PROJECT

MARVEL 2 MANAGE SUBCONTRACTOR :


MENT,
SITE PROJECT : CONTINOUS HYDROGENATION PLANT

DAILY REPORT PT. PlateTECH Bajatama Indonesia


LOCATION : KAWASAN EKONOMI KHUSUS SEI MANGKEI-MEDAN
PEB & BRIDGE
PROJECT NO : TA2839

PROFESSION
INSTALLED
NO DESCRIPTION DATE GRID LINE ELEVATION TOTAL DOCUMENTATION
NAME MATERIAL CODE MATERIAL QTY Weight (kg)
1a / CC EL. +200 COLUMN C213 1 657,7
1 / CC EL. +200 COLUMN C211 1 657,63
2-3 / C EL. +200 COLUMN C21 1 274,4
1a / CC EL. +6.000 BEAM B132 1 100,97
C - CC EL. +4.500 BEAM B119 1 105,22
1 / C - CC EL. +6.000 BEAM B118 1 174,71
1 - 1 a / CC EL. +6.000 BEAM B1121 1 246,25
3111,23
1 - 1 a / CC EL. +10.000 BEAM B1120 1 246,09
C - CC EL. +10.000 BEAM B135 1 105,68
1a / C - CC EL. +10.000 BEAM B134 1 100,97
1a / C - CC EL. +10.000 BEAM B1122 1 46,75
3 Erection Structure 09-Feb-23 1a / CC EL. +6.000 BEAM B133 1 114,93
C - CC EL. +6.000 BEAM B120 1 105,22
1 / C - CC EL. +10.000 BEAM B118 1 174,71
REMARKS