NSC LIFT CPM BASELINE

ID Task Name Duration Cost Start Finish Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M M J S N J M M J S N J M M J S N J M M J S N J M M
1 SISTEM LIF UNTUK MENAIK TARAF RUMAH SERI KENANGAN BEDONG, 919 days RM 843,000.00 Wed 6/1/22 Sun 12/7/25
KEDAH
2 Letter Award (LA) 0 days RM 0.00 Wed 6/1/22 Wed 6/1/22 6/1
3 Site Possession 0 days RM 0.00 Mon 6/20/22 Mon 6/20/22 6/20
4 PRELIMINARIES 905 days RM 47,500.00 Tue 6/21/22 Sun 12/7/25
5 Insurances 30 days RM 9,500.00 Mon 7/11/22 Fri 8/19/22
6 Workmen's Compesation 30 days RM 5,000.00 Mon 7/11/22 Fri 8/19/22
7 Contractor All Risk's 30 days RM 4,500.00 Mon 7/11/22 Fri 8/19/22
8 Management Cost 894 days RM 13,500.00 Tue 6/21/22 Fri 11/21/25
9 Accommodation 894 days RM 8,000.00 Tue 6/21/22 Fri 11/21/25
52 Transportation 894 days RM 5,000.00 Tue 6/21/22 Fri 11/21/25
95 Miscellaneous 894 days RM 500.00 Tue 6/21/22 Fri 11/21/25
138 Preparing of ten (10) copies of Contract Document( Hardcover 30 days RM 5,000.00 Mon 8/22/22 Fri 9/30/22
Binding)
139 Preparing of six (6) copies shop drawing and samples as 45 days RM 7,500.00 Fri 10/21/22 Thu 12/22/22
specification
140 Shop Drawing 45 days RM 7,500.00 Fri 10/21/22 Thu 12/22/22
141 Preparation of Shop Drawing & Submission for SO Approval 30 days RM 7,000.00 Fri 10/21/22 Thu 12/1/22

142 Approval of Shop Drawing 0 days RM 0.00 Thu 12/1/22 Thu 12/1/22 12/1
143 Submission of 6 copies of approval drawing 1 day RM 500.00 Thu 12/22/22 Thu 12/22/22

144 Material Approval 30 days RM 0.00 Fri 10/21/22 Thu 12/1/22


145 Preparation of catalogue, sample board & material approval 30 days RM 0.00 Fri 10/21/22 Thu 12/1/22
form
146 Approval of material by SO 0 days RM 0.00 Thu 12/1/22 Thu 12/1/22 12/1
147 Pratical Training 1 day RM 800.00 Fri 12/2/22 Fri 12/2/22
148 Preparing of five (5) copies As Built Drawing, Maintenance and 14 days RM 4,000.00 Mon 6/10/24 Thu 6/27/24
Operations Manuals and otjer manuals necessary for the
maintenance

149 Testing Fees by respective authorit inclusive of submission fees 1 day RM 500.00 Fri 1/13/23 Fri 1/13/23

150 Comprehensive service and maintenance of lifts for 12 month 0 days RM 3,200.00 Sun 12/7/25 Sun 12/7/25 12/7
after handing ove
151 Signange and notices 1 day RM 1,500.00 Tue 10/10/23 Tue 10/10/23
152 Operation Instruction and Repair Manual 14 days RM 500.00 Mon 7/1/24 Thu 7/18/24

153 Performance Witness Testing 1 day RM 1,500.00 Wed 9/11/24 Wed 9/11/24
154 LIFT TWO (2) UNIT 581 days RM 785,500.00 Tue 6/21/22 Tue 9/10/24
155 ORDER CONFIRMATION 298 days RM 5,900.00 Tue 6/21/22 Thu 8/10/23
156 Purchase Order 1 day RM 5,900.00 Tue 6/21/22 Tue 6/21/22

Task Project Summary Manual Task Start-only Deadline

Project: BASELINE CPM SISTEM Split Inactive Task Duration-only Finish-only Progress
Date: Tue 8/23/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
NSC LIFT CPM BASELINE
ID Task Name Duration Cost Start Finish Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M M J S N J M M J S N J M M J S N J M M J S N J M M
157 Order confirmation 0 days RM 0.00 Thu 5/18/23 Thu 5/18/23 5/18
158 Manufacturing 60 days RM 0.00 Fri 5/19/23 Thu 8/10/23
159 Delivery 48 days RM 628,000.00 Fri 8/11/23 Tue 10/17/23
160 Shipment to malaysia from china 30 days RM 0.00 Fri 8/11/23 Thu 9/21/23
161 Custom Clearance 14 days RM 0.00 Fri 9/22/23 Wed 10/11/23
162 Deliver to site 3 days RM 0.00 Thu 10/12/23 Mon 10/16/23
163 Materials On Site 1 day RM 628,000.00 Tue 10/17/23 Tue 10/17/23
164 Lift Car(s) inclusive of all Panels with finishes and Attachments c/w 1 day RM 116,000.00 Tue 10/17/23 Tue 10/17/23
Fan and Car Locking Device as per specification

165 Landing Doors including Frames, Sills and all other attachments 1 day RM 32,000.00 Tue 10/17/23 Tue 10/17/23

166 Hall Lantern(s), Position Indicators, Call Buttons and all other 1 day RM 9,600.00 Tue 10/17/23 Tue 10/17/23
attachments
167 Traction Machine(s) c/w Sheaves, Regenerative Drives and plinth 1 day RM 88,000.00 Tue 10/17/23 Tue 10/17/23
(where applicable)
168 Governors and Ropes 1 day RM 24,000.00 Tue 10/17/23 Tue 10/17/23
169 Controllers and shaft information 1 day RM 104,000.00 Tue 10/17/23 Tue 10/17/23
170 Traveling cables and its accessories 1 day RM 24,000.00 Tue 10/17/23 Tue 10/17/23
171 Electrical Switchboards c/w all necessary accessories 1 day RM 6,400.00 Tue 10/17/23 Tue 10/17/23

172 Cables and Wiring c/w Hot Dipped Galvanized Trunking 1 day RM 12,800.00 Tue 10/17/23 Tue 10/17/23

173 Intercom System and connection to lift master unit control panel in 1 day RM 800.00 Tue 10/17/23 Tue 10/17/23
the building c/w all atachments. The master unit shall include a
microphone & speaker with amplifier, buzzer, selector switches and
indicating lights.

174 Central Supervisory Panel 1 day RM 8,000.00 Tue 10/17/23 Tue 10/17/23
175 Batteries with Trickle Chargers 1 day RM 960.00 Tue 10/17/23 Tue 10/17/23
176 Car Buffers 1 day RM 16,000.00 Tue 10/17/23 Tue 10/17/23
177 Counterweight Buffers 1 day RM 12,800.00 Tue 10/17/23 Tue 10/17/23
178 Counterweights 1 day RM 16,000.00 Tue 10/17/23 Tue 10/17/23
179 Guide rails and attachments c/w trimmer beam (All brackets shall 1 day RM 88,000.00 Tue 10/17/23 Tue 10/17/23
be factory fabricated type and any welding work at site shall be
done by the certified/competent welder)

180 Traction Ropes 1 day RM 40,000.00 Tue 10/17/23 Tue 10/17/23


181 Automatic Rescue Device (ARD) cw all attachments 1 day RM 12,800.00 Tue 10/17/23 Tue 10/17/23

182 Emergency Battery Operated Power Supply (EBOPS) 1 day RM 4,000.00 Tue 10/17/23 Tue 10/17/23

183 Lightning and Surge Protectors 1 day RM 960.00 Tue 10/17/23 Tue 10/17/23
Task Project Summary Manual Task Start-only Deadline

Project: BASELINE CPM SISTEM Split Inactive Task Duration-only Finish-only Progress
Date: Tue 8/23/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
NSC LIFT CPM BASELINE
ID Task Name Duration Cost Start Finish Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M M J S N J M M J S N J M M J S N J M M J S N J M M
184 Voice Synthesizer 1 day RM 480.00 Tue 10/17/23 Tue 10/17/23
185 Cat Ladder Inside Lift Pit 1 day RM 960.00 Tue 10/17/23 Tue 10/17/23
186 Lighting along lift shafts as per JKKP requirement 1 day RM 1,440.00 Tue 10/17/23 Tue 10/17/23
187 Additional plinth for oil buffer or other lift component, necessary 1 day RM 3,600.00 Tue 10/17/23 Tue 10/17/23
for the complete installation and complying with authority's
requirement.(if required)

188 Rope Snatch switch 1 day RM 800.00 Tue 10/17/23 Tue 10/17/23
189 Ascending Car Overspeed Protection 1 day RM 1,200.00 Tue 10/17/23 Tue 10/17/23
190 Unintended Car Movement Protection (UCMP) 1 day RM 2,400.00 Tue 10/17/23 Tue 10/17/23
191 Materials deliver on Site 0 days RM 0.00 Tue 10/17/23 Tue 10/17/23 10/17
192 Lift Shaft Acceptance 2 days RM 0.00 Wed 9/27/23 Thu 9/28/23
193 Handover Lift Shaft By Maincon 1 day RM 0.00 Wed 9/27/23 Wed 9/27/23
194 Lift Shaft Join Inspection 1 day RM 0.00 Thu 9/28/23 Thu 9/28/23
195 Lift Shaft Acceptance By NSC Lift 0 days RM 0.00 Thu 9/28/23 Thu 9/28/23 9/28
196 Lift Installation 52 days RM 141,550.00 Wed 10/18/23 Thu 12/28/23
197 Installation Works (Hoistway) 15 days RM 91,300.00 Wed 10/18/23 Tue 11/7/23
198 Scaffolding Erection 3 days RM 20,000.00 Wed 10/18/23 Fri 10/20/23
199 Erection of Templates 3 days RM 300.00 Mon 10/23/23 Wed 10/25/23
200 Plumb set out works 1 day RM 3,000.00 Thu 10/26/23 Thu 10/26/23
201 Install Guide Rail Bracket and Guide Rail 2 days RM 30,000.00 Fri 10/27/23 Mon 10/30/23
202 Traveling Cable c/w accessories 2 days RM 30,000.00 Tue 10/31/23 Wed 11/1/23
203 Counterweight Frame and Counterweight 2 days RM 5,000.00 Thu 11/2/23 Fri 11/3/23
204 Traction Ropes 2 days RM 3,000.00 Mon 11/6/23 Tue 11/7/23
205 Installation Works (Lift Lobby) 5 days RM 13,000.00 Wed 11/8/23 Tue 11/14/23
206 Install Landing Door Frame and Door 4 days RM 12,000.00 Wed 11/8/23 Mon 11/13/23
207 Hall Lantern (s), Position Indicators, Call Buttons 1 day RM 1,000.00 Tue 11/14/23 Tue 11/14/23
208 Installation Works (Motor Room) 16 days RM 17,000.00 Wed 11/15/23 Wed 12/6/23
209 Construct New Plinth/Foundation/Base Plate 3 days RM 2,500.00 Wed 11/15/23 Fri 11/17/23
210 Install Traction Motor Equipment and Wiring 2 days RM 5,000.00 Mon 11/20/23 Tue 11/21/23
211 Governors and Ropes 2 days RM 2,000.00 Wed 11/22/23 Thu 11/23/23
212 Controller and shaft information 2 days RM 2,000.00 Fri 11/24/23 Mon 11/27/23
213 Lift Switchboard 1 day RM 3,500.00 Tue 11/28/23 Tue 11/28/23
214 Intercom System 1 day RM 500.00 Wed 11/29/23 Wed 11/29/23
215 Batteries with Trickle Charges 1 day RM 300.00 Thu 11/30/23 Thu 11/30/23
216 Automatic Rescue Device 1 day RM 300.00 Fri 12/1/23 Fri 12/1/23
217 Emegency Battery Operated Power Supply (EBOPS) 1 day RM 300.00 Mon 12/4/23 Mon 12/4/23
218 Unintended Car Movement Protection (UCMP) 1 day RM 300.00 Tue 12/5/23 Tue 12/5/23
219 Ascending Car Overspeed Protection (ACOP) 1 day RM 300.00 Wed 12/6/23 Wed 12/6/23
220 Installation Works (Lift Pit) 5 days RM 9,350.00 Thu 12/7/23 Wed 12/13/23

Task Project Summary Manual Task Start-only Deadline

Project: BASELINE CPM SISTEM Split Inactive Task Duration-only Finish-only Progress
Date: Tue 8/23/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
NSC LIFT CPM BASELINE
ID Task Name Duration Cost Start Finish Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M M J S N J M M J S N J M M J S N J M M J S N J M M
221 New Cat Ladder 1 day RM 1,200.00 Thu 12/7/23 Thu 12/7/23
222 Car Buffer and Counter Weight Buffer 1 day RM 7,500.00 Fri 12/8/23 Fri 12/8/23
223 Clean up the lift walls and floor 2 days RM 150.00 Mon 12/11/23 Tue 12/12/23
224 Non slip epoxy paint glossy finish for the lift pit floor slab and 1 day RM 500.00 Wed 12/13/23 Wed 12/13/23
wall
225 Installation Works (Lift Car) 11 days RM 10,900.00 Thu 12/14/23 Thu 12/28/23
226 Lift Car Assembling 4 days RM 5,000.00 Thu 12/14/23 Tue 12/19/23
227 Department's/Client Logo 1 day RM 2,000.00 Wed 12/20/23 Wed 12/20/23
228 Car Door Locking Device 1 day RM 300.00 Thu 12/21/23 Thu 12/21/23
229 COP for the diabled 1 day RM 300.00 Fri 12/22/23 Fri 12/22/23
230 Handrail at side and rear lift enclosure 1 day RM 1,500.00 Mon 12/25/23 Mon 12/25/23
231 Lift interior Finishes 2 days RM 1,500.00 Tue 12/26/23 Wed 12/27/23
232 Voice Synthesizer 1 day RM 300.00 Thu 12/28/23 Thu 12/28/23
233 OTHER WORKS 10 days RM 6,300.00 Fri 12/29/23 Thu 1/11/24
234 Coring, Hacking, Punching holes, making good and other related jobs 3 days RM 2,300.00 Fri 12/29/23 Tue 1/2/24
235 Making good and filling concrete or plastering between landing door 7 days RM 4,000.00 Wed 1/3/24 Thu 1/11/24
and structural opening including door jamb, sill and head
236 TESTING, ADJUSTING, BALANCING & COMMISSIONING 23 days RM 3,750.00 Fri 8/9/24 Tue 9/10/24
237 Complete Testing and Commisioning (Slow Speed and High Speed)
21 days RM 2,000.00 Fri 8/9/24 Fri 9/6/24
238 Reprogramme, interfacing for system 1 day RM 875.00 Mon 9/9/24 Mon 9/9/24
239 Intergration with existing system, Firefighting etc 1 day RM 875.00 Tue 9/10/24 Tue 9/10/24
240 JKKP Inspection 0 days RM 0.00 Tue 9/10/24 Tue 9/10/24 9/10
241 PMA Approval 0 days RM 0.00 Tue 9/10/24 Tue 9/10/24 9/10
242 PRE HANDING OVER (UPON PYHSICAL COMPLETE) 3 days RM 10,000.00 Thu 6/27/24 Mon 7/1/24
243 Pre Hand Over Inspection 1 day RM 0.00 Thu 6/27/24 Thu 6/27/24
244 Pratical Training 1 day RM 6,000.00 Fri 6/28/24 Fri 6/28/24
245 Handover Documents 1 day RM 4,000.00 Mon 7/1/24 Mon 7/1/24
246 HAND OVER TO USER 0 days RM 0.00 Mon 7/1/24 Mon 7/1/24 7/1
247 FINISH 0 days RM 0.00 Sun 12/7/25 Sun 12/7/25 12/7
248 DEFECT LIABILITY PERIOD (DLP) 0 days RM 0.00 Sat 7/12/25 Sat 7/12/25 7/12
249 Montly Maintenance & Servicing 0 days RM 0.00 Sat 7/12/25 Sat 7/12/25 7/12

Task Project Summary Manual Task Start-only Deadline

Project: BASELINE CPM SISTEM Split Inactive Task Duration-only Finish-only Progress
Date: Tue 8/23/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress