ID Task Task Name Duration Start Finish Predecessors Resource Names 28 Nov '21 05 Dec '21 12 Dec '21

Resource Names 28 Nov '21 05 Dec '21 12 Dec '21 19 Dec '21 26 Dec '21 02 Jan '22 09 Jan '22 16 Jan '22 23 Jan '22 30 Jan '22 06 Feb '22 13 Feb '22 20 Feb '22 27 Feb '22 06 Mar '22 13 Mar '22 20 Mar '22
Mode MTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT
0 Quis 14 Microsoft. Project 75 days Wed 01/12/21 Tue 15/03/22

1 Biaya Umum 75 days Wed 01/12/21 Tue 15/03/22 Rp3.750.000

2 Pekerjaan Persiapan 4 days Wed 01/12/21 Mon 06/12/21 Rp880.000

3 Pembersihan Lapangan 4 days Wed 01/12/21 Mon 06/12/21 Rp60.000 Rp60.000

4 Membuat Gudang/Los Kerja 2 days Tue 07/12/21 Wed 08/12/21 3 Rp640.000 Rp640.000

5 Bouplank dan Pengukurang 1 day Tue 07/12/21 Tue 07/12/21 3 Rp180.000 Rp180.000

6 Pekerjaan Pondasi 7 days Wed 01/12/21 Thu 09/12/21 Rp3.130.000

7 Menggali Tanah 6 days Tue 07/12/21 Tue 14/12/21 5SS Rp360.000 Rp360.000

8 Aanstamping 5 days Wed 08/12/21 Tue 14/12/21 7FS-5 days Rp350.000 Rp350.000

9 Pasangan Batu Kali 7 days Tue 14/12/21 Wed 22/12/21 8FS-1 day Rp2.240.000 Rp2.240.000

10 Timbunan Kembali 6 days Thu 23/12/21 Thu 30/12/21 9 Rp180.000 Rp180.000

11 Pekerjaan Beton 14 days Wed 01/12/21 Mon 20/12/21 Rp10.400.000

12 Merangkai Besi 3 days Thu 16/12/21 Mon 20/12/21 4FS+5 days Rp660.000 Rp660.000

13 Mengecor Sloof 5 days Thu 23/12/21 Wed 29/12/21 9;12 Rp2.600.000 Rp2.600.000

14 Mengecor Kolom 14 days Mon 03/01/22 Thu 20/01/22 13FS+2 days Rp4.280.000 Rp4.280.000

15 Mengecor Ring Balok 7 days Fri 21/01/22 Mon 31/01/22 14;17 Rp2.860.000 Rp2.860.000

16 Pekerjaan Dinding 14 days Wed 01/12/21 Mon 20/12/21 Rp8.760.000

17 Memasang Bata 14 days Thu 30/12/21 Tue 18/01/22 13 Rp6.160.000 Rp6.160.000

18 Plesteran 10 days Wed 19/01/22 Tue 01/02/22 17 Rp2.600.000 Rp2.600.000

19 Pekerjaan Atap 7 days Wed 01/12/21 Thu 09/12/21 Rp8.025.000

20 Kuda-Kuda 7 days Tue 01/02/22 Wed 09/02/22 15 Rp3.345.000 Rp3.345.000

21 Gording, Rusuk & Reng 4 days Thu 10/02/22 Tue 15/02/22 20 Rp2.290.000 Rp2.290.000

22 Seng dan Talang 4 days Wed 16/02/22 Mon 21/02/22 21 Rp2.390.000 Rp2.390.000

23 Pekerjaan Plafon 3 days Wed 01/12/21 Fri 03/12/21 Rp1.850.000

24 Memasang Rangka 3 days Tue 22/02/22 Thu 24/02/22 22 Rp1.040.000 Rp1.040.000

25 Memasang Penutup Triplek 3 days Thu 24/02/22 Mon 28/02/22 24FS-1 day Rp810.000 Rp810.000

26 Pekerjaan Lantai 7 days Wed 01/12/21 Thu 09/12/21 Rp3.370.000

27 Timbunan Lantai 3 days Fri 31/12/21 Tue 04/01/22 10 Rp290.000 Rp290.000

28 Keramik 7 days Tue 01/03/22 Wed 09/03/22 17;25 Rp3.080.000 Rp3.080.000

29 Pekerjaan Cat 4 days Wed 01/12/21 Mon 06/12/21 Rp7.005.000

30 Mengecat Dinding 4 days Wed 02/02/22 Mon 07/02/22 18;31 Rp6.695.000 Rp6.695.000

31 Mengecat Plafon 4 days Thu 10/03/22 Tue 15/03/22 25;28 Rp310.000 Rp310.000

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Quis 14 Microsoft. Pro
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Fri 10/06/22
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress