SCHEDULE OF WORK
The following Project Schedule key dates shall be based on the Letter of Award date issued
by PCIHBV to the successful bidder
The Contractor shall meet or improve upon the maximum durations envisioned by PCIHBV.
The Contract Price shall be all-inclusive for the execution and proper completion of the as specified in
and shall be completed within the durations specified above.
Contractor shall use its best endeavours to monitor and control aggressive project schedule for early
completion.
Contractor shall prepare and include a detailed Project Schedule (Level 3) to fully comply with the
above dates, as a part of the Bid submission.
Contractor shall prepare and submit the following to fully comply with the above dates, as part of the
Bid submission.
1. Detailed schedule with correct logic sequence and Work Breakdown Structure (WBS) Level 3
using Primavera Version 6 (P6) or Microsoft Project for all phases i.e. procurement and
construction with resource loaded i.e. people and equipment.
2. The detail schedule shall clearly show the start, finish, duration, plan bar, linkage, total float
and critical activities for all planned WORK stipulated in the Contract.
3. The detail schedule shall be in colour and submitted in hardcopy printed on A3 paper, and
one (1) electronic copy of native file format.
6. Schedule Basis Memorandum (SBM) to support the generation of the detailed schedule.
B. PAYMENT MILESTONE
% OF
MILE -
PORTION OF WORK COMPLETED CONTRACT
STONE
VALUE
Upon Submission of SBLC, Performance Guarantee And
No. 1 5%
Insurance Policies
No. 2 Upon mobilization and approval of Design 5%
TOTAL 100%
- END OF EXHIBIT II -