ID Task Task Name Duration Start Finish Predecessors 13 Apr '20 20 Apr '20 27 Apr '20 04 May '20

Apr '20 20 Apr '20 27 Apr '20 04 May '20 11 May '20 18 May '20
Mode S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1

2 Curatarea terenului 1 day Mon 13- Mon 13


3 Trasare 0.5 days Mon 13- Mon 13 2FF
4 Sapatura subsol 2 days Tue 14-0 Wed 15 2
5 Turnarea egalizarii la subsol 1 day Wed 15- Thu 16- 4
6 Trasarea Fundatiilor si a peretilor 0.5 days Thu Thu 5
la subsol 16-04-2016-04-2
7 Armarea funatiilor 2 days Fri 17-04 Mon 20 6
8 Axarea peretilor 0.5 days Tue 21-0 Tue 21- 7FF
9 Turnarea blocului de fundare 0.5 days Wed 22- Wed 22 8
10 Aramrea peretilor la fundatii 2 days Wed 22- Fri 24-0 9
11 Trasarea cofrajului la pereti 0.5 days Fri 24-04 Fri 24-0 10FF
12 Cofrarea peretilor la subsol etapa 2 days Thu Mon 10FF+1 day
1 23-04-2027-04-2
13 Turnarea betonului la subsol
0.5 days Mon Mon 12
etapa 1 27-04-2027-04-2
14 Cofrarea peretilor la subsol etapa 2 days Fri
Tue 13SF+1 day
2 24-04-2028-04-2
15 Turnarea peretilor la subsol etapa 0.5 days Tue Tue 14
2 28-04-2028-04-2
16 Hidroizolarea peretilor la subsol 1 day? Tue Tue 13
28-04-2028-04-2
17 Umpluturi de pamant 2 days Wed 29- Thu 30- 15
18 Trasarea fundatii dub cota 0.00 0.5 days Fri 01-05 Fri 01-0 17
19 Sapatura fundatii dub cota 0.00 1 day Fri 01-05 Mon 04 18
20 Turanarea egalizarii 0.5 days Mon 04- Mon 04 19FF
21 Aramrea fundatiilor 2 days Mon 04- Wed 06 20
22 Cofrarea fundatiilor 2 days Wed 06- Fri 08-0 21
23 Turnarea fundatiilor 0.5 days Fri 08-05 Fri 08-0 22FF
24 Umpluturi de balast 2 days Fri 08-05 Tue 12- 23
25 Montarea termoizolatiei 1 day Tue 12-0 Wed 13 24
26 Cofrarea placii cota 0.00 2 days Wed 13- Fri 15-0 25
27 Turnarea Placii BA cota 0.00 1 day Fri 15-05 Mon 18 26
28 Hidroizolarea fundatiilor 1 day Mon 18- Tue 19- 27
29 Umpluturi de pamant si balast 2 days Tue 19-0 Thu 21- 28

Task Project Summary Manual Task Start-only Deadline

Project: Grafic de executie Split Inactive Task Duration-only Finish-only Progress


12.04 Date: Mon 13-04-20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone