ID Task TaskName Duration Start Finish Thu16Mar Mon20Mar Fri24Mar Tue28Mar Sat01Apr Wed05Apr Sun09Apr

Mode 12 9 6 3 12 9 6 3 12 9 6 3 12 9
1 RAWADVILLAWORKSCHEDULE 0.88days Mon200317 Mon200317
2 COMPOUNDWALLWORK 0.88days Mon200317 Mon200317
3
4 RCCWork 19days Mon200317 Fri070417
5 Concreting(8040)=40m,1stlift 0.88days Mon200317 Mon200317
6 Deshuttering(8040)=40m,1stlift 1day Tue210317 Tue210317
7 Shuttering(8040)=40m,2ndlift 1day Wed220317 Wed220317
8 Concreting(8040)=40m,2ndlift 1day Thu230317 Thu230317
9 Deshuttering(8040)=40m,2ndlift 1day Fri240317 Fri240317
10 Shuttering(8060)=20m,1stlift 1day Sat250317 Sat250317
11 Concreting(8060)=20m,1stlift 1day Sun260317 Sun260317
12 Deshuttering(8060)=20m,1stlift 1day Mon270317 Mon270317
13 Shuttering(8060)=20m,2ndlift 1day Tue280317 Tue280317
14 Concreting(8060)=20m,2ndlift 1day Wed290317 Wed290317
15 Deshuttering(8060)=20m,2ndlift 1day Thu300317 Thu300317
16
17 PlasterWork 11days Mon200317 Thu300317
18 1stCoat 10days Tue210317 Thu300317
19 2ndCoat 11days Mon200317 Thu300317
20
21 PaintWork 8days Fri310317 Fri070417
22 1stCoat 3days Fri310317 Sun020417
23 2ndCoat 5days Mon030417 Fri070417

Task ProjectSummary InactiveMilestone ManualSummaryRollup Deadline

Project:RawadVillaSchedule Split ExternalTasks InactiveSummary ManualSummary Progress


Date:Mon200317 Milestone ExternalMilestone ManualTask Startonly
Summary InactiveTask Durationonly Finishonly

Page1

You might also like