TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I

ID WBS Task Name Duration Start Finish January February March


T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
1 1 LEWPP‐1 TEAM ‐ 02 84 days Sat 16‐12‐17 Fri 09‐03‐18
2 1.1 BARGE 2 84 days Sat 16‐12‐17 Fri 09‐03‐18
3 1.1.1 NR WHP 84 days Sat 16‐12‐17 Fri 09‐03‐18
4 1.1.1.1 NR WHP BARGE ‐3 ACTIVITIES 84 days Sat 16‐12‐17 Fri 09‐03‐18
5 1.1.1.1.1 Anchor Handling & Gangway Installation 2 days Sat 16‐12‐17 Sun 17‐12‐17
6 1.1.1.1.1.1 Anchor Handling & Gangway Installation 2 days Sat 16‐12‐17 Sun 17‐12‐17
7 1.1.1.1.2 Preparatory works 28 days Mon 18‐12‐17 Sun 14‐01‐18
8 1.1.1.1.2.1 Material shifting & preparatory works 8 days Mon 18‐12‐17 Mon 25‐12‐17
9 1.1.1.1.2.2 Scaffolding Preparation 28 days Mon 18‐12‐17 Sun 14‐01‐18 SC‐1,SC‐2
10 1.1.1.1.3 Structural Activities 81 days Mon 18‐12‐17 Thu 08‐03‐18
11 1.1.1.1.3.1 BOAT LANDING 11 days Mon 18‐12‐17 Thu 28‐12‐17
12 1.1.1.1.3.1 Preparatory Works 3 days Mon 18‐12‐17 Wed 20‐12‐17
13 1.1.1.1.3.1 Scaffolding Preparation 3 days Mon 18‐12‐17 Wed 20‐12‐17 SC‐1
14 1.1.1.1.3.1 Demolition 7 days Tue 19‐12‐17 Mon 25‐12‐17
15 1.1.1.1.3.1 Handrails 12 Mtr 2 days Tue 19‐12‐17 Wed 20‐12‐17 ST‐1
16 1.1.1.1.3.1 Gratings 18 Sqm 2 days Tue 19‐12‐17 Wed 20‐12‐17 ST‐1
17 1.1.1.1.3.1 Boat landing Ladders 2 Nos 1 day Thu 21‐12‐17 Thu 21‐12‐17 ST‐1
18 1.1.1.1.3.1 Handrail, Cleat support & treads of Stair from 1st to 2nd Tier 2 days Fri 22‐12‐17 Sat 23‐12‐17 ST‐1
19 1.1.1.1.3.1 Handrail, Cleat support & treads of Stair from 2nd to 3rd Tier 2 days Fri 22‐12‐17 Sat 23‐12‐17 ST‐1
20 1.1.1.1.3.1 Staircase From Boatlanding to jacket level 1 Nos 2 days Sun 24‐12‐17 Mon 25‐12‐17 ST‐1
21 1.1.1.1.3.1 Swing rope and support 4 Nos 2 days Sun 24‐12‐17 Mon 25‐12‐17 ST‐1
22 1.1.1.1.3.1 Installation 9 days Wed 20‐12‐17 Thu 28‐12‐17
23 1.1.1.1.3.1 Handrails 12 Mtr 3 days Wed 20‐12‐17 Fri 22‐12‐17 ST‐1
24 1.1.1.1.3.1 Gratings 18 Sqm 3 days Wed 20‐12‐17 Fri 22‐12‐17 ST‐1
25 1.1.1.1.3.1 Boat landing Ladders 2 Nos 2 days Sat 23‐12‐17 Sun 24‐12‐17 ST‐1
26 1.1.1.1.3.1 Handrail, Cleat support & treads of Stair from 1st to 2nd Tier 2 days Mon 25‐12‐17 Tue 26‐12‐17 ST‐1
27 1.1.1.1.3.1 Handrail, Cleat support & treads of Stair from 2nd to 3rd Tier 2 days Mon 25‐12‐17 Tue 26‐12‐17 ST‐1
28 1.1.1.1.3.1 Staircase From Boatlanding to jacket level 1 Nos 2 days Wed 27‐12‐17 Thu 28‐12‐17 ST‐1
29 1.1.1.1.3.1 Swing rope and support 4 Nos 2 days Wed 27‐12‐17 Thu 28‐12‐17 ST‐1
30 1.1.1.1.3.2 JAKET WALKWAY LEVEL 19 days Mon 18‐12‐17 Fri 05‐01‐18
31 1.1.1.1.3.2 SCAFFOLDING PREPARATION FOR JACKET WALK WAY & INTERMEDIATE LANDING 10 days Mon 18‐12‐17 Wed 27‐12‐17 SC‐2,SC‐3
32 1.1.1.1.3.2 Demolition 13 days Tue 19‐12‐17 Sun 31‐12‐17
33 1.1.1.1.3.2 Handrails 65 Mtr 4 days Tue 19‐12‐17 Fri 22‐12‐17 ST‐3,ST‐2
34 1.1.1.1.3.2 Gratings 38 Sqm 4 days Tue 19‐12‐17 Fri 22‐12‐17 ST‐3,ST‐2
35 1.1.1.1.3.2 Conductor Guide & stopper 6 Nos 6 days Tue 19‐12‐17 Sun 24‐12‐17 ST‐4
36 1.1.1.1.3.2 Staircase From jacket level to intermediat landing 1 Nos 3 days Fri 29‐12‐17 Sun 31‐12‐17 ST‐1
37 1.1.1.1.3.2 Installation 16 days Thu 21‐12‐17 Fri 05‐01‐18
38 1.1.1.1.3.2 Handrails 65 Mtr 4 days Thu 21‐12‐17 Sun 24‐12‐17 ST‐2,ST‐3
39 1.1.1.1.3.2 Gratings 38 Sqm 1 day Fri 22‐12‐17 Fri 22‐12‐17 ST‐2,ST‐3
40 1.1.1.1.3.2 Conductor Guide & stopper 6 Nos 9 days Thu 21‐12‐17 Fri 29‐12‐17 ST‐4
41 1.1.1.1.3.2 Staircase From jacket level to intermediat landing 1 Nos 5 days Mon 01‐01‐18 Fri 05‐01‐18 ST‐1
42 1.1.1.1.3.3 INTERMEDIATE LANDING & SUB CELLAR DECK 6 days Sat 06‐01‐18 Thu 11‐01‐18
43 1.1.1.1.3.3 Demolition 5 days Sat 06‐01‐18 Wed 10‐01‐18
44 1.1.1.1.3.3 Handrails at intermediate landing10 Mtr 2 days Sat 06‐01‐18 Sun 07‐01‐18 ST‐1
45 1.1.1.1.3.3 Gratings at intermediate landing(c.s grating) 5 Sqm 3 days Sat 06‐01‐18 Mon 08‐01‐18 ST‐1
46 1.1.1.1.3.3 Staircase From intermediate landing to cellar deck 1 Nos 2 days Tue 09‐01‐18 Wed 10‐01‐18 ST‐1
47 1.1.1.1.3.3 Installation 4 days Mon 08‐01‐18 Thu 11‐01‐18
48 1.1.1.1.3.3 Handrails at intermediate landing 10 Mtr 2 days Mon 08‐01‐18 Tue 09‐01‐18 ST‐1
49 1.1.1.1.3.3 Gratings at intermediate landing(c.s grating) 5 Sqm 1 day Tue 09‐01‐18 Tue 09‐01‐18 ST‐1
50 1.1.1.1.3.3 Staircase From intermediate landing to cellar deck 1 Nos 2 days Wed 10‐01‐18 Thu 11‐01‐18 ST‐1
51 1.1.1.1.3.4 CELLAR DECK 59 days Thu 21‐12‐17 Sat 17‐02‐18
52 1.1.1.1.3.4 SCAFFOLDING PREAPARATION ‐ CELLAR DECK  14 days Thu 21‐12‐17 Wed 03‐01‐18 SC‐1,SC‐3,SC‐2
53 1.1.1.1.3.4 Cellar deck to Main deck Stair & Cellar deck landing area 7 days Sat 30‐12‐17 Fri 05‐01‐18

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

Page 1
TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I
ID WBS Task Name Duration Start Finish January February March
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
54 1.1.1.1.3.4 Demolition 3 days Sat 30‐12‐17 Mon 01‐01‐18
55 1.1.1.1.3.4 Gratings at stair landing area 3 Sqm 2 days Sat 30‐12‐17 Sun 31‐12‐17 ST‐4
56 1.1.1.1.3.4 Staircase From Cellardeck to Main deck 1 Nos 2 days Sun 31‐12‐17 Mon 01‐01‐18 ST‐4
57 1.1.1.1.3.4 Installation 4 days Tue 02‐01‐18 Fri 05‐01‐18
58 1.1.1.1.3.4 Staircase From Cellardeck to Main deck 1 Nos 3 days Tue 02‐01‐18 Thu 04‐01‐18 ST‐4
59 1.1.1.1.3.4 Gratings at stair landing area 3 Sqm 1 day Fri 05‐01‐18 Fri 05‐01‐18 ST‐4
60 1.1.1.1.3.4 Chequered Plate & Hand Rail Replacement and Strenghtening of Structural members 57 days Sat 23‐12‐17 Sat 17‐02‐18
61 1.1.1.1.3.4 Row A‐B & Row 1‐F1 27 days Sat 23‐12‐17 Thu 18‐01‐18
62 1.1.1.1.3.4 Demolition 8 days Sat 23‐12‐17 Sat 30‐12‐17
63 1.1.1.1.3.4 Handrail ‐ 6.1 Mtr 2 days Sat 23‐12‐17 Sun 24‐12‐17 ST‐3,ST‐2
64 1.1.1.1.3.4 Chequered Plate ‐ 38 sq Mtr 4 days Sun 24‐12‐17 Wed 27‐12‐17 ST‐3,ST‐2
65 1.1.1.1.3.4 Conductor sleeve ‐ 6 nos 3 days Tue 26‐12‐17 Thu 28‐12‐17 ST‐3,ST‐2
66 1.1.1.1.3.4 Beams ‐MB350 ‐3 Nos ( 2 mtr each) 2 days Fri 29‐12‐17 Sat 30‐12‐17 ST‐3,ST‐2
67 1.1.1.1.3.4 Strengthening 11 days Mon 25‐12‐17 Thu 04‐01‐18
68 1.1.1.1.3.4 W24 ‐24.4 Mtr 7 days Mon 25‐12‐17 Sun 31‐12‐17 ST‐3,ST‐2
69 1.1.1.1.3.4 MB350 ‐ 18 mtr 4 days Mon 01‐01‐18 Thu 04‐01‐18 ST‐2,ST‐3
70 1.1.1.1.3.4 Installation 18 days Mon 01‐01‐18 Thu 18‐01‐18
71 1.1.1.1.3.4 Beams ‐MB350 ‐3 Nos ( 2 mtr each) 3 days Mon 01‐01‐18 Wed 03‐01‐18 ST‐3,ST‐2
72 1.1.1.1.3.4 Chequered Plate ‐ 38 sq Mtr 15 days Thu 04‐01‐18 Thu 18‐01‐18 ST‐3,ST‐2
73 1.1.1.1.3.4 Conductor sleeve ‐ 6 nos 5 days Fri 05‐01‐18 Tue 09‐01‐18 ST‐3,ST‐2
74 1.1.1.1.3.4 Handrail ‐ 6.1 Mtr 1 day Wed 10‐01‐18 Wed 10‐01‐18 ST‐2,ST‐3
75 1.1.1.1.3.4 Row A‐FA & Row 1‐F1 12 days Fri 12‐01‐18 Tue 23‐01‐18
76 1.1.1.1.3.4 Demolition 6 days Fri 12‐01‐18 Wed 17‐01‐18
77 1.1.1.1.3.4 Chequered Plate ‐ 12 sq Mtr 3 days Fri 12‐01‐18 Sun 14‐01‐18 ST‐1
78 1.1.1.1.3.4 MC‐150 ‐ 6 nos ( 1.8 mtr each) 2 days Mon 15‐01‐18 Tue 16‐01‐18 ST‐1
79 1.1.1.1.3.4 MB350 ‐2 Nos(1.8 mtr each) 2 days Tue 16‐01‐18 Wed 17‐01‐18 ST‐1
80 1.1.1.1.3.4 Strengthening 3 days Sun 14‐01‐18 Tue 16‐01‐18
81 1.1.1.1.3.4 W24 ‐ 1.8 Mtr 1 day Sun 14‐01‐18 Sun 14‐01‐18 ST‐1
82 1.1.1.1.3.4 MB350 ‐ 6 mtr 2 days Mon 15‐01‐18 Tue 16‐01‐18 ST‐1
83 1.1.1.1.3.4 Installation 7 days Wed 17‐01‐18 Tue 23‐01‐18
84 1.1.1.1.3.4 MC‐150 ‐ 6 nos ( 1.8 mtr each) 2 days Wed 17‐01‐18 Thu 18‐01‐18 ST‐1
85 1.1.1.1.3.4 MB350 ‐2 Nos(1.8 mtr each) 2 days Fri 19‐01‐18 Sat 20‐01‐18 ST‐1
86 1.1.1.1.3.4 Chequered Plate ‐ 12 sq Mtr 3 days Sun 21‐01‐18 Tue 23‐01‐18 ST‐1
87 1.1.1.1.3.4 ROW A‐ FB & Row F2‐2 20 days Thu 11‐01‐18 Tue 30‐01‐18
88 1.1.1.1.3.4 Demolition 7 days Thu 11‐01‐18 Wed 17‐01‐18
89 1.1.1.1.3.4 Handrail ‐ 9 mtr 1 day Thu 11‐01‐18 Thu 11‐01‐18 ST‐2,ST‐3
90 1.1.1.1.3.4 Chequered Plate ‐ 50 sq Mtr 7 days Thu 11‐01‐18 Wed 17‐01‐18 ST‐2,ST‐3
91 1.1.1.1.3.4 Beams ‐MB350 ‐3 nos ( 6.1 Mtr each)  3 days Mon 15‐01‐18 Wed 17‐01‐18 ST‐2
92 1.1.1.1.3.4 Beams ‐MB350 ‐3 nos ( 5.6 Mtr each) 3 days Mon 15‐01‐18 Wed 17‐01‐18 ST‐3
93 1.1.1.1.3.4 Strengthening 3 days Sat 13‐01‐18 Mon 15‐01‐18
94 1.1.1.1.3.4 W24 ‐28 Mtr 3 days Sat 13‐01‐18 Mon 15‐01‐18 ST‐2,ST‐3
95 1.1.1.1.3.4 Installation 13 days Thu 18‐01‐18 Tue 30‐01‐18
96 1.1.1.1.3.4 Beams ‐MB350 ‐3 nos ( 6.1 Mtr each)  5 days Thu 18‐01‐18 Mon 22‐01‐18 ST‐2
97 1.1.1.1.3.4 Beams ‐MB350 ‐3 nos ( 5.6 Mtr each) 5 days Thu 18‐01‐18 Mon 22‐01‐18 ST‐3
98 1.1.1.1.3.4 Chequered Plate ‐ 50 sq Mtr 8 days Tue 23‐01‐18 Tue 30‐01‐18 ST‐2,ST‐3
99 1.1.1.1.3.4 Handrail ‐ 9 mtr 1 day Tue 30‐01‐18 Tue 30‐01‐18 ST‐2
100 1.1.1.1.3.4 Row A‐B & Row F2 ‐ south 16 days Wed 24‐01‐18 Thu 08‐02‐18
101 1.1.1.1.3.4 Demolition 5 days Wed 24‐01‐18 Sun 28‐01‐18
102 1.1.1.1.3.4 Handrail ‐ 12 mtr 1 day Wed 24‐01‐18 Wed 24‐01‐18 ST‐1
103 1.1.1.1.3.4 Chequered Plate ‐ 18.3 sq Mtr 5 days Wed 24‐01‐18 Sun 28‐01‐18 ST‐1
104 1.1.1.1.3.4 Beams ‐MB350 ‐3 nos ( 3 Mtr each) 3 days Fri 26‐01‐18 Sun 28‐01‐18 ST‐1
105 1.1.1.1.3.4 Strengthening 4 days Fri 26‐01‐18 Mon 29‐01‐18
106 1.1.1.1.3.4 W24 ‐18 Mtr 4 days Fri 26‐01‐18 Mon 29‐01‐18 ST‐1

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

Page 2
TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I
ID WBS Task Name Duration Start Finish January February March
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
107 1.1.1.1.3.4 Installation 11 days Mon 29‐01‐18 Thu 08‐02‐18
108 1.1.1.1.3.4 Beams ‐MB350 ‐3 nos ( 3 Mtr each) 5 days Mon 29‐01‐18 Fri 02‐02‐18 ST‐1
109 1.1.1.1.3.4 Chequered Plate ‐ 18.3 sq Mtr 6 days Sat 03‐02‐18 Thu 08‐02‐18 ST‐1
110 1.1.1.1.3.4 Handrail ‐ 12 mtr 1 day Thu 08‐02‐18 Thu 08‐02‐18 ST‐1
111 1.1.1.1.3.4 DG Enclosure Area 18 days Wed 31‐01‐18 Sat 17‐02‐18
112 1.1.1.1.3.4 Demolition 18 days Wed 31‐01‐18 Sat 17‐02‐18
113 1.1.1.1.3.4 Bulkhead Plates ‐ 79 Sq Mtr 13 days Wed 31‐01‐18 Mon 12‐02‐18 ST‐2,ST‐3
114 1.1.1.1.3.4 Chequered Plate ‐ 24 Sq mtr 5 days Tue 13‐02‐18 Sat 17‐02‐18 ST‐2,ST‐3
115 1.1.1.1.3.4 Strengthening 4 days Wed 31‐01‐18 Sat 03‐02‐18
116 1.1.1.1.3.4 W24‐ 11.2 mtr 4 days Wed 31‐01‐18 Sat 03‐02‐18 ST‐2,ST‐3
117 1.1.1.1.3.4 Installation 8 days Sun 04‐02‐18 Sun 11‐02‐18
118 1.1.1.1.3.4 Chequered plate ‐ 24 Sq mtr 8 days Sun 04‐02‐18 Sun 11‐02‐18 ST‐2,ST‐3
119 1.1.1.1.3.4 Handrail ‐ 16 mtr 2 days Sat 10‐02‐18 Sun 11‐02‐18 ST‐2,ST‐3
120 1.1.1.1.3.5 MAIN DECK  49 days Mon 18‐12‐17 Sun 04‐02‐18
121 1.1.1.1.3.5 SCAFFOLDING PREPARATION ‐ MAIN DECK 14 days Thu 04‐01‐18 Wed 17‐01‐18 SC‐1,SC‐3,SC‐2
122 1.1.1.1.3.5 ROW FA‐A & ROW F1‐1 12 days Mon 18‐12‐17 Fri 29‐12‐17
123 1.1.1.1.3.5 Demolition 3 days Mon 18‐12‐17 Wed 20‐12‐17
124 1.1.1.1.3.5 Handrail ‐ 18 mtr 2 days Mon 18‐12‐17 Tue 19‐12‐17 ST‐6
125 1.1.1.1.3.5 Chequered Plate ‐ 12 Sq mtr 3 days Mon 18‐12‐17 Wed 20‐12‐17 ST‐6
126 1.1.1.1.3.5 MB‐ 350 ‐ 6 Nos (1.9 mtr each)  3 days Mon 18‐12‐17 Wed 20‐12‐17 ST‐6
127 1.1.1.1.3.5 Strengthening 2 days Mon 18‐12‐17 Tue 19‐12‐17
128 1.1.1.1.3.5 W24‐ 6.12 Mtr 2 days Mon 18‐12‐17 Tue 19‐12‐17 ST‐6
129 1.1.1.1.3.5 Installation 10 days Wed 20‐12‐17 Fri 29‐12‐17
130 1.1.1.1.3.5 MB‐ 350 ‐ 6 Nos (1.9 mtr each)  6 days Wed 20‐12‐17 Mon 25‐12‐17 ST‐6
131 1.1.1.1.3.5 Chequered Plate ‐ 12 Sq mtr 4 days Tue 26‐12‐17 Fri 29‐12‐17 ST‐6
132 1.1.1.1.3.5 Handrail ‐ 18 mtr 2 days Thu 28‐12‐17 Fri 29‐12‐17 ST‐6
133 1.1.1.1.3.5 ROW F1 TO 2 &  FA TO FB 22 days Fri 29‐12‐17 Fri 19‐01‐18
134 1.1.1.1.3.5 Demolition 10 days Fri 29‐12‐17 Sun 07‐01‐18
135 1.1.1.1.3.5 Handrail ‐ 15 mtr 2 days Sat 30‐12‐17 Sun 31‐12‐17 ST‐6
136 1.1.1.1.3.5 Chequered Plate ‐ 20 Sq mtr 5 days Fri 29‐12‐17 Tue 02‐01‐18 ST‐6
137 1.1.1.1.3.5 MB‐ 350 ‐ 3 Nos (6.1 mtr each)  4 days Wed 03‐01‐18 Sat 06‐01‐18 ST‐6
138 1.1.1.1.3.5 MB‐ 350 ‐ 6 Nos (1.9 mtr each)  5 days Wed 03‐01‐18 Sun 07‐01‐18 ST‐6
139 1.1.1.1.3.5 Strengthening 7 days Fri 29‐12‐17 Thu 04‐01‐18
140 1.1.1.1.3.5 W24‐ 7 Mtr 4 days Fri 29‐12‐17 Mon 01‐01‐18 ST‐6
141 1.1.1.1.3.5 MB 350 ‐ 16 mtr 6 days Sat 30‐12‐17 Thu 04‐01‐18 ST‐6
142 1.1.1.1.3.5 Installation 18 days Tue 02‐01‐18 Fri 19‐01‐18
143 1.1.1.1.3.5 MB‐ 350 ‐ 3 Nos (6.1 mtr each)  8 days Tue 02‐01‐18 Tue 09‐01‐18 ST‐6
144 1.1.1.1.3.5 MB‐ 350 ‐ 6 Nos (1.9 mtr each)  8 days Fri 05‐01‐18 Fri 12‐01‐18 ST‐6
145 1.1.1.1.3.5 Handrail ‐ 15 mtr 3 days Wed 10‐01‐18 Fri 12‐01‐18 ST‐6
146 1.1.1.1.3.5 Chequered Plate ‐ 20 Sq mtr 7 days Sat 13‐01‐18 Fri 19‐01‐18 ST‐6
147 1.1.1.1.3.5 FROM ROW F2 TOWARDS SOUTH SIDE 11 days Sat 20‐01‐18 Tue 30‐01‐18
148 1.1.1.1.3.5 Demolition 2 days Sat 20‐01‐18 Sun 21‐01‐18
149 1.1.1.1.3.5 Handrail ‐ 10 mtr 2 days Sat 20‐01‐18 Sun 21‐01‐18 ST‐6
150 1.1.1.1.3.5 Strengthening 6 days Mon 22‐01‐18 Sat 27‐01‐18
151 1.1.1.1.3.5 W24‐ 2.8 Mtr 3 days Mon 22‐01‐18 Wed 24‐01‐18 ST‐6
152 1.1.1.1.3.5 MB 350 ‐ 4.8 mtr 3 days Thu 25‐01‐18 Sat 27‐01‐18 ST‐6
153 1.1.1.1.3.5 Installation 3 days Sun 28‐01‐18 Tue 30‐01‐18
154 1.1.1.1.3.5 Handrail ‐ 10 mtr 3 days Sun 28‐01‐18 Tue 30‐01‐18 ST‐6
155 1.1.1.1.3.5 STAIRCASE FROM MAIN DECK to MEZZANINE DECK 5 days Wed 31‐01‐18 Sun 04‐02‐18
156 1.1.1.1.3.5 DEMOLITION 2 days Wed 31‐01‐18 Thu 01‐02‐18 ST‐6
157 1.1.1.1.3.5 INSTALLATION 3 days Fri 02‐02‐18 Sun 04‐02‐18 ST‐6
158 1.1.1.1.3.6 MEZZANINE DECK 13 days Sat 06‐01‐18 Thu 18‐01‐18
159 1.1.1.1.3.6 SCAFFOLDING PREPARATION FOR MEZZANINE DECK 8 days Sat 06‐01‐18 Sat 13‐01‐18 SC‐3,SC‐2

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

Page 3
TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I
ID WBS Task Name Duration Start Finish January February March
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
160 1.1.1.1.3.6 DEMOLITION 2 days Sat 06‐01‐18 Sun 07‐01‐18
161 1.1.1.1.3.6 Handrail ‐ 7mtr 1 day Sat 06‐01‐18 Sat 06‐01‐18 ST‐4
162 1.1.1.1.3.6 Gratings ‐6.4 sq mtr 1 day Sat 06‐01‐18 Sat 06‐01‐18 ST‐4
163 1.1.1.1.3.6 2" Tubular ‐ 4 MTR ( 2NOS) 1 day Sun 07‐01‐18 Sun 07‐01‐18 ST‐4
164 1.1.1.1.3.6 STRENGTHENNING 5 days Mon 08‐01‐18 Fri 12‐01‐18
165 1.1.1.1.3.6 MB 250 ‐22 MTR 4 days Mon 08‐01‐18 Thu 11‐01‐18 ST‐4
166 1.1.1.1.3.6 MC 250 ‐ 3.85 MTR 1 day Fri 12‐01‐18 Fri 12‐01‐18 ST‐4
167 1.1.1.1.3.6 INSTALLATION 6 days Sat 13‐01‐18 Thu 18‐01‐18
168 1.1.1.1.3.6 Handrail ‐ 12 mtr 2 days Sat 13‐01‐18 Sun 14‐01‐18 ST‐4
169 1.1.1.1.3.6 Gratings ‐11 sq mtr 2 days Mon 15‐01‐18 Tue 16‐01‐18 ST‐4
170 1.1.1.1.3.6 2" Tubular ‐ 4 MTR ( 2NOS) 2 days Wed 17‐01‐18 Thu 18‐01‐18 ST‐4
171 1.1.1.1.3.7 INSTALLATION OF VENT BOOM & DECK EXTENSION 8 days Mon 05‐02‐18 Mon 12‐02‐18
172 1.1.1.1.3.7 DECK EXTENSION & VENT BOOM INSTALLATION 8 days Mon 05‐02‐18 Mon 12‐02‐18 ST‐6
173 1.1.1.1.3.8 CCD DECK EXTENSION & CCD INSTALLATON 7 days Sat 20‐01‐18 Fri 26‐01‐18
174 1.1.1.1.3.8 DECK EXTENSION  7 days Sat 20‐01‐18 Fri 26‐01‐18 ST‐6
175 1.1.1.1.3.8 CCD INSTALLATION 1 day Fri 26‐01‐18 Fri 26‐01‐18 ST‐6
176 1.1.1.1.3.9 HELIDECK 24 days Fri 19‐01‐18 Sun 11‐02‐18
177 1.1.1.1.3.9 DEMOLITION 6 days Fri 19‐01‐18 Wed 24‐01‐18
178 1.1.1.1.3.9  Existing safety net 1 day Fri 19‐01‐18 Fri 19‐01‐18 ST‐3,ST‐4
179 1.1.1.1.3.9  Helideck plating 182 Sqm 5 days Sat 20‐01‐18 Wed 24‐01‐18 ST‐3,ST‐4
180 1.1.1.1.3.9  Helideck Secondary beams(H150) 5 days Sat 20‐01‐18 Wed 24‐01‐18 ST‐3,ST‐4
181 1.1.1.1.3.9 STRENGTHENING 7 days Mon 22‐01‐18 Sun 28‐01‐18
182 1.1.1.1.3.9 MB250 ‐ 92 Mtr 7 days Mon 22‐01‐18 Sun 28‐01‐18 ST‐3,ST‐4
183 1.1.1.1.3.9 INSTALLATION 14 days Mon 29‐01‐18 Sun 11‐02‐18
184 1.1.1.1.3.9  new helideck aluminium pancake 182 Sqm 14 days Mon 29‐01‐18 Sun 11‐02‐18 ST‐3,ST‐4
185 1.1.1.1.3.1 Chequered Plate & Hand Rail Replacement and Strenghtening of Structural members 41 days Sat 27‐01‐18 Thu 08‐03‐18
186 1.1.1.1.3.1 Remaining Chequered Plate & Hand Rail Replacement at Cellar deck 41 days Sat 27‐01‐18 Thu 08‐03‐18
187 1.1.1.1.3.1 Row B‐FB  & Row F1 & 2 ( WELL FLUID LAUNCHER AREA) 11 days Mon 12‐02‐18 Thu 22‐02‐18
188 1.1.1.1.3.1 Demolition 3 days Mon 12‐02‐18 Wed 14‐02‐18
189 1.1.1.1.3.1 chequiredplate (8 mm thick)  :‐ 30.6 Sqm 3 days Mon 12‐02‐18 Wed 14‐02‐18 ST‐3,ST‐4
190 1.1.1.1.3.1 MB‐350 ‐ ( 2 Mtr each) ‐ 9 nos 3 days Mon 12‐02‐18 Wed 14‐02‐18 ST‐3,ST‐4
191 1.1.1.1.3.1 Strengthening 3 days Wed 14‐02‐18 Fri 16‐02‐18
192 1.1.1.1.3.1 W24 ‐ 6 mtr 1 day Wed 14‐02‐18 Wed 14‐02‐18 ST‐3,ST‐4
193 1.1.1.1.3.1 MB‐350 ‐ 15.3 mtr 2 days Thu 15‐02‐18 Fri 16‐02‐18 ST‐3,ST‐4
194 1.1.1.1.3.1 Installation 8 days Thu 15‐02‐18 Thu 22‐02‐18
195 1.1.1.1.3.1 MB‐350 ‐ ( 2 Mtr each) ‐ 9 nos 4 days Thu 15‐02‐18 Sun 18‐02‐18 ST‐3,ST‐4
196 1.1.1.1.3.1 chequiredplate (8 mm thick) :‐ 30.6 Sqm 4 days Mon 19‐02‐18 Thu 22‐02‐18 ST‐3,ST‐4
197 1.1.1.1.3.1 Row A‐B & F1‐2 ( PRODUCTION MANIFOLD , TEST HEADER etc) 14 days Fri 23‐02‐18 Thu 08‐03‐18
198 1.1.1.1.3.1 Demolition 6 days Fri 23‐02‐18 Wed 28‐02‐18
199 1.1.1.1.3.1 chequiredplate (8 mm thick)  :‐ 93 Sqm 6 days Fri 23‐02‐18 Wed 28‐02‐18 ST‐3,ST‐4
200 1.1.1.1.3.1 MB‐350 ‐ ( 6.1 Mtr each) ‐ 9 nos 5 days Sat 24‐02‐18 Wed 28‐02‐18 ST‐3,ST‐4
201 1.1.1.1.3.1 Strengthening 3 days Sun 25‐02‐18 Tue 27‐02‐18
202 1.1.1.1.3.1 W24 ‐ 21.4 mtr 3 days Sun 25‐02‐18 Tue 27‐02‐18 ST‐3,ST‐4
203 1.1.1.1.3.1 Installation 9 days Wed 28‐02‐18 Thu 08‐03‐18
204 1.1.1.1.3.1 MB‐350 ‐ ( 6.1 Mtr each) ‐ 9 nos 4 days Wed 28‐02‐18 Sat 03‐03‐18 ST‐3,ST‐4
205 1.1.1.1.3.1 chequiredplate (8 mm thick) :‐ 93 Sqm 5 days Sun 04‐03‐18 Thu 08‐03‐18 ST‐3,ST‐4
206 1.1.1.1.3.1 Row B‐FB  & Row F1 & 1 ( SHUTDOWN PANEL AREA) 10 days Sat 27‐01‐18 Mon 05‐02‐18
207 1.1.1.1.3.1 Demolition 3 days Sat 27‐01‐18 Mon 29‐01‐18
208 1.1.1.1.3.1 chequiredplate (8 mm thick)  :‐ 12.24 Sqm 2 days Sat 27‐01‐18 Sun 28‐01‐18 ST‐2
209 1.1.1.1.3.1 MB‐350 ‐ ( 2 Mtr each) ‐ 2 nos 1 day Sun 28‐01‐18 Sun 28‐01‐18 ST‐2
210 1.1.1.1.3.1 MC 150 ‐ ( 2 mtr each ) ‐ 6 nos 1 day Mon 29‐01‐18 Mon 29‐01‐18 ST‐2
211 1.1.1.1.3.1 Strengthening 3 days Mon 29‐01‐18 Wed 31‐01‐18
212 1.1.1.1.3.1 W24 ‐ 2 mtr 1 day Mon 29‐01‐18 Mon 29‐01‐18 ST‐2

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

Page 4
TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I
ID WBS Task Name Duration Start Finish January February March
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
213 1.1.1.1.3.1 MB‐350 ‐ 8.12 mtr 2 days Tue 30‐01‐18 Wed 31‐01‐18 ST‐2
214 1.1.1.1.3.1 Installation 5 days Thu 01‐02‐18 Mon 05‐02‐18
215 1.1.1.1.3.1 MB‐350 ‐ ( 2 Mtr each) ‐ 2 nos 2 days Thu 01‐02‐18 Fri 02‐02‐18 ST‐2
216 1.1.1.1.3.1 MC 150 ‐ ( 2 mtr each ) ‐ 6 nos 2 days Sat 03‐02‐18 Sun 04‐02‐18 ST‐2
217 1.1.1.1.3.1 chequiredplate (8 mm thick) :‐ 12.24 Sqm 3 days Sat 03‐02‐18 Mon 05‐02‐18 ST‐2
218 1.1.1.1.3.1 MODULAR RIG 23 days Tue 06‐02‐18 Wed 28‐02‐18
219 1.1.1.1.3.1 Installtion 23 days Tue 06‐02‐18 Wed 28‐02‐18
220 1.1.1.1.3.1 Stengthening of Deck truss Raw A&B,deck beams,truss chord beams etc 9 days Tue 06‐02‐18 Wed 14‐02‐18 ST‐2
221 1.1.1.1.3.1 Tubular stub at Row(1)(Φ1219) 3 days Thu 15‐02‐18 Sat 17‐02‐18 ST‐2
222 1.1.1.1.3.1 column stub at Row (2) 3 days Sun 18‐02‐18 Tue 20‐02‐18 ST‐2
223 1.1.1.1.3.1 Cap plate ,stiffner plate & box up plate 6 days Wed 21‐02‐18 Mon 26‐02‐18 ST‐2
224 1.1.1.1.3.1 Burnerboom support at southeast corner of platform 2 days Tue 27‐02‐18 Wed 28‐02‐18 ST‐2
225 1.1.1.1.3.1 DECK EXTENSION 23 days Fri 09‐02‐18 Sat 03‐03‐18
226 1.1.1.1.3.1 maindeck new extention 15.3 X .8 mtr 4 days Fri 09‐02‐18 Mon 12‐02‐18 ST‐1
227 1.1.1.1.3.1 maindeck new extention 12.4 X .8 mtr 3 days Thu 01‐03‐18 Sat 03‐03‐18 ST‐2
228 1.1.1.1.3.1 Main Deck 16 days Tue 13‐02‐18 Wed 28‐02‐18
229 1.1.1.1.3.1 Row A‐B & Row F2 ‐ south 16 days Tue 13‐02‐18 Wed 28‐02‐18
230 1.1.1.1.3.1 Demolition 5 days Tue 13‐02‐18 Sat 17‐02‐18
231 1.1.1.1.3.1 Handrail ‐ 18 mtr 1 day Tue 13‐02‐18 Tue 13‐02‐18 ST‐1
232 1.1.1.1.3.1 Chequered Plate ‐ 37 sq Mtr 5 days Tue 13‐02‐18 Sat 17‐02‐18 ST‐1
233 1.1.1.1.3.1 Beams ‐MB350 ‐5 nos ( 6 Mtr each) 3 days Thu 15‐02‐18 Sat 17‐02‐18 ST‐1
234 1.1.1.1.3.1 Strengthening 4 days Thu 15‐02‐18 Sun 18‐02‐18
235 1.1.1.1.3.1 W24 ‐24 Mtr 4 days Thu 15‐02‐18 Sun 18‐02‐18 ST‐1
236 1.1.1.1.3.1 Installation 11 days Sun 18‐02‐18 Wed 28‐02‐18
237 1.1.1.1.3.1 Beams ‐MB350 ‐5 nos ( 6 Mtr each) 5 days Sun 18‐02‐18 Thu 22‐02‐18 ST‐1
238 1.1.1.1.3.1 Chequered Plate ‐ 37 sq Mtr 6 days Fri 23‐02‐18 Wed 28‐02‐18 ST‐1
239 1.1.1.1.3.1 Handrail ‐ 18 mtr 1 day Wed 28‐02‐18 Wed 28‐02‐18 ST‐1
240 1.1.1.1.3.1 SOLAR PANNEL PLATFORM 20 days Tue 13‐02‐18 Sun 04‐03‐18
241 1.1.1.1.3.1 Demolition 7 days Tue 13‐02‐18 Mon 19‐02‐18
242 1.1.1.1.3.1 Hadrails :‐ 18 Mtr 1 day Tue 13‐02‐18 Tue 13‐02‐18 ST‐6
243 1.1.1.1.3.1 chequiredplate (6 mm thick) :‐ 24 Sqm 3 days Wed 14‐02‐18 Fri 16‐02‐18 ST‐6
244 1.1.1.1.3.1 MB 250 ‐ 14 Mtr 2 days Sat 17‐02‐18 Sun 18‐02‐18 ST‐6
245 1.1.1.1.3.1 MC 150 ‐ 12 Mtr 1 day Mon 19‐02‐18 Mon 19‐02‐18 ST‐6
246 1.1.1.1.3.1 Strenghtnening 6 days Fri 16‐02‐18 Wed 21‐02‐18
247 1.1.1.1.3.1 Strengthening Structural members(MB‐250 ):‐ 36 Mtr 4 days Fri 16‐02‐18 Mon 19‐02‐18 ST‐6
248 1.1.1.1.3.1 Strengthening Structural members(MC‐250 ) :‐26 Mtr 2 days Tue 20‐02‐18 Wed 21‐02‐18 ST‐6
249 1.1.1.1.3.1 Installation 11 days Thu 22‐02‐18 Sun 04‐03‐18
250 1.1.1.1.3.1 MB 250 ‐ 14 Mtr 4 days Thu 22‐02‐18 Sun 25‐02‐18 ST‐6
251 1.1.1.1.3.1 MC 150 ‐ 12 Mtr 2 days Mon 26‐02‐18 Tue 27‐02‐18 ST‐6
252 1.1.1.1.3.1 chequiredplate (6 mm thick) :‐ 24 Sqm 3 days Wed 28‐02‐18 Fri 02‐03‐18 ST‐6
253 1.1.1.1.3.1 Hadrails :‐ 18 Mtr 2 days Sat 03‐03‐18 Sun 04‐03‐18 ST‐6
254 1.1.1.1.3.1 Common Activity 60 days Fri 05‐01‐18 Mon 05‐03‐18
255 1.1.1.1.3.1 NDT 60 days Fri 05‐01‐18 Mon 05‐03‐18
256 1.1.1.1.4 Piping Activities 78 days Wed 20‐12‐17 Wed 07‐03‐18
257 1.1.1.1.4.1 UNIT SHUTDOWN ACTIVITIES 63 days Wed 20‐12‐17 Tue 20‐02‐18
258 1.1.1.1.4.1 Preparatory works for Piping Activities 27 days Wed 20‐12‐17 Mon 15‐01‐18
259 1.1.1.1.4.1 Scaffolding Preparations 27 days Wed 20‐12‐17 Mon 15‐01‐18 SC‐3,SC‐2
260 1.1.1.1.4.1 Open & Closed Hydrocarbon Drain Revamping & CCD Replacement 45 days Thu 21‐12‐17 Sat 03‐02‐18
291 1.1.1.1.4.1 Fire Water Net Work 40 days Fri 22‐12‐17 Tue 30‐01‐18
292 1.1.1.1.4.1 Demolition of Fire water network 18 days Fri 22‐12‐17 Mon 08‐01‐18
293 1.1.1.1.4.1 Demolition of fire water Header/fire water hose reel connections/over board line 18 days Fri 22‐12‐17 Mon 08‐01‐18 P‐3,P‐4
294 1.1.1.1.4.1 Installation Of Fire water network 31 days Sat 23‐12‐17 Mon 22‐01‐18

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

Page 5
TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I
ID WBS Task Name Duration Start Finish January February March
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
295 1.1.1.1.4.1 Installation of fire water Header/fire water hose reel connections/over board line  31 days Sat 23‐12‐17 Mon 22‐01‐18 P‐3,P‐4
(Appx. Scope ‐ 600 inch dia)
296 1.1.1.1.4.1 Common Activities 32 days Sat 30‐12‐17 Tue 30‐01‐18
297 Installation Installation Of Piping Supports 11 days Sun 14‐01‐18 Wed 24‐01‐18 P‐3,P‐4
298 1.1.1.1.4.1 NDT/PWHT 26 days Sat 30‐12‐17 Wed 24‐01‐18
299 1.1.1.1.4.1 Hydro testing 6 days Sun 21‐01‐18 Fri 26‐01‐18 Hy‐1
300 1.1.1.1.4.1 Re‐Instatement 4 days Sat 27‐01‐18 Tue 30‐01‐18
301 1.1.1.1.4.1 Vent boom Replacement, Vent network Revamping & Co2 Snuffing system Installation 54 days Thu 21‐12‐17 Mon 12‐02‐18
302 1.1.1.1.4.1 Vent Piping Network Replacement 53 days Fri 22‐12‐17 Mon 12‐02‐18
303 1.1.1.1.4.1 Isolation , Purging & Teporary Arrangement 2 days Fri 22‐12‐17 Sat 23‐12‐17
304 1.1.1.1.4.1 Nitrogen Purging 2 days Fri 22‐12‐17 Sat 23‐12‐17 P‐7
305 1.1.1.1.4.1 Demolition of Vent network piping 25 days Sun 24‐12‐17 Wed 17‐01‐18
306 1.1.1.1.4.1 6" Vent Header & Vent Boom piping (Scope Apprx. 144 inch Dia) 7 days Sun 24‐12‐17 Sat 30‐12‐17 P‐7
307 1.1.1.1.4.1 2" Vent lines fromTest & Production header & well fluid flow arms gas Flow arm(5  6 days Sun 31‐12‐17 Fri 05‐01‐18 P‐7
nos)(Scope Apprx. 80 inch dia)
308 1.1.1.1.4.1 6" Vent Lines from Test Separator (Scope Apprx. 12 inch dia) 2 days Sat 06‐01‐18 Sun 07‐01‐18 P‐7
309 1.1.1.1.4.1 2" vent lines from Well Fluid Launcher‐2nos. (Scope Apprx. 8 inch dia) 2 days Mon 08‐01‐18 Tue 09‐01‐18 P‐7
310 1.1.1.1.4.1 3" Vent line from Lift gas Launcher (Scope Apprx. 20 inch dia) 2 days Wed 10‐01‐18 Thu 11‐01‐18 P‐7
311 1.1.1.1.4.1 2" Vent from Lift gas flow arms(Scope Apprx. 100 inch dia) 4 days Fri 12‐01‐18 Mon 15‐01‐18 P‐7
312 1.1.1.1.4.1 2" vent lines from IUG System (Scope Approx. 12 inch dia) 2 days Tue 16‐01‐18 Wed 17‐01‐18 P‐7
313 1.1.1.1.4.1 Installation of vent network 48 days Mon 25‐12‐17 Sat 10‐02‐18
314 1.1.1.1.4.1 6" Vent Header & Vent Boom piping (Scope Apprx. 62 Mtr, 144 inch Dia) 11 days Mon 25‐12‐17 Thu 04‐01‐18 P‐7
315 1.1.1.1.4.1 2" Vent lines fromTest & Production header & well fluid flow arms gas Flow arm(10 11 days Fri 05‐01‐18 Mon 15‐01‐18 P‐7
nos)(Scope Apprx. 140 mtr, 80 inch dia)
316 1.1.1.1.4.1 6" Vent Lines from Test Separator (Scope Apprx. 12 inch dia) 3 days Tue 16‐01‐18 Thu 18‐01‐18 P‐7
317 1.1.1.1.4.1 2" vent lines from Well Fluid Launcher‐2nos. (Scope Apprx. 8 inch dia) 5 days Fri 19‐01‐18 Tue 23‐01‐18 P‐7
318 1.1.1.1.4.1 3" Vent line from Lift gas Launcher (Scope Apprx. 20 inch dia) 3 days Wed 24‐01‐18 Fri 26‐01‐18 P‐7
319 1.1.1.1.4.1 2" Vent from Lift gas flow arms(Scope Apprx. 100 inch dia) 8 days Sat 27‐01‐18 Sat 03‐02‐18 P‐7
320 1.1.1.1.4.1 2" vent lines from IUG System (Scope Approx. 12 inch dia) 2 days Sun 04‐02‐18 Mon 05‐02‐18 P‐7
321 1.1.1.1.4.1 2" & 3" Vent lines from CCD (Efflunt Disposel system)(Scope Aprox. 45 inch dia) 5 days Tue 06‐02‐18 Sat 10‐02‐18 P‐7
322 1.1.1.1.4.1 Installation of Co2 Snuffing System 2 days Thu 25‐01‐18 Fri 26‐01‐18
324 1.1.1.1.4.1 Glycol Seal Pot Replacement 3 days Sat 27‐01‐18 Mon 29‐01‐18
326 1.1.1.1.4.1 Common Activities 34 days Wed 10‐01‐18 Mon 12‐02‐18
327 Installation Installation Of Piping Supports 4 days Fri 09‐02‐18 Mon 12‐02‐18 P‐7
328 1.1.1.1.4.1 NDT/PWHT 21 days Wed 10‐01‐18 Tue 30‐01‐18
329 1.1.1.1.4.1 Hydro testing 9 days Wed 24‐01‐18 Thu 01‐02‐18 Hy‐1
330 1.1.1.1.4.1 Re‐Instatement 2 days Fri 02‐02‐18 Sat 03‐02‐18
331 1.1.1.1.4.1 Barge Fabrication team 32 days Thu 21‐12‐17 Sun 21‐01‐18
332 1.1.1.1.4.1 Piping & Pipe support fabrication team (Barge) 32 days Thu 21‐12‐17 Sun 21‐01‐18 P‐8
333 1.1.1.1.4.1 Open Drain System Replacement 15 days Tue 16‐01‐18 Tue 30‐01‐18
334 1.1.1.1.4.1 Demolition of Open drain line network 15 days Tue 16‐01‐18 Tue 30‐01‐18
335 1.1.1.1.4.1 6" & 4" Drain Water Header & 3" Drain Line for Cellar Deck, Main Deck & Over board l 15 days Tue 16‐01‐18 Tue 30‐01‐18 P‐2
336 1.1.1.1.4.1 Installation of Open drain line network 12 days Thu 18‐01‐18 Mon 29‐01‐18
337 1.1.1.1.4.1 6" & 4" Drain Water Header & 3" Drain Line for Cellar Deck, Main Deck, Helideck &  12 days Thu 18‐01‐18 Mon 29‐01‐18 P‐2,P‐1
Over board line (Appx. Scope ‐  465 inch dia) 204 inch dia / 465
338 1.1.1.1.4.1 Temparory Connection for Well fluid,  Lift Gas & Water Injection Lines 11 days Wed 20‐12‐17 Sat 30‐12‐17
339 1.1.1.1.4.1 Temporary Well fluid Line from N20 to N24 7 days Wed 20‐12‐17 Tue 26‐12‐17
340 1.1.1.1.4.1 Temporary wellfluid line from N20 reciver to N24 Launcher (Approx 80 Inch Dia) 5 days Wed 20‐12‐17 Sun 24‐12‐17 P‐1A
341 1.1.1.1.4.1 Installation of supports 2 days Mon 25‐12‐17 Tue 26‐12‐17 P‐1A
342 1.1.1.1.4.1 NDT/Hydro test 2 days Mon 25‐12‐17 Tue 26‐12‐17
343 1.1.1.1.4.1 Tempoaray Lift Gas Spool between N17 launcher to N20 receiver 7 days Wed 20‐12‐17 Tue 26‐12‐17
344 1.1.1.1.4.1 Temporary lift gas spool from N17 launcher to N20 Reciver (Approx Inch Dia ‐80) 5 days Wed 20‐12‐17 Sun 24‐12‐17 P‐2A
345 1.1.1.1.4.1 Installation of supports 2 days Mon 25‐12‐17 Tue 26‐12‐17 P‐2A
346 1.1.1.1.4.1 NDT/Hydro test 2 days Mon 25‐12‐17 Tue 26‐12‐17
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

Page 6
TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I
ID WBS Task Name Duration Start Finish January February March
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
347 1.1.1.1.4.1 Tempoaray Water Injection Spool to divert water from NQD to N7  4 days Wed 27‐12‐17 Sat 30‐12‐17
348 1.1.1.1.4.1 Temporary lift gas spool from N17 launcher to N20 Reciver (Approx Inch Dia ‐40) 3 days Wed 27‐12‐17 Fri 29‐12‐17 P‐2A,P‐1A
349 1.1.1.1.4.1 Installation of supports 1 day Sat 30‐12‐17 Sat 30‐12‐17 P‐2A,P‐1A
350 1.1.1.1.4.1 NDT/Hydro test 2 days Fri 29‐12‐17 Sat 30‐12‐17
351 1.1.1.1.4.1 IUG Replacement 8 days Tue 13‐02‐18 Tue 20‐02‐18
352 1.1.1.1.4.1 Isolation & Purging 1 day Tue 13‐02‐18 Tue 13‐02‐18
353 1.1.1.1.4.1 Nitrogen Purging 1 day Tue 13‐02‐18 Tue 13‐02‐18 P‐7,P‐6
354 1.1.1.1.4.1 Demolition of IUG piping network 6 days Wed 14‐02‐18 Mon 19‐02‐18
355 1.1.1.1.4.1 2" / 1" Inst gas heater to INST gas supply header & supply network(Scope Aprox. 102  5 days Wed 14‐02‐18 Sun 18‐02‐18 P‐7,P‐6
Inch Dia)
356 1.1.1.1.4.1 2" Inst. Gas from Inst.Gas Receiver to Inst. Gas heater(Scope Aprox. 14 Mtr) 1 day Mon 19‐02‐18 Mon 19‐02‐18 P‐7,P‐6
357 1.1.1.1.4.1 Installation of IUG piping network 6 days Thu 15‐02‐18 Tue 20‐02‐18
358 1.1.1.1.4.1 2" / 1" Inst gas heater to INST gas supply header & supply network(Scope Aprox. 102  5 days Thu 15‐02‐18 Mon 19‐02‐18 P‐7,P‐6
Inch Dia)
359 1.1.1.1.4.1 2" line from Pipe to seperator (Scope Aprox. 10 Inch Dia) 1 day Tue 20‐02‐18 Tue 20‐02‐18 P‐7,P‐6
360 1.1.1.1.4.2 First Platform Shutdown (Divert Production) 5 days Tue 02‐01‐18 Sat 06‐01‐18
361 1.1.1.1.4.2 Isolation , Flushing & Nitrogen Purging 1 day Tue 02‐01‐18 Tue 02‐01‐18 P‐1,P‐2
362 1.1.1.1.4.2 Temporary Well Fluid Diversion from N20 Reciver to N24 Launcher (40 Inch dia)  3 days Wed 03‐01‐18 Fri 05‐01‐18 P‐1,P‐2
363 1.1.1.1.4.2 Temporary Lift Gas Diversion from N17 Launcher to N20 Reciverr (30 Inch dia)  3 days Wed 03‐01‐18 Fri 05‐01‐18 P‐6,P‐7
364 1.1.1.1.4.2 Temporary Connection to divert Water Injection Line from NQD to N7 (30 Inch dia) 3 days Wed 03‐01‐18 Fri 05‐01‐18 P‐8,P‐4
365 1.1.1.1.4.2 NDT 4 days Wed 03‐01‐18 Sat 06‐01‐18
366 1.1.1.1.4.2 Re‐Instatement 1 day Sat 06‐01‐18 Sat 06‐01‐18
367 1.1.1.1.4.3 POST SHUTDOWN ACTIVITIES (WELL FLUID PROD. HEADER, TEST HEADER & LIFT GAS  60 days Sun 07‐01‐18 Wed 07‐03‐18
LAUNCHER, IUG REPLACEMENT AND  ASSOCIATED PIPINGS)
368 1.1.1.1.4.3 Water Injection System 44 days Sun 07‐01‐18 Mon 19‐02‐18
369 1.1.1.1.4.3 Water Injection Shutdown activities 35 days Sun 07‐01‐18 Sat 10‐02‐18
370 1.1.1.1.4.3 Isolation & Preparatory Works 3 days Sun 07‐01‐18 Tue 09‐01‐18
371 1.1.1.1.4.3 Isolation & Positive Isolation 3 days Sun 07‐01‐18 Tue 09‐01‐18 P‐5,P‐6
372 1.1.1.1.4.3 Demolition 7 days Wed 10‐01‐18 Tue 16‐01‐18
373 1.1.1.1.4.3 10",2",6",2" & 8" Water Injection Piping from Water injection Header(Scope Aprox.  6 days Wed 10‐01‐18 Mon 15‐01‐18 P‐5,P‐6
252 Inch Dia)
374 1.1.1.1.4.3 10" Over Board line from Water injection Header (Scope Aprox. 28 Mtr,123 Inch  4 days Wed 10‐01‐18 Sat 13‐01‐18 P‐5,P‐6
Dia)
375 1.1.1.1.4.3 6" Water injection flow arms ‐ 1 nos from water injection Header (Scope Aprox. 66  3 days Sun 14‐01‐18 Tue 16‐01‐18 P‐5,P‐6
Inch Dia)
376 1.1.1.1.4.3 8" Water Injection Piping from HeaderScope Aprox. 20 Mtr,160 Inch Dia) 3 days Wed 10‐01‐18 Fri 12‐01‐18 P‐5,P‐6
377 1.1.1.1.4.3 Installation 31 days Thu 11‐01‐18 Sat 10‐02‐18
378 1.1.1.1.4.3 10",2",6",2" & 8" Water Injection Piping from Water injection Header(Scope Aprox.  12 days Thu 11‐01‐18 Mon 22‐01‐18 P‐6,P‐5
252 Inch Dia)
379 1.1.1.1.4.3 10" Over Board line from Water injection Header (Scope Aprox. 28 Mtr,123 Inch  7 days Tue 23‐01‐18 Mon 29‐01‐18 P‐6,P‐5
Dia)
380 1.1.1.1.4.3 6" Water injection flow arms ‐ 1 nos from water injection Header (Scope Aprox. 66  4 days Tue 30‐01‐18 Fri 02‐02‐18 P‐6,P‐5
Inch Dia)
381 1.1.1.1.4.3 8" Water Injection Piping from Header to W‐10 Launcher(Scope Aprox. 20 Mtr,160  8 days Sat 03‐02‐18 Sat 10‐02‐18 P‐6,P‐5
Inch Dia)
382 1.1.1.1.4.3 Common Activities 30 days Sun 21‐01‐18 Mon 19‐02‐18
383 1.1.1.1.4.3 Installation of Piping Supports 7 days Tue 06‐02‐18 Mon 12‐02‐18 P‐6,P‐5
384 1.1.1.1.4.3 NDT/PWHT 23 days Sun 21‐01‐18 Mon 12‐02‐18
385 1.1.1.1.4.3 Hydro testing 5 days Sat 10‐02‐18 Wed 14‐02‐18 Hy‐1
386 1.1.1.1.4.3 Re‐Instatement 2 days Thu 15‐02‐18 Fri 16‐02‐18
387 1.1.1.1.4.3 Pre.Comm & Commissioning 3 days Sat 17‐02‐18 Mon 19‐02‐18
388 1.1.1.1.4.3 Well Fluid System 20 days Tue 13‐02‐18 Sun 04‐03‐18
389 1.1.1.1.4.3 Isolation & Purging 2 days Tue 13‐02‐18 Wed 14‐02‐18
390 1.1.1.1.4.3 De Pressurising / Water Flushing 1 day Tue 13‐02‐18 Tue 13‐02‐18 P‐5,P‐6

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

Page 7
TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I
ID WBS Task Name Duration Start Finish January February March
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
391 1.1.1.1.4.3 Nitrogen Purging 1 day Wed 14‐02‐18 Wed 14‐02‐18 P‐5,P‐3,P‐4
392 1.1.1.1.4.3 Demolition 10 days Thu 15‐02‐18 Sat 24‐02‐18
393 1.1.1.1.4.3  12"Production & 6" Test Header(Scope Aprox. 18 inch dia) 2 days Thu 15‐02‐18 Fri 16‐02‐18 P‐5
394 1.1.1.1.4.3 6" FLOW ARMS‐5 nos (Scope Aprox. 372 inch dia) 5 days Thu 15‐02‐18 Mon 19‐02‐18 P‐3,P‐4
395 1.1.1.1.4.3 Well fluid line from Production header to well fluid Launcher (NR to NQO) & Launcher  5 days Sat 17‐02‐18 Wed 21‐02‐18 P‐5
associated pipings(Scope Aprox. 92 inch dia)
396 1.1.1.1.4.3 Well fluid line from RS8 Receiver to Well fluid Header & receiver associated pipings  3 days Thu 22‐02‐18 Sat 24‐02‐18 P‐5
(N20‐NR) (Scope Aprox. 68)
397 1.1.1.1.4.3 Installation 17 days Fri 16‐02‐18 Sun 04‐03‐18
398 1.1.1.1.4.3  12"Production & 6" Test Header(Scope Aprox. 18 inch dia) 2 days Sat 17‐02‐18 Sun 18‐02‐18 P‐5
399 1.1.1.1.4.3 6" FLOW ARMS‐5 nos (Scope Aprox. 372 inch dia) 14 days Fri 16‐02‐18 Thu 01‐03‐18 P‐3,P‐4
400 1.1.1.1.4.3 Well fluid line from Production header to well fluid Launcher (NR to NQO) & Launcher  8 days Mon 19‐02‐18 Mon 26‐02‐18 P‐5
associated pipings(Scope Aprox. 92 inch dia)
401 1.1.1.1.4.3 Well fluid line from RS8 Receiver to Well fluid Header & receiver associated pipings  6 days Tue 27‐02‐18 Sun 04‐03‐18 P‐5
(N20‐NR) (Scope Aprox. 68)
402 1.1.1.1.4.3 Test Header Piping Replacement 14 days Tue 13‐02‐18 Mon 26‐02‐18
403 1.1.1.1.4.3 (Test Header piping from test header to Test separator) 14 days Tue 13‐02‐18 Mon 26‐02‐18
404 1.1.1.1.4.3 Isolation & Flushing 2 days Tue 13‐02‐18 Wed 14‐02‐18
405 1.1.1.1.4.3 Isolation ,Depressurization & positive isolation 1 day Tue 13‐02‐18 Tue 13‐02‐18 P‐6
406 1.1.1.1.4.3 Water flushing & Nitrogen Purging 1 day Wed 14‐02‐18 Wed 14‐02‐18 P‐6
407 1.1.1.1.4.3 Demolition 6 days Thu 15‐02‐18 Tue 20‐02‐18
408 1.1.1.1.4.3 6" Test Header piping with associated Instruments,Valves Etc from Test Header to  3 days Thu 15‐02‐18 Sat 17‐02‐18 P‐6
Test separator inlet  54 inch dia
409 1.1.1.1.4.3 6 Test Separator outlet piping(Gas & Well Fluid) with associated Instruments,Valves 3 days Sun 18‐02‐18 Tue 20‐02‐18 P‐6
Etc up‐to Isolation valve near Production header (Scope Appx. 84 Inch Dia)

410 1.1.1.1.4.3 Installation 11 days Fri 16‐02‐18 Mon 26‐02‐18


411 1.1.1.1.4.3 6" Test Header piping with associated Instruments,Valves Etc from Test Header to  5 days Fri 16‐02‐18 Tue 20‐02‐18 P‐6
Test separator inlet 54 inch dia
412 1.1.1.1.4.3 6 Test Separator outlet piping(Gas & Well Fluid) with associated Instruments,Valves 6 days Wed 21‐02‐18 Mon 26‐02‐18 P‐6
Etc up‐to Isolation valve near Production header (Scope Appx. 84 Inch Dia)

413 1.1.1.1.4.3 Lift Gas System 29 days Tue 30‐01‐18 Tue 27‐02‐18


414 1.1.1.1.4.3 Isolation & Purging 2 days Tue 30‐01‐18 Wed 31‐01‐18
416 1.1.1.1.4.3 Demolition 7 days Thu 01‐02‐18 Wed 07‐02‐18
417 1.1.1.1.4.3 10" Lift gas from N17 platform to Lift gas header, receiver associated pipings and 6"  4 days Thu 01‐02‐18 Sun 04‐02‐18 P‐1
gas injection manifold( Scope Aprox. 80 Inch Dia)
418 1.1.1.1.4.3 6" Lift gas line from header to N20 launcher & launcher associated piping( Scope  3 days Mon 05‐02‐18 Wed 07‐02‐18 P‐1
Aprox. 26 Inch Dia)
419 1.1.1.1.4.3 2" Lift gas to IUG system(Lift gas seperator inlet)( Scope Aprox. 18 Mtr, 32 Inch Dia) 3 days Thu 01‐02‐18 Sat 03‐02‐18 P‐1
420 1.1.1.1.4.3 2"Lift gas flow arm‐5 nos and from lift gas seperator( Scope Aprox. 170 Inch Dia ) 2 days Thu 01‐02‐18 Fri 02‐02‐18 P‐2
421 1.1.1.1.4.3 4" Lift gas De‐Watering line to well fluid launcher( Scope Aprox. 27 Mtr, 27 Inch Dia) 1 day Sun 04‐02‐18 Sun 04‐02‐18 P‐1
422 1.1.1.1.4.3 2" Lift gas to CCD( Scope Aprox. 37 Mtr, 30 Inch Dia) 2 days Mon 05‐02‐18 Tue 06‐02‐18 P‐1
423 1.1.1.1.4.3 Installation 18 days Fri 02‐02‐18 Mon 19‐02‐18
424 1.1.1.1.4.3 10" Lift gas from N17 platform to Lift gas header, receiver associated pipings and 6"  7 days Fri 02‐02‐18 Thu 08‐02‐18 P‐1
gas injection manifold( Scope Aprox. 80 Inch Dia)
425 1.1.1.1.4.3 6" Lift gas line from header to N20 launcher & launcher associated piping( Scope  2 days Fri 09‐02‐18 Sat 10‐02‐18 P‐1
Aprox. 26 Inch Dia)
426 1.1.1.1.4.3 2" Lift gas to IUG system(Lift gas seperator inlet)( Scope Aprox. 18 Mtr, 32 Inch Dia) 4 days Sun 11‐02‐18 Wed 14‐02‐18 P‐1
427 1.1.1.1.4.3 2"Lift gas flow arm‐5 nos and from lift gas seperator( Scope Aprox. 170 Inch Dia ) 15 days Fri 02‐02‐18 Fri 16‐02‐18 P‐2
428 1.1.1.1.4.3 4" Lift gas De‐Watering line to well fluid launcher( Scope Aprox. 27 Mtr, 27 Inch Dia) 3 days Thu 15‐02‐18 Sat 17‐02‐18 P‐1
429 1.1.1.1.4.3 2" Lift gas to CCD( Scope Aprox. 37 Mtr, 30 Inch Dia) 2 days Sun 18‐02‐18 Mon 19‐02‐18 P‐1
430 1.1.1.1.4.3 Common Activities 25 days Sat 03‐02‐18 Tue 27‐02‐18
431 1.1.1.1.4.3 Installation of Piping Supports 12 days Sat 10‐02‐18 Wed 21‐02‐18 P‐1
432 1.1.1.1.4.3 NDT/PWHT 21 days Sat 03‐02‐18 Fri 23‐02‐18

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

Page 8
TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I
ID WBS Task Name Duration Start Finish January February March
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
433 1.1.1.1.4.3 Hydro testing 5 days Wed 21‐02‐18 Sun 25‐02‐18
434 1.1.1.1.4.3 Re‐Instatement 1 day Mon 26‐02‐18 Mon 26‐02‐18
435 1.1.1.1.4.3 Pre.Comm & Commissioning 1 day Tue 27‐02‐18 Tue 27‐02‐18
436 1.1.1.1.4.3 Sump‐caission Isolation & Piping Demolition 15 days Sat 17‐02‐18 Sat 03‐03‐18
437 1.1.1.1.4.3 Demolition of Piping spools 4 days Sat 17‐02‐18 Tue 20‐02‐18 P‐2
438 1.1.1.1.4.3 Isolation of Sump caission 4 days Wed 21‐02‐18 Sat 24‐02‐18 P‐2
439 1.1.1.1.4.3 Diesel line demolition 5 days Sun 25‐02‐18 Thu 01‐03‐18 P‐2
440 1.1.1.1.4.3 Chemical lines demolition 5 days Tue 27‐02‐18 Sat 03‐03‐18 P‐2
441 1.1.1.1.4.3 Installation of Sprinkler System 7 days Wed 21‐02‐18 Tue 27‐02‐18
442 1.1.1.1.4.3 Installation of Sprinkler Network (Appx. Scope ‐ 183) 7 days Wed 21‐02‐18 Tue 27‐02‐18 P‐1,P‐2,P‐3,P‐4,P‐5,P‐6,P‐7
443 1.1.1.1.4.3 Common Activities 33 days Sat 03‐02‐18 Wed 07‐03‐18
444 1.1.1.1.4.3 Installation of Piping Supports 27 days Sat 03‐02‐18 Thu 01‐03‐18 P‐3,P‐5,P‐4
445 1.1.1.1.4.3 NDT/PWHT 28 days Sun 04‐02‐18 Sat 03‐03‐18
446 1.1.1.1.4.3 Hydro testing 22 days Sun 11‐02‐18 Sun 04‐03‐18
447 1.1.1.1.4.3 Re‐Instatement 16 days Sun 18‐02‐18 Mon 05‐03‐18
448 1.1.1.1.4.3 Pre‐Comm &  Commissioning 8 days Wed 28‐02‐18 Wed 07‐03‐18
449 1.1.1.1.4.4 Painting 41 days Fri 26‐01‐18 Wed 07‐03‐18
450 1.1.1.1.4.4 Touch Up Painting 41 days Fri 26‐01‐18 Wed 07‐03‐18
451 1.1.1.1.5 Architectural Activities 62 days Tue 02‐01‐18 Sun 04‐03‐18
452 1.1.1.1.5.1 SWITCHGEAR ROOM  24 days Tue 02‐01‐18 Thu 25‐01‐18
453 1.1.1.1.5.1 DEMOLITION 8 days Tue 02‐01‐18 Tue 09‐01‐18
454 1.1.1.1.5.1 Ceiling (13 sq.m) 1 day Tue 02‐01‐18 Tue 02‐01‐18 ST‐5
455 1.1.1.1.5.1 vinyal sheet (13 sq.m) 1 day Tue 02‐01‐18 Tue 02‐01‐18 ST‐5
456 1.1.1.1.5.1 Wall panel (44 sq.m) 3 days Wed 03‐01‐18 Fri 05‐01‐18 ST‐5
457 1.1.1.1.5.1 Door, window & louver (3 no.) 1 day Thu 04‐01‐18 Thu 04‐01‐18 ST‐5
458 1.1.1.1.5.1 Screeding (13 sq.m) 2 days Fri 05‐01‐18 Sat 06‐01‐18 ST‐5
459 1.1.1.1.5.1 Insulation (74 Sq.m) 2 days Fri 05‐01‐18 Sat 06‐01‐18 ST‐5
460 1.1.1.1.5.1 Chequered plate (11 Sq.m) 3 days Sun 07‐01‐18 Tue 09‐01‐18 ST‐5
461 1.1.1.1.5.1 Member of MC150 (1.2m X 4 ) 1 day Mon 08‐01‐18 Mon 08‐01‐18 ST‐5
462 1.1.1.1.5.1 INSTALLATION 17 days Tue 09‐01‐18 Thu 25‐01‐18
463 1.1.1.1.5.1 Member of MC150 (1.2m X 4 ) 2 days Tue 09‐01‐18 Wed 10‐01‐18 ST‐5
464 1.1.1.1.5.1 Chequered plate (11 Sq.m) 5 days Thu 11‐01‐18 Mon 15‐01‐18 ST‐5
465 1.1.1.1.5.1  Insulation (74 Sq.m) 4 days Tue 16‐01‐18 Fri 19‐01‐18 ST‐5
466 1.1.1.1.5.1  Top bottom profile (29 mtr) 1 day Tue 16‐01‐18 Tue 16‐01‐18 ST‐5
467 1.1.1.1.5.1  Wall panel (44 sq.m) 3 days Wed 17‐01‐18 Fri 19‐01‐18 ST‐5
468 1.1.1.1.5.1  Door, window & louver (3 no.) 2 days Tue 16‐01‐18 Wed 17‐01‐18 ST‐5
469 1.1.1.1.5.1  Screeding (13 sq.m) 3 days Sat 20‐01‐18 Mon 22‐01‐18 ST‐5
470 1.1.1.1.5.1  Ceiling (13 sq.m) 2 days Tue 23‐01‐18 Wed 24‐01‐18 ST‐5
471 1.1.1.1.5.1  vinyal sheet (13 sq.m) 2 days Wed 24‐01‐18 Thu 25‐01‐18 ST‐5
472 1.1.1.1.5.2 TELEMETRY ROOM 27 days Tue 02‐01‐18 Sun 28‐01‐18
473 1.1.1.1.5.2 DEMOLITION 12 days Tue 02‐01‐18 Sat 13‐01‐18
474 1.1.1.1.5.2  Ceiling (11 Sq.m) 1 day Tue 02‐01‐18 Tue 02‐01‐18 ST‐5
475 1.1.1.1.5.2  Vinyal sheet (11 Sq.m) 1 day Tue 02‐01‐18 Tue 02‐01‐18 ST‐5
476 1.1.1.1.5.2  Wall panel (41 Sq.m) 3 days Wed 03‐01‐18 Fri 05‐01‐18 ST‐5
477 1.1.1.1.5.2  Door, window & louver (3 no.) 1 day Wed 10‐01‐18 Wed 10‐01‐18 ST‐5
478 1.1.1.1.5.2  Screeding (11 Sq.m) 2 days Sat 06‐01‐18 Sun 07‐01‐18 ST‐5
479 1.1.1.1.5.2  Insulation (68 sq.m) 2 days Mon 08‐01‐18 Tue 09‐01‐18 ST‐5
480 1.1.1.1.5.2 Chequered plate (11 Sq.m) 3 days Thu 11‐01‐18 Sat 13‐01‐18 ST‐5
481 1.1.1.1.5.2 INSTALLATION 11 days Thu 18‐01‐18 Sun 28‐01‐18
482 1.1.1.1.5.2 Chequered plate (11 Sq.m) 4 days Thu 18‐01‐18 Sun 21‐01‐18 ST‐5
483 1.1.1.1.5.2  Insulation (68 sq.m) 3 days Mon 22‐01‐18 Wed 24‐01‐18 ST‐5
484 1.1.1.1.5.2  Top bottom profile (27 mtr) 1 day Mon 22‐01‐18 Mon 22‐01‐18 ST‐5
485 1.1.1.1.5.2  Wall panel (41 Sq.m) 2 days Tue 23‐01‐18 Wed 24‐01‐18 ST‐5

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

Page 9
TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I
ID WBS Task Name Duration Start Finish January February March
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
486 1.1.1.1.5.2  Door, window & louver (3 no.) 2 days Mon 22‐01‐18 Tue 23‐01‐18 ST‐5
487 1.1.1.1.5.2  Screeding (11 Sq.m) 1 day Thu 25‐01‐18 Thu 25‐01‐18 ST‐5
488 1.1.1.1.5.2  Ceiling (11 Sq.m) 2 days Fri 26‐01‐18 Sat 27‐01‐18 ST‐5
489 1.1.1.1.5.2  Vinyal sheet (11 Sq.m) 2 days Sat 27‐01‐18 Sun 28‐01‐18 ST‐5
490 1.1.1.1.5.3 Bunk house (demolition) 3 days Mon 29‐01‐18 Wed 31‐01‐18
491 1.1.1.1.5.3 Furniture ( 6 no.) 1 day Mon 29‐01‐18 Mon 29‐01‐18 ST‐5
492 1.1.1.1.5.3 Ceiling (10 Sq.m) 1 day Mon 29‐01‐18 Mon 29‐01‐18 ST‐5
493 1.1.1.1.5.3 Vinyal sheet (10 Sq.m) 1 day Mon 29‐01‐18 Mon 29‐01‐18 ST‐5
494 1.1.1.1.5.3 Wall panel (33 Sq.m) 2 days Tue 30‐01‐18 Wed 31‐01‐18 ST‐5
495 1.1.1.1.5.3 Door & window (2 no.) 1 day Tue 30‐01‐18 Tue 30‐01‐18 ST‐5
496 1.1.1.1.5.3 Screeding (10 Sq.m) 1 day Wed 31‐01‐18 Wed 31‐01‐18 ST‐5
497 1.1.1.1.5.3 Insulation (34 sq.m) 1 day Wed 31‐01‐18 Wed 31‐01‐18 ST‐5
498 1.1.1.1.5.4 Bunk house (installation) 11 days Thu 01‐02‐18 Sun 11‐02‐18
499 1.1.1.1.5.4 Insulation (34 sq.m) 2 days Thu 01‐02‐18 Fri 02‐02‐18 ST‐5
500 1.1.1.1.5.4 Top bottom profile (27mtr) 1 day Fri 02‐02‐18 Fri 02‐02‐18 ST‐5
501 1.1.1.1.5.4 Wall panel (33 Sq.m) 2 days Sat 03‐02‐18 Sun 04‐02‐18 ST‐5
502 1.1.1.1.5.4 Door & window (2 no.) 1 day Mon 05‐02‐18 Mon 05‐02‐18 ST‐5
503 1.1.1.1.5.4 Screeding (10 Sq.m) 2 days Tue 06‐02‐18 Wed 07‐02‐18 ST‐5
504 1.1.1.1.5.4 Ceiling (10 Sq.m) 1 day Thu 08‐02‐18 Thu 08‐02‐18 ST‐5
505 1.1.1.1.5.4 Vinyal sheet (10 Sq.m) 2 days Fri 09‐02‐18 Sat 10‐02‐18 ST‐5
506 1.1.1.1.5.4 Furniture ( 6 no.) 1 day Sun 11‐02‐18 Sun 11‐02‐18 ST‐5
507 1.1.1.1.5.5 Battery room (demolition) 7 days Mon 12‐02‐18 Sun 18‐02‐18
508 1.1.1.1.5.5 Floor tiles (38 sq.m) 2 days Mon 12‐02‐18 Tue 13‐02‐18 ST‐5
509 1.1.1.1.5.5 Wall panel (84 Sq. m) 2 days Mon 12‐02‐18 Tue 13‐02‐18 ST‐5
510 1.1.1.1.5.5 Door, window & louver (14 no.) 3 days Mon 12‐02‐18 Wed 14‐02‐18 ST‐5
511 1.1.1.1.5.5 Insulation (106 sq.m) 2 days Thu 15‐02‐18 Fri 16‐02‐18 ST‐5
512 1.1.1.1.5.5 Screeding (38 sq.m) 2 days Sat 17‐02‐18 Sun 18‐02‐18 ST‐5
513 1.1.1.1.5.6 Battery room (installation) 14 days Mon 19‐02‐18 Sun 04‐03‐18
514 1.1.1.1.5.6 Insulation (106 sq.m) 3 days Mon 19‐02‐18 Wed 21‐02‐18
515 1.1.1.1.5.6 Top bottom profile (43mtr) 1 day Tue 20‐02‐18 Tue 20‐02‐18 ST‐5
516 1.1.1.1.5.6 Wall panel (84 Sq. m) 2 days Wed 21‐02‐18 Thu 22‐02‐18 ST‐5
517 1.1.1.1.5.6 Door, window & louver (14 no.) 5 days Fri 23‐02‐18 Tue 27‐02‐18 ST‐5
518 1.1.1.1.5.6 Screeding (38 sq.m) 2 days Wed 28‐02‐18 Thu 01‐03‐18 ST‐5
519 1.1.1.1.5.6 Floor tiles (38 sq.m) 3 days Fri 02‐03‐18 Sun 04‐03‐18 ST‐5
520 1.1.1.1.6 E&I Activities 67 days Wed 20‐12‐17 Sat 24‐02‐18
521 1.1.1.1.6.1 Electrical panel Dismantling ‐ 8 Nos 3 days Wed 20‐12‐17 Fri 22‐12‐17 E&I T‐1
522 1.1.1.1.6.2 Support Dismantling & Support Installation ‐Electrical ‐5.3 Ton 16 days Sat 23‐12‐17 Sun 07‐01‐18 E&I T‐1
523 1.1.1.1.6.3 MCT base frame installation ‐6 Nos (Elec & Instru) 2 days Mon 08‐01‐18 Tue 09‐01‐18 E&I T‐1
524 1.1.1.1.6.4 Solar panel Installation(F&G) ‐ 36 Nos 2 days Wed 10‐01‐18 Thu 11‐01‐18 E&I T‐1
525 1.1.1.1.6.5 Junction Box Installation (Solar &Lighting ) ‐ 18 Nos 1 day Fri 12‐01‐18 Fri 12‐01‐18 E&I T‐1
526 1.1.1.1.6.6 Light Fixture Installation, 2 Pole Switches installation ‐10 Nos & Change Over Switch  2 days Wed 17‐01‐18 Thu 18‐01‐18 E&I T‐1
installation ‐1 Nos
527 1.1.1.1.6.7 Solar Controller Panel & DC Distribution Board installation ‐4 Nos 2 days Fri 19‐01‐18 Sat 20‐01‐18 E&I T‐1
528 1.1.1.1.6.8 Battery bank Replacement ‐2 Nos 4 days Sat 13‐01‐18 Tue 16‐01‐18 E&I T‐1
529 1.1.1.1.6.9 Installation of Inst Panels‐ 2 Nos 3 days Sun 21‐01‐18 Tue 23‐01‐18 E&I T‐1
530 1.1.1.1.6.1 Support Fabrication (Elect & Instru) ‐ 9 Ton 50 days Wed 20‐12‐17 Wed 07‐02‐18 E&I T‐2
531 1.1.1.1.6.1 Support Installation‐ Instru ‐6.8 Ton 51 days Thu 21‐12‐17 Fri 09‐02‐18 E&I T‐3
532 1.1.1.1.6.1 Cable Tray dismantling( Elec & Instru) ‐681 Mtr 13 days Thu 21‐12‐17 Tue 02‐01‐18 E&I T‐5
533 1.1.1.1.6.1 Cable & Tube Tray Installation (Elec & Instru) ‐ 2700 Mtr 39 days Wed 03‐01‐18 Sat 10‐02‐18 E&I T‐5
534 1.1.1.1.6.1 Solar panel Demolition ‐ 2 Nos 1 day Wed 20‐12‐17 Wed 20‐12‐17 E&I T‐7
535 1.1.1.1.6.1 Cable Dismantling (Elect & Instru) ‐8.8 Km 13 days Thu 21‐12‐17 Tue 02‐01‐18 E&I T‐7
536 1.1.1.1.6.1 Instruments Dismantling ‐106 Nos 9 days Wed 03‐01‐18 Thu 11‐01‐18 E&I T‐7
537 1.1.1.1.6.1 Cable laying ‐ Electrical ‐1304 Mtr 9 days Fri 12‐01‐18 Sat 20‐01‐18 E&I T‐7

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only

Page 10
TENTATIVE SCHEDULE FOR NR PLATFORM - PROJECT LEWPP I
ID WBS Task Name Duration Start Finish January February March
T F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S
538 1.1.1.1.6.1 Electrical Equip Demolition (Light Fixture‐71 Nos,JB‐47 Nos & Socket ‐ 7 Nos) 23 days Wed 20‐12‐17 Thu 11‐01‐18 E&I T‐9
539 1.1.1.1.6.1 Glanding & Termination (F&G System ‐electrical) ‐152 Nos 11 days Fri 12‐01‐18 Mon 22‐01‐18 E&I T‐9
540 1.1.1.1.6.2 Pre‐Comm Activities‐ Electrical ‐ 1 Lot 8 days Tue 16‐01‐18 Tue 23‐01‐18 E&I T‐8
541 1.1.1.1.6.2 Support Dismantling ( Instru ) ‐ 3.3 Ton 21 days Wed 20‐12‐17 Tue 09‐01‐18 E&I T‐4
542 1.1.1.1.6.2 F&G Detector Dismantling ‐ 15 Nos 2 days Wed 10‐01‐18 Thu 11‐01‐18 E&I T‐4
543 1.1.1.1.6.2 Replacement of SDP(Test Separator) ‐ 1 Nos 2 days Fri 12‐01‐18 Sat 13‐01‐18 E&I T‐4
544 1.1.1.1.6.2 Instrument JB Dismantling ‐18 Nos 4 days Sun 14‐01‐18 Wed 17‐01‐18 E&I T‐4
545 1.1.1.1.6.2 Installation of JB (intrsu & f&g ) ‐19 Nos 3 days Thu 18‐01‐18 Sat 20‐01‐18 E&I T‐4
546 1.1.1.1.6.2 IGM Installation ‐6 Nos 2 days Sun 21‐01‐18 Mon 22‐01‐18 E&I T‐4
547 1.1.1.1.6.2 Installation of ESD & FSD Pull Stations ‐8 Nos 1 day Tue 23‐01‐18 Tue 23‐01‐18 E&I T‐4
548 1.1.1.1.6.2 Tube Dismantling ‐2.3 km 6 days Wed 20‐12‐17 Mon 25‐12‐17 E&I T‐6
549 1.1.1.1.6.2 Tube Tray dismantling ‐ 165 Mtr 6 days Tue 26‐12‐17 Sun 31‐12‐17 E&I T‐6
550 1.1.1.1.6.3 Tube Laying ( ESD FSD , Impulse & Control Tubing) ‐3730 Mtr 23 days Mon 01‐01‐18 Tue 23‐01‐18 E&I T‐6
551 1.1.1.1.6.3 Tube Laying (Drain & vent)‐ 520 Mtr 10 days Sat 10‐02‐18 Mon 19‐02‐18 E&I T‐6
552 1.1.1.1.6.3 Calibration of Instruments ‐167 Nos 27 days Wed 20‐12‐17 Mon 15‐01‐18 E&I T‐8
553 1.1.1.1.6.3 Instruments Dismantling ‐ Shut Down Related 2 days Wed 24‐01‐18 Thu 25‐01‐18 E&I T‐8
554 1.1.1.1.6.3 Installation of Instruments ‐174 Nos 11 days Fri 26‐01‐18 Mon 05‐02‐18 E&I T‐8
555 1.1.1.1.6.3 Installation of f&g detector/ Equipments ‐ 46 Nos 3 days Tue 06‐02‐18 Thu 08‐02‐18 E&I T‐8
556 1.1.1.1.6.3 Pre‐Comm Activities‐ Instru ‐1 Lot 13 days Fri 09‐02‐18 Wed 21‐02‐18 E&I T‐8
557 1.1.1.1.6.3 Cable laying : multipair and branch ‐5155 Mtr 19 days Sun 21‐01‐18 Thu 08‐02‐18 E&I T‐7
558 1.1.1.1.6.3 Glanding and Termination (Instru Branch Cable)‐262 Nos 17 days Tue 23‐01‐18 Thu 08‐02‐18 E&I T‐9
559 1.1.1.1.6.3 Installation Of Solar Panel (Lighting) 1 day Tue 06‐02‐18 Tue 06‐02‐18 E&I T‐1
560 1.1.1.1.6.4 Glanding & Termination (Lighting ‐electrical) ‐54Nos 1 day Fri 09‐02‐18 Fri 09‐02‐18 E&I T‐9&7
561 1.1.1.1.6.4 MCT Filling, Tray Cover Installation, Tagging (Elect) ‐ 1 Lot 13 days Mon 12‐02‐18 Sat 24‐02‐18 E&I T‐4
562 1.1.1.1.6.4 MCT Filling, Tray Cover Installation, Tagging (Instru) ‐ 1 Lot 14 days Sun 11‐02‐18 Sat 24‐02‐18 E&I T‐1
563 1.1.1.1.6.4 Shut down Activities (E&I) 29 days Wed 24‐01‐18 Wed 21‐02‐18
564 1.1.1.1.6.4  SSV & SSSV Tube Dismantling ‐ 600 Mtr 5 days Wed 24‐01‐18 Sun 28‐01‐18 E&I T‐4
565 1.1.1.1.6.4  ESD FSD Station Dismantling ‐ 10 Nos 2 days Mon 29‐01‐18 Tue 30‐01‐18 E&I T‐4
566 1.1.1.1.6.4  Inst. Panel & Inst JB Dismantling ‐10 Nos 4 days Wed 31‐01‐18 Sat 03‐02‐18 E&I T‐4
567 1.1.1.1.6.4  Replacement of SDP ‐ 1 Nos 4 days Sun 04‐02‐18 Wed 07‐02‐18 E&I T‐4
568 1.1.1.1.6.4  Dismantling of SDP to TIC Interconnection Cables ‐ 12 Nos 2 days Wed 24‐01‐18 Thu 25‐01‐18 E&I T‐1
569 1.1.1.1.6.4  TIC Replacement ‐ 1 Nos 3 days Fri 26‐01‐18 Sun 28‐01‐18 E&I T‐1
570 1.1.1.1.6.4  SSV & SSSV Tube Laying ‐800 Mtr 11 days Wed 24‐01‐18 Sat 03‐02‐18 E&I T‐6
571 1.1.1.1.6.4  SSV & SSSV Tube Testing ‐800 Mtr 3 days Sun 04‐02‐18 Tue 06‐02‐18 E&I T‐6
572 1.1.1.1.6.4  Hook up of ESD FSD Loop ‐ 8 Nos 3 days Wed 07‐02‐18 Fri 09‐02‐18 E&I T‐6
573 1.1.1.1.6.4  Hook Up of Production Related Instruments ‐ 1 Lot 3 days Sat 03‐02‐18 Mon 05‐02‐18 E&I T‐1
574 1.1.1.1.6.4  Relocation of Solar panel (Telemetry System) 5 days Mon 29‐01‐18 Fri 02‐02‐18 E&I T‐1
575 1.1.1.1.6.4  Glanding & Termination (Instru ‐ Multipair Cable) ‐70 nos 5 days Sat 10‐02‐18 Wed 14‐02‐18 E&I T‐9&7
576 1.1.1.1.6.4  RTU Termination & modification 4 days Thu 15‐02‐18 Sun 18‐02‐18 E&I T‐9
577 1.1.1.1.6.4  SCADA Integration 3 days Mon 19‐02‐18 Wed 21‐02‐18 E&I T‐9
578 1.1.1.1.6.4  Power supply modifuication for Telemetry system 7 days Thu 15‐02‐18 Wed 21‐02‐18 E&I T‐7
579 1.1.1.1.7 Scaffolding Removal 26 days Sun 11‐02‐18 Thu 08‐03‐18
580 1.1.1.1.7.1  Scaffolding Removing  26 days Sun 11‐02‐18 Thu 08‐03‐18 SC‐1,SC‐2
581 1.1.1.1.8 Demobilization Activities 1 day Fri 09‐03‐18 Fri 09‐03‐18
582 1.1.1.1.8.1 Gangway Removal & Anchor Handling 1 day Fri 09‐03‐18 Fri 09‐03‐18

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: LEWPP 1‐ NR PLATFORM Split External Tasks Inactive Summary Manual Summary Progress


Date: Fri 24‐11‐17 Milestone External Milestone Manual Task Start‐only Manual Progress
Summary Inactive Task Duration‐only Finish‐only