Professional Documents
Culture Documents
ID Task Name Duration Start Finish Schedule % Actual % Ahd/Dly Cost Planning cost
(+/-)
1 KERJA MEMBINA & MELABUH TUKUN 122 days Sat 1/6/19 Mon 21/10/19 69.19 63.21 -5.98 RM397,435.60 RM274,985.69
2 TIRUAN
Mula 0 days Sat 1/6/19 Sat 1/6/19 0 0 0 RM0.00 RM0.00
3 Mengenalpasti Tapak & Pemeriksaan 7 days Sat 1/6/19 Mon 10/6/19 100 100 0 RM0.00 RM0.00
4 Kerja Awalan 118 days Mon 3/6/19 Thu 17/10/19 72.97 59.46 -13.51 RM10,650.60 RM7,771.74
5 Mobilasi 14 days Mon 3/6/19 Tue 18/6/19 100 100 0 RM3,000.00 RM3,000.00
6 Insuran Kerja 14 days Fri 14/6/19 Sat 29/6/19 100 100 0 RM5,000.00 RM5,000.00
7 1st Aid Box 2 days Fri 14/6/19 Sat 15/6/19 100 100 0 RM150.60 RM150.60
8 Kelengkapan Keselamatan utk P.P 4 days Fri 14/6/19 Tue 18/6/19 100 100 0 RM1,700.00 RM1,700.00
9 Papantanda Projek 14 days Fri 14/6/19 Sat 29/6/19 100 100 0 RM500.00 RM500.00
10 Lain-lain Kerja Permulaan 100 days Mon 24/6/19 Thu 17/10/19 60 40 -20 RM300.00 RM180.00
11 Tukun Tiruan 92 days Sat 6/7/19 Mon 21/10/19 66.03 64.4 -1.63 RM386,785.00 RM255,394.14
12 Mula 0 days Sat 6/7/19 Sat 6/7/19 0 0 0 RM0.00 RM0.00
13 Jenis Aktiviti dan Pengangkutan 92 days Sat 6/7/19 Mon 21/10/19 66.03 64.4 -1.63 RM386,785.00 RM255,394.14
14 untuk
UjianTukun
terhadap Bahan Utama 60 days Sat 6/7/19 Sat 14/9/19 81.46 61 -20.46 RM12,600.00 RM10,263.96
15 Struktur
Penyediaan Acuan dan Besi 30 days Mon 22/7/19 Sat 24/8/19 100 90 -10 RM257,985.00 RM257,985.00
16 Tetulang
Cat Kalis Air untuk Penandaan 21 days Mon 29/7/19 Wed 21/8/19 100 87 -13 RM2,700.00 RM2,700.00
17 Penyediaan Barge & Tugbot untuk 21 days Mon 5/8/19 Wed 28/8/19 100 99 -1 RM80,000.00 RM80,000.00
18 penghantaran
Krane untuk Mengangkat Tukun 21 days Mon 5/8/19 Wed 28/8/19 100 70 -30 RM20,000.00 RM20,000.00
19 Penyediaan Life Jacket, Loud 21 days Mon 12/8/19 Wed 4/9/19 85.71 75 -10.71 RM1,500.00 RM1,285.65
20 Hailer, Walkie
Bekalan talkie kerja
kelengkapan 21 days Thu 29/8/19 Sat 21/9/19 14.29 30 15.71 RM4,000.00 RM571.60
21 Bot Laju untuk Penyelam dan P.P 21 days Mon 9/9/19 Wed 2/10/19 0 14 14 RM4,000.00 RM0.00
22 Membekal Scuba Diver untuk 21 days Mon 16/9/19 Wed 9/10/19 0 50 50 RM4,000.00 RM0.00
23 Pemeriksaan Tukun
T&C 10 days Thu 10/10/19 Mon 21/10/19 0 60 60 RM0.00 RM0.00
24 Finish 0 days Mon Mon 21/10/19 0 0 0 RM0.00 RM0.00
21/10/19
Critical Finish-only Manual Summary
Critical Split Duration-only Project Summary
Critical Progress Baseline External Tasks
Task Baseline Split External Milestone
Split Baseline Milestone Inactive Task
Task Progress Milestone Inactive Milestone
Manual Task Summary Progress Inactive Summary
Start-only Summary Deadline
Page 1
CPM_tukun tiruan rompin (MASTER)rev00
Actual Cost Weightage % Decimal % 21 May
% Complete 10/3 14/7
RM350,777.10 100 63% 63.21
RM0.00 0 100% 0 1/6
RM0.00 0 0% 0 21/10
Page 2