ID ID Task Task Name Duration

Start Finish Predecessors


Resource Names Cost Qtr 2, 2021 Qtr 3, 2021
Mode Feb Mar Apr May Jun Jul Aug
1 1 Preplanning 2 wks Mon 01-02-21 Fri 12-02-21 Rs 3,240.00 12-02
2 2 Oil Cooler 1 wk Mon 01-02-21 Fri 05-02-21 Ali Rs 1,440.00 Ali
Confirmation
against work
order
3 3 Marking and Tagging
0 wks Mon 01-02-21 Mon 01-02-212SS Ali Rs 0.00 01-02
4 4 Pre-Inspection 1 wk Mon 08-02-21 Fri 12-02-21 2,3 Master Zubair Rs 1,800.00 Master Zubair
5 5 Disassembly 1 wk Mon 15-02-21 Fri 19-02-21 Rs 2,320.00 19-02
6 6 Draining 1 wk Mon 15-02-21 Fri 19-02-21 4 Ali Rs 1,440.00 Ali
7 7 Disassembly 1 wk Mon 15-02-21 Fri 19-02-21 6SS Adeel Rs 880.00 Adeel
8 8 First Cleaning 8 wks Mon 22-02-21 Fri 16-04-21 Rs 10,380.00 16-04
9 9 Vapor Degreasing 2 wks Mon 22-02-21 Fri 05-03-21 7 Degreaser ,Raheem Rs 960.00 Degreaser ,Raheem
10 10 Outer area 2 wks Mon 08-03-21 Fri 19-03-21 9 Baqar Rs 3,200.00 Baqar
contamination
Removal

11 11 Hose flushing 2 wks Mon 15-03-21 Fri 26-03-21 10FS-1 wkFlush Chamber ,Hoses [1],Raheem Rs 1,020.00 Flush Chamber ,Hoses [1],Raheem
12 12 Pressure Check 1 wk Mon 22-03-21 Fri 26-03-21 10 Ali Rs 1,440.00 Ali
13 13 Crack and 2 wks Mon 29-03-21 Fri 09-04-21 11,12 Ali Rs 2,880.00 Ali
Leakage
Inspection 1
14 14 Repairing 1 wk Mon 12-04-21 Fri 16-04-21 13 Adeel Rs 880.00 Adeel
15 15 Decontamination 9 wks Mon 19-04-21 Fri 18-06-21 Rs 17,120.00 18-06
16 16 Ultra-sonic cleaning
3 wks Mon 19-04-21 Fri 07-05-21 14 Ali Rs 4,320.00 Ali
17 17 Decontamination 3 wks Mon 10-05-21 Fri 28-05-21 16 Baqar Rs 4,800.00 Baqar
(X-Ray Quality)

18 18 Decontamination 2 wks Mon 31-05-21 Fri 11-06-21 17 Baqar Rs 3,200.00 Baqar


(high pressure &
high volume)(100
micron)
19 19 Decontamination 1 wk Mon 14-06-21 Fri 18-06-21 18 Baqar Rs 1,600.00 Baqar
(flushing) (10
micron)
20 20 Draining 1 wk Mon 14-06-21 Fri 18-06-21 19SS Baqar Rs 1,600.00 Baqar
21 21 Drying 1 wk Mon 14-06-21 Fri 18-06-21 20SS Baqar Rs 1,600.00 Baqar
22 22 Repair and Replacement
3 wks Mon 21-06-21 Fri 09-07-21 Rs 4,640.00 09-07
23 23 Fin straightening 1 wk Mon 21-06-21 Fri 25-06-21 21 Ali Rs 1,440.00 Ali
24 24 Insulation checking2 wks Mon 21-06-21 Fri 02-07-21 23SS Adeel Rs 1,760.00 Adeel
25 25 Seal and O-Ring 3 wks Mon 21-06-21 Fri 09-07-21 24SS Raheem Rs 1,440.00 Raheem
Replacement

26 26 Reassembly and 2 wks Mon 12-07-21 Fri 23-07-21 Rs 6,240.00 23-07


Inspection

Page 1
ID ID Task Task Name Duration
Start Finish Predecessors
Resource Names Cost Qtr 2, 2021 Qtr 3, 2021
Mode Feb Mar Apr May Jun Jul Aug
27 27 Reassembly 1 wk Mon 12-07-21 Fri 16-07-21 24,25 Adeel Rs 880.00 Adeel
28 28 Safety Wiring 1 wk Mon 12-07-21 Fri 16-07-21 27SS Adeel Rs 880.00 Adeel
29 29 Pressure Testing 1 wk Mon 12-07-21 Fri 16-07-21 28SS Adeel Rs 880.00 Adeel
30 30 Crack and 2 wks Mon 12-07-21 Fri 23-07-21 29SS Master Zubair Rs 3,600.00 Master Zubair
Leakage
Inspection 2
31 31 Final Treatment 4 wks Mon 26-07-21 Fri 20-08-21 Rs 3,240.00 20-08
32 32 Blasting 1 wk Mon 26-07-21 Fri 30-07-21 30 Bead blaster Rs 0.00 Bead blaster
33 33 Treatment 2 wks Mon 02-08-21 Fri 13-08-21 32 Iridite treatment Rs 0.00 Iridite treatme
34 34 Sealing 1 wk Mon 09-08-21 Fri 13-08-21 33FS-1 wkAli Rs 1,440.00 Ali
35 35 Final Inspection 1 wk Mon 16-08-21 Fri 20-08-21 34 Master Zubair Rs 1,800.00 Master Zub
36 36 Dispatch 1 wk Fri 20-08-21 Fri 27-08-21 Rs 1,800.00 27-08
37 37 Marking 0 wks Fri 20-08-21 Fri 20-08-21 35 Ali Rs 0.00 20-08
38 38 Fitting 1 wk Mon 23-08-21 Fri 27-08-21 37 Master Zubair Rs 1,800.00 Master