ID Task Task Name Duration Start Finish Predecessors April 2022

Mode 29 31 02 04 06 08
1 Gujar Khan Branch 40 days Wed 01-03-23 Sun 09-04-23
2 Civil Works / Construction 13 days Wed 01-03-23 Mon 13-03-23
3 Construction of IT Room/ ATM/ Cash Counter / Safe Room 8 days Wed 01-03-23 Wed 08-03-23
4 Plaster Work + Safe Room Work 4 days Thu 09-03-23 Sun 12-03-23 3
5 Construction Work Complete 1 day Mon 13-03-23 Mon 13-03-23 4
6 CME Works 8 days Tue 14-03-23 Tue 21-03-23
7 Electrical Pipes + AC Drain Piping 4 days Tue 14-03-23 Fri 17-03-23 2
8 Ceiling Work 4 days Sat 18-03-23 Tue 21-03-23 7
9 Plumbing Work 2 days Sat 18-03-23 Sun 19-03-23 7
10 Woodwork 8 days Wed 22-03-23 Wed 29-03-23
11 Cash Counter + Cabinets + Kitchen / Store + BM Partition 8 days Wed 22-03-23 Wed 29-03-23 6
12 Paint Work 8 days Thu 30-03-23 Thu 06-04-23
13 Wall Putty + Distemper 8 days Thu 30-03-23 Thu 06-04-23 10
14 Electrical Fittings + AC Fittings 3 days Fri 07-04-23 Sun 09-04-23
15 Electrical Fittings + AC Fittings 3 days Fri 07-04-23 Sun 09-04-23 12

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Simple Project Plan
Summary Manual Summary Rollup Progress
Date: Tue 28-02-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
2023 March 2023 April 2023
06 08 10 12 14 16 18 20 22 24 26 28 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 01 03 05 07 09 11 13 15 17 19 21 23

Construction of IT Room/ ATM/ Cash Counter / Safe Room


Plaster Work + Safe Room Work
Construction Work Complete

Electrical Pipes + AC Drain Piping


Ceiling Work
Plumbing Work

Cash Counter + Cabinets + Kitchen / Store + BM Partition

Wall Putty + Distemper

Electrical Fittings + AC Fittings

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Simple Project Plan
Summary Manual Summary Rollup Progress
Date: Tue 28-02-23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6