 40°.
• Unit weight, γ = 19kN/m3.
General arrangement:
Cross section
Construction sequences:
1. Construct foundations and substructures.
Stage 1
2. Erect the girders, construct pier diaphragm to make continuity.
3. Pour in-situ slab and end diaphragms. Stage 2
4. Backfill behind abutments.
Stage 3
5. Construct approach slab, barriers, footpaths and surfacing.
Design loads:
Three stages of loading are defined according to the construction sequences. Calculation of the loading is done
based on Section 5.1 and step is omitted below.
Live load –
3 design lanes SM1600
Braking force: 720kN
Thermal effects –
For Region II, coastal, < 1000m above sea level,
Shade air temperature: -1°C ~ 44°C
Average bridge temperature: 5°C ~ 48°C
Differential temperature:
For Region 2 and bridge type 1,
Span 1 Span 2
# Red: Top hot Blue: Top cold
Differential shrinkage:
Differential shrinkage strain: Φcs.j = 194x10-6 = 194x10-6
Primary moment = 1322kNm = 1358kNm
Earth pressures –
At rest pressure,
Lateral Earth pressure coefficient, Ko = 1 – sinΦ’
0
= 0.36
SAM Model:
Structure module:
Longitudinal movement:
Apply passive earth pressure on the resistance side of end diaphragm to braking force with a material partial
safety factor of 0.5, apply at rest earth pressure on another end diaphragm and on both abutments with a material
partial safety factor of 1. With braking force only, the bridge displaces by 8mm. Use 8mm as an initial value for
iterations.
Calculate K*,
K* = 0.5 x 8.5(d/50)0.4
= 2.04
Fp = 17.2kN/m
The result converges. The bridge longitudinal movement is 7mm, which is acceptable.
Pile design:
Load cases are combined to obtain the maximum effects on the pile as shown below. Passive earth pressure by
K* is calculated when load combination includes braking force and thermal expansion.
Combination N* (kN) Mx* (kNm) My* (kNm) M* (kNm) Vx* (kN) Vy* (kN) V* (kN)
ULS
N*max 3791 -68 -116 134 57 44 73
N*min 604 143 53 153 -40 -177 181
M*max 2322 -60 -220 228 82 28 86
Long term 2369 23 -232 233 85 -33 91
SLS
Ns 2507 -61 -69 92 33 68 76
Ms 1721 -56 -122 135 45 59 75
Long term 1790 13 -135 136 49 8 49
For 900mm dia. pile with 14N24 and f’c = 40MPa, the ultimate bending moment capacity under axial load:
With N12 helix ligs at 150mm pitch, the ultimate shear resistance, ΦVu = 1000kN > V*
Combination N* (kN) Mx* (kNm) My* (kNm) M* (kNm) Vx* (kN) Vy* (kN) V* (kN)
ULS
N*max 20577 -3285 1748 3721 -93 769 775
N*min 6890 -281 0 281 0 -73 73
M*max 19105 -2984 7408 7987 -394 793 885
Long term 18803 -2992 7408 7990 -394 829 918
SLS
Ns 14618 -1941 971 2170 -52 394 397
Ms 13800 -1774 4116 4482 -219 407 462
Long term 13347 -1773 4116 4481 -219 438 489
For 1800mm dia. pile with 20N32 and f’c = 40MPa, the ultimate bending moment capacity under axial load:
With N12 helix ligs at 150mm pitch, the ultimate shear resistance, ΦVu = 3000kN > V*
The maximum steel stress = 11MPa < limit = 200MPa (Spacing of reo ≈ 240mm)
Both pile designs are adequate structurally. It is then checked against the geotechnical resistance by the
geotechnical engineers.
20N32
N12-150
N12-150
14N24
Deck design:
Live load of SM1600 is positioned on the deck to generate maximum effects. Results are collected and
superimposed with the other effects. Only calculation for prestress beams in span 1 is shown in this example.
This is a simplified calculation for prestress beam. Please refer to related “How-to” guide for more details.
At transfer check:
With 50 prestress strands, it marginally satisfies the stress requirement at transfer.
Maximum compressive stress at bottom = 22.6MPa ≈ limit = 0.6f’c = 22.2MPa
The maximum shear and torsion at D from the support are shown below. With shear ligs of N16 at 100mm
spacing,
Maximum V* (kN) T* (kNm) ΦVus (kN) ΦTus (kNm) Interaction
combined effect
V*/ΦVus + T*/ΦTus
Abutment end
V*max 1489 225 3240 3020 0.53
T*max 1325 400 3450 3020 0.52
Pier end
V*max 2057 176 2470 3020 0.89
T*max 1943 267 2560 3020 0.85
Deflection -
Deflection under live load plus DLA = 25mm < 56.5mm (span/600)
Maximum hog deflection = 55mm < 113mm (span/300)
Reinforcement:
G1: 5N16
G2: 3N16
G5: 4N12
G6: N12-200
G7: N12-150
G8: N16-150
G23: N16
G34: 2N36
Therefore, M* = 12.1kNm
V* = 18.2kN
Therefore, the end diaphragm is adequate for ultimate passive earth pressures.
Backfill details:
• 1.85m depth to soffit of abutment;
• Internal friction angle, Φ’ ≈ 35°;
• Unit weight, γ = 19kN/m3.
General arrangement:
Elevation
Cross section
Construction sequences:
1. Construct substructures.
Stage 1 Dead load applied
2. Erect precast units on abutments.
3. Cast in-situ deck slab and fender walls with debond layers and required gap.
4. Backfill behind abutments.
5. Construct approach slab, ballast wall. Further loads applied
Design loads:
Two stages of loading are defined according to the construction sequences. Calculation of the loading is done
based on Section 5.1 and step is omitted below.
Live load –
2 tracks 300LA.
For 15.6m span, dynamic load allowance, α = 0.31
Multiplication factor, (1+α): 1.31 for bending
1.20 for other actions
Braking force: 100kN for each track
Thermal effects –
For Region II, coastal, < 1000m above sea level,
Shade air temperature: -1°C ~ 44°C
Average bridge temperature: 5°C ~ 48°C
Differential temperature:
For Region 2 and bridge type 1 over water, T = 18°C
Because the bridge is covered by 500mm ballast, the reduced temperature is applied to the top of the deck for
y = 500mm.
Top Hot:
T(y) = T(1 – y/1200)5
= 18x(1 – 500/1200)5
= 1.2°C
Top Cold:
T(y) = 0
Differential Temperature
Differential shrinkage:
Differential shrinkage strain: Φcs.j = 203x10-6
Primary moment = 239kNm
Earth pressures –
At rest pressure,
Lateral Earth pressure coefficient, Ko = 0.43
Lateral Earth pressure on U/S abutment = 0.43 x 19 x 1.85
= 15.1kPa
Net force on abutment = (15.1 x 1.85)/2
= 14.0kN/m
Passive pressure,
0
Lateral Earth pressure coefficient, Kp = 6.0 (see Appendix B)
Lateral Earth pressure coefficient, K* = (d/0.05H)0.4Kp
= 6(d/92.5)0.4 1.23
Fatigue load –
Track 1: 300LA with (1 + ½ α), load factor = 1
Track 2: 80% of 300LA with no DLA, load factor = 1
Stress cycle
Span length, Lf = 15.6m
(2𝐿𝑣−𝐿𝑓) 3
Number of equivalent stress cycles of amplitude, nT = 60( 𝐿𝑓
) +2
= 11.4
Base number of load cycle for main line, CT = 1 x 105
Effective umber of stress cycle, n = CTnT = 1.14 x 106
Longitudinal movement:
Apply passive earth pressure on the resistance side to braking force with a material partial safety factor of 0.5,
apply at rest earth pressure on another side with a material partial safety factor of 1. With braking forces from both
tracks only, the bridge displaces by 1mm. Use 1mm as an initial value for iterations.
Calculate K*,
K* = 0.5 x 6(d/92.5)0.4
= 0.49
Fp = 28.9K*
= 14.2kN/m
The result converges. The bridge longitudinal movement is 1.2mm, which is acceptable.
Pile design:
Load cases are combined to obtain the maximum effects on the pile as shown below. Passive earth pressure by
K* is calculated when load combination includes braking force and thermal expansion.
Combination N* (kN) Mx* (kNm) My* (kNm) M* (kNm) Vx* (kN) Vy* (kN) V* (kN)
ULS
N*max 2400 -640 -169 662 67 266 274
M*max 507 -86 71 112 -34 14 37
N*min 1694 -856 -157 871 63 323 329
SLS
Ns 1662 -441 -120 457 47 183 189
Ms 1240 -573 -113 584 45 218 223
For 750mm dia. pile with 12N32 and f’c = 40MPa, the ultimate bending moment capacity under axial load:
With N12 helix ligs at 150mm pitch, the ultimate shear resistance, ΦVu = 890kN > V*
The maximum steel stress = 171MPa < limit = 295MPa (Spacing of reo ≈ 130mm)
The pile design is adequate structurally. It is then checked against the geotechnical resistance by the
geotechnical engineers.
# Check other inner piles as well.
12N32
N12-150
Deck design:
Live loads of both tracks of 300LA are positioned on the deck to generate maximum effects. Results are collected
and superimposed with the other effects. Only calculation for prestress beams on the edge is shown in this
example.
This is a simplified calculation for prestress beam. Please refer to related “How-to” guide for more details.
At transfer check:
With 22 prestress strands, it marginally satisfies the stress requirement at transfer.
Maximum compressive stress at bottom = 16.5MPa < limit = 0.6f’c = 22.2MPa
0.000 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.000 0.0 -6.1 0.0 0.0 -23.9 0.0 0.0 0.0 15.6 0.0 0.0 0.0
0.680 0.0 -5.8 0.0 0.0 -7.7 0.0 0.0 0.0 77.8 0.0 0.0 0.0
1.700 0.0 1.2 0.0 0.0 32.5 0.0 0.0 0.0 212.1 0.0 0.0 0.0
2.710 0.0 6.9 0.0 0.0 66.5 0.0 0.0 0.0 345.2 0.0 0.0 0.0
3.730 0.0 11.1 0.0 0.0 94.2 0.0 0.0 0.0 460.7 0.0 0.0 0.0
4.750 0.0 14.1 0.0 0.0 115.7 0.0 0.0 0.0 554.3 0.0 0.0 0.0
5.770 0.0 16.1 0.0 0.0 131.0 0.0 0.0 0.0 620.2 0.0 0.0 0.0
6.780 0.0 17.3 0.0 0.0 140.2 0.0 0.0 0.0 658.9 0.0 0.0 0.0
7.800 0.0 17.8 0.0 0.0 143.3 0.0 0.0 0.0 669.8 0.0 0.0 0.0
8.820 0.0 17.5 0.0 0.0 140.2 0.0 0.0 0.0 654.2 0.0 0.0 0.0
9.830 0.0 16.5 0.0 0.0 131.0 0.0 0.0 0.0 612.6 0.0 0.0 0.0
10.850 0.0 14.5 0.0 0.0 115.7 0.0 0.0 0.0 542.7 0.0 0.0 0.0
11.870 0.0 11.6 0.0 0.0 94.2 0.0 0.0 0.0 448.4 0.0 0.0 0.0
12.890 0.0 7.4 0.0 0.0 66.7 0.0 0.0 0.0 332.5 0.0 0.0 0.0
13.900 0.0 1.4 0.0 0.0 33.0 0.0 0.0 0.0 204.9 0.0 0.0 0.0
14.920 0.0 -5.8 0.0 0.0 -7.7 0.0 0.0 0.0 92.9 0.0 0.0 0.0
15.600 0.0 -6.1 0.0 0.0 -23.9 0.0 0.0 0.0 17.8 0.0 0.0 0.0
15.600 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
The maximum shear and torsion at D from the support are shown below. With shear ligs of N12 at 150mm
spacing,
Maximum V* (kN) ΦVu (kN) T* (kNm) 0.25ΦTuc Note
combined effect (kNm)
V*max 492 1390 45 53.3 Torsional reo not required
T*max 459 1390 50 53.3 Torsional reo not required
# Dynamic load allow, α = 0.20.
ytop Width
(mm) (mm)
Diameter 528 mm 60 470
ytop 111 mm 635 470
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
Done 0 0
0 0
0 0
Single Stage Analysis
Shear and Torsion Parameters Calculate Parameters
ycomp 350 mm D/2= 350 fsyf 500 MPa fsyf 500 MPa
ytens 350 mm Asv 226 mm2 Asw 113 mm2
sp.v ert 0 MPa Spacing 150 mm Spacing 150 mm
f 0.7 Pv 0 kN y1 750 mm
sc.p 5.143 MPa av 90 degrees Jt 1.01E+08 mm3
Ast 1030.4 mm2 do 640 mm Am 0 mm2
Apt 1716.0 mm2 b1 1.10 At 270250 mm2
Asc 804.2 mm
2
b2 1.00 ut 2090 mm
Apc 286.0 mm
2
b3 1.00
qv & qt
Deflection -
Deflection under live load plus DLA = 13mm < 26mm (span/600)
Maximum hog deflection = 19mm < 52mm (span/300)
Fatigue design:
Maximum bending moment at mid span,
M* = 492 x (1 + 0.31/2) + 0.8 x 20
= 582kNm
Therefore, design fatigue stress range = 28MPa (reo)
= 14MPa (prestress strand)
Stress range factor, αf 6
= (2x10 / n) 1/3
= 1.21
Permissible stress in steel = 150 x αf
= 181MPa > Design fatigue stress range
The end rotation of the girders causes the hogging moment in the link slab.
Unfactored actions
Loads N* M* V*
SDL -37.8 2.4 4.8
LL
Track 1 -44.4 10.8 19.5
Track 2 19.8 1.8 3.2
Braking 1 9.9 0.3 0.3
Braking 2 9.4 0.2 0.3
Thermal
Expansion -18.5 -0.5 -1
Contraction 12.3 0.3 0.7
Long term
Shrinkage 25.2 1 1.3
Creep 30.7 1.3 1.6
Diff. shrinkage -89.6 -3.1 -4.2
Earth pressures
Ko A 11.6 0.3 0.4
Ko B -11.2 -0.3 -0.4
K* A 24 0.7 0.8
K* B -23.2 -0.6 -0.8
Because the crack moment, Mcr = 16kNm, the section is cracked as assumed.
Therefore, the link slab is adequate for both ultimate and serviceability limit state designs.
8.0 References
British Standard (2004), Eurocode 7: Geotechnical Design
Highway Agency (2003), Design of Integral Bridge
Nicholson, B. A. (1998), Integral Abutments for Prestressed Beam Bridges, Prestressed Concrete Association
Standard Australia (2004), AS5100 – Bridge Design
Standard Australia (2011), AS1170 – Structural Design Actions
VicRoads (2012), Bridge Technical Note BTN 2012/003 – Design of Integral and Semi-Integral Bridges
Appendix B: Value of Kp
δ/φ’ = 0.5