ID Task Name Duration Start Finish Predecessors Successors Task Calendar Deadline January 2022 February 2022 March

Predecessors Successors Task Calendar Deadline January 2022 February 2022 March 2022 April 2022 May 2022 June 2022
31030609121518212427300205081114172023260104071013161922252831030609121518212427300306091215182124273002
1 24in Shell Sarawak F28 (draft schedule) 77 days Fri 28-01-22 Mon 16-05-22 Standard NA

2 award date 0 days Fri 28-01-22 Fri 28-01-22 4 Standard NA 28-01

3 Engineering 27 days Fri 28-01-22 Mon 07-03-22 Standard NA

4 Data collection from client + site visit 7 days Fri 28-01-22 Mon 07-02-22 2 5 Standard NA

5 Ops Engineering 20 days Tue 08-02-22 Mon 07-03-22 4 8SS+10 days Standard NA

7 Tool Assembly and Testing 22 days Tue 22-02-22 Wed 23-03-22 Standard NA

8 Assembly for FAT 10 days Tue 22-02-22 Mon 07-03-22 5SS+10 days 9 Standard NA

9 Internal FAT 2 days Tue 08-03-22 Wed 09-03-22 8 10FS+3 days Standard NA

10 Gas intrusion test 2 days Tue 15-03-22 Wed 16-03-22 9FS+3 days 11FS+3 days Standard NA

11 Client FAT 2 days Tue 22-03-22 Wed 23-03-22 10FS+3 days 13,14 Standard NA

12

13 Tool Shipment 20 days Thu 24-03-22 Tue 12-04-22 11 7 days/week NA

14 Pack and prepare for shipment 3 days Thu 24-03-22 Mon 28-03-22 11 15 Standard NA

15 Ex.W Stavanger 0 days Mon 28-03-22 Mon 28-03-22 14 16 Standard NA 28-03

16 Airfreight to Malaysia 10 days Tue 29-03-22 Thu 07-04-22 15 17 7 days/week NA

17 Handling, clearance Locally 2 days Fri 08-04-22 Sat 09-04-22 16 18FS+3 days 7 days/week NA

18 Tool on site 0 days Tue 12-04-22 Tue 12-04-22 17FS+3 days 27 7 days/week NA 12-04

19

20 Crew mobilization 16 days Mon 28-03-22 Wed 13-04-22 7 days/week NA

21 Crew mob from Norway 0 days Mon 28-03-22 Mon 28-03-22 22SF 7 days/week NA 28-03

22 Flight to Malaysia 1 day Mon 28-03-22 Tue 29-03-22 23SF 21SF 7 days/week NA

23 Quarantine (Malaysia + Sarawak) 14 days Tue 29-03-22 Tue 12-04-22 24SF-1 day 22SF 7 days/week NA

24 Crew ready to start work 0 days Wed 13-04-22 Wed 13-04-22 27SF 23SF-1 day 7 days/week NA 13-04

25

26 Field operation 34 days Wed 13-04-22 Mon 16-05-22 7 days/week NA

27 Rigging up 3 days Wed 13-04-22 Fri 15-04-22 18,28SF 24SF 7 days/week NA

28 Launching 1 day Fri 15-04-22 Fri 15-04-22 29,27SF 7 days/week NA

29 Isolation 14 days Sat 16-04-22 Fri 29-04-22 28 30 7 days/week NA

30 Retrieval 1 day Sat 30-04-22 Sat 30-04-22 29 31 7 days/week NA

31 Pack and prepare for return shipment 2 days Sun 01-05-22 Mon 02-05-22 30 32 7 days/week NA

32 Return shipment 14 days Tue 03-05-22 Mon 16-05-22 31 7 days/week NA

Task Project Summary Inactive Milestone Manual Summary Rollup Progress


Project: Shell F28 Split External Tasks Inactive Summary Manual Summary Deadline
Date: 18 Jan 2022
Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only